MahaRERA · the public record
VTP Beaumonde Building T2
Manjari · ARHUM ERECTORS PRIVATE LIMITED
Know the project.
Then choose your home.
The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.
The record · free to read
Registration read 12 Jul 2026Progress & dates
The timeline on file.
Available record
No construction trend to plot.
The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.
declared completion
30 Jun 2025
The registered date and a construction update answer different questions. Neither is a confirmation of possession.
MahaRERA registration · read 12 Jul 2026
From another project
See the report before you buy.
A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.
Read a sample report ↗The source record
The details behind the headline.
MahaRERA · P52100025232
Delivery and registration
When is the project declared for completion?
VTP Beaumonde Building T2 is registered with MahaRERA as P52100025232 and the promoter has declared completion for 30 Jun 2025.
30 Jun 2025
declared completion
15months past
against the declared date
The completion date and status as they stand on the MahaRERA registration record.
Source · MahaRERA project registration · read 12 Jul 2026
| MahaRERA registration | P52100025232 |
| Registered on | 23 Mar 2020 |
| Promoter-declared completion | 30 Jun 2025 |
| Current status | Certificate Signed |
| Against today | about 15 months past the declared date |
Approvals and compliance
What compliance filings are on record?
MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for VTP Beaumonde Building T2 record 22 quarterly progress reports since registration.
22quarterly filings
Entries as they appear on MahaRERA's own lists and the project's progress filing.
Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026
- Current QPR default — the promoter has stopped filing the mandatory quarterly progress report (FY 2025-2026).
Promoter record
What else is this promoter on record for?
Arhum Erectors is the promoter of record on 48 projects registered with MahaRERA, 9 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).
48projects
registered with MahaRERA
9flagged
by MahaRERA
Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.
Source · MahaRERA register, all projects · read 12 Jul 2026
What the filings record, home by home
Read from MahaRERA on 17 September 2026
MahaRERA publishes, home by home, what this promoter filed: which homes are sold and which are not, the RERA carpet area of each, and for the sold ones the registered agreement value — the consideration filed for that specific home. On this project 266 homes carry one, and 4 of the 270 are recorded unsold.
A filed consideration is what was registered for one home. It is not a valuation, and MahaRERA does not publish the date of any of these agreements — read a range as a spread, not as a trend. An unsold row means no sale had been filed for it when we looked, which is a filing state, not a promise that the home is available to you today. Only one observation of this ledger so far: no change can be reported yet.
In VTP Beaumonde Building T2, 0 of the 4 unsold homes have agreements filed on their own stack. The Price Comparison Report gives each of them its own row — the filed agreements behind that stack listed in full, the government reckoner value the promoter filed against it, and whether it is mortgaged to a lender while still on the unsold list. Built from the filing itself, sent by email.
Buildings & Wings
The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+29.
| Building | Wings | Floors | Declared completion |
|---|---|---|---|
| Building T2 | 1 | G+29 | - |
Legal and disputes
What disputes are disclosed?
4 complaints are on the MahaRERA record for VTP Beaumonde Building T2, with orders passed in 3 of them.
4complaints
3with an order
Counts as disclosed in the project record.
Source · MahaRERA project disclosures · read 12 Jul 2026
| Complaint no. | Filed | Parties | Status |
|---|---|---|---|
| CC12501517 | 06/05/2025 | Naresh Poshayya Kottamidde vs ARHUM ERECTORS PRIVATE LIMITED | order passed |
| CC12501542 | 09/05/2025 | Pradeep Kumar Sahoo vs ARHUM ERECTORS PRIVATE LIMITED | order passed |
| CC12504331 | 07/12/2025 | Anurag Vishwakarma vs ARHUM ERECTORS PRIVATE LIMITED | order passed |
| CC12504655 | 28/12/2025 | Anish Haridass vs ARHUM ERECTORS PRIVATE LIMITED | pending / no order on file |
Location, Land & Connectivity
Located at Manjari, Manjari, Haveli, Pune, 412307. Per the filed land record, the plot is bounded to the north by Building T1, to the south by Driveway and compoundwall, to the east by Driveway and compound wall and to the west by Driveway and open space. These are the boundaries as recorded in the filed land record.