MahaRERA Property Intelligence · Pune

SHREE RAM APARTMENTS

P52100014267 · NEHRU NAGAR PIMPRI CHINCHWAD · promoter Shree Chaitanya Developers

Certificate SignedDue 31 Mar 2021

Delivery & Registration

MahaRERA registrationP52100014267
Registered on17 Nov 2017
Promoter-declared completion31 Mar 2021
Current statusCertificate Signed
Against todayabout 64 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Shree Chaitanya Developers is the promoter of record on 77 projects, of which 13 carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+5.

BuildingWingsFloorsDeclared completion
SHREE RAM APARTMENTS1G+531 Dec 2020

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Location, Land & Connectivity

Located at NEHRU NAGAR PIMPRI CHINCHWAD, STADIUM ROAD, Haveli, Pune, 411018. Per the filed land record, the plot is bounded to the north by CTS 6590, to the south by CTS NO 6583, to the east by CTS NO 6584- 9 AND 6584 -2 and to the west by 12 M WIDE ROAD. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~99 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Hinjewadi Rajiv Gandhi IT Park99 km
Baner–Balewadi belt104 km
Pune Int'l Airport (Lohegaon)114 km
Pune Junction / city centre114 km
Kharadi / EON IT Park117 km
Magarpatta / Hadapsar IT119 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Shree Chaitanya Developers is the promoter on 3 MahaRERA-registered projects, with none currently carrying a regulator flag — a reassuring wider track record (matched on the promoter name in the register; it doesn't guarantee this specific project, but a clean portfolio is a good sign).

Other RERA-registered projects in Pimpri

Stella Apex
possession by Oct 2026 · Vastuspace Realty Promoters AND Develope
Dharampal Corporate Avenue
possession by Dec 2026 · Surender Dharampal Agarwal
Pristine Palazzo
possession by Dec 2026 · Kanha Developers
Skylish Vaastuu
possession by May 2027 · Skylish Bluediamond Innfrracon
Santoshi Mata Complex
possession by Aug 2027 · Njhb Properties
Mahindra Nestalgia
possession by Aug 2027 · Mahindra Bloomdale Developers Limited

Major developers building in Pimpri

Other RERA-registered projects in Pune

Shree RAM Icon
possession by Dec 2029 · Takawale Satav Associates
Shree RAM Plaza
declared completion Oct 2024 · M/S Shreeram Builders
Shree RAM Residency
possession by Dec 2027 · Shree RAM Developer
Shree Residency
declared completion Dec 2023 · Delta Buildcon
Shree Residency Phase A
declared completion Oct 2020 · UK Construction
Shree Royal
declared completion Jun 2018 · Shree Parshwa Construction

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026