Bangalore/Project record

K-RERA · the public record

CASAGRAND ZAIDEN

Bengaluru South · CASA GRANDE GARDEN CITY BUILDERS

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

65%construction reportedQ1 2026 filing
0units not bookedof 286 · Q1 2026 filing
22 Mar 2026declared completionK-RERA registration · read 20 Sep 2026

The record · free to read

Registration read 20 Sep 2026

Progress & dates

The timeline on file.

Promoter-reported construction

K-RERA quarterly filings · Q3 2025 to Q1 2026

declared completion

22 Mar 2026

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

K-RERA registration · read 20 Sep 2026

Inventory & scale

What this registration contains.

3BHK+3T
93
3BHK+2T
56
2BHK+2T
137

Filed categories, unchanged · K-RERA registration · read 20 Sep 2026

The whole registration

3.7registered acres

77.5registered units per acre

The average covers the registered land and all registered unit types. It does not describe the space, outlook or surroundings of an individual home.

From another project · Prestige Park Grove

A larger advertised area. Almost the same carpet area.

In Tower 14, E4 has 141 sq ft more saleable area than E2. Its carpet area is only 0.46 sq m larger. The report puts the two layouts side by side.

This illustrates the report format. These findings concern the named sample, not this project.

Read the sample report ↗
Prestige Park Grove · Tower 14 comparison · approved sample report
Prestige Park Grove · Tower 14 comparison · approved sample report

The source record

The details behind the headline.

K-RERA · PRM/KA/RERA/1251/310/PR/120423/005862

This project, on the record

The comparable facts of this project, from its own RERA registration record. Each context percentile names its exact comparison set, drawn from Quietlist’s full register store. The paid report adds drawing-read rows to this same table — what the filed plans show about the site, its edges and the unit layouts.

On the register

Declared completion22 March 2026
Land area14,928 sq m (3.7 acres)
Homes registered286
Tower/wing entries3
Unit mix93 × 3BHK+3T, 56 × 3BHK+2T, 137 × 2BHK+2T

In context

Density77.5 homes per acre
Density in context51st percentile of 787 Bengaluru South projects (median 77.3)

Values as crawled from the official K-RERA record; context percentiles name their comparison population.

Official Registry Facts

Official project scale

RERA filing

Registration-form facts from the K-RERA detail page: use these to sanity-check the builder brochure, parking allotment, and sanctioned-plan references before relying on plan-extracted approximations.

DisclosureOfficial valueWhy it matters
Registered units286Total inventory registered with K-RERA.
Official carpet area24,206 sqmRegulator-disclosed project-level carpet area, not vision-derived room sums.
Official built-up area45,592 sqmUseful scale context when comparing density and project cost.
Registered land area14,928 sqmThe land area attached to this K-RERA registration.
Sanctioned FAR/FSI2.25Higher FAR generally means a denser vertical build, subject to site layout and open-space design.
Registered tower/wing entries3Official tower/wing count in the K-RERA detail page.
Parking total (reconciled)286Separate filed counts; these categories may overlap and are not added together.
Covered-parking field287Separate filed counts; these categories may overlap and are not added together.
Open-parking field29Separate filed counts; these categories may overlap and are not added together.
Garage field0Separate filed counts; these categories may overlap and are not added together.
Approved plan numberPRJ/14724/22-23INUse this to match the sanctioned drawing set shown by the builder.
Plan approval date21-03-2023
Project start date07-04-2023

Official inventory & towers

RERA filing

K-RERA registration tables showing the project mix and tower/wing scale. Use this to sanity-check sales claims such as "only large homes", "low density", or "plenty of parking" against the filed inventory.

Registered inventory mix

TypeUnitsShareOfficial carpet area
3BHK+3T9333%9,739 sqm
3BHK+2T5620%4,927 sqm
2BHK+2T13748%9,539 sqm

Registered tower / wing summary

Tower/wingFloorsUnitsParkingHeight
Tower A9818131.5 m
Tower B9959531.5 m
Tower C911011030.9 m

Official unit register

RERA filing

K-RERA detail-page flat rows: exact unit numbers, official carpet area, UDS, and parking lots. 286 official flat/unit rows, matching the 286 registered units disclosed above. Use this as a checklist against the specific flat number in your cost sheet and draft agreement.

By unit type

Unit typeRowsCarpet areaUDSParking lots
2BHK+2T13769.4-72.3 sqm44.0-45.5 sqm137
3BHK+3T9397.7-112.3 sqm59.2-67.5 sqm93
3BHK+2T5687.9-88.0 sqm53.5-53.8 sqm56

By tower / wing

Tower/wingRowsCarpet areaUDSParking lots
Tower C11069.4-112.3 sqm44.0-67.5 sqm110
Tower B9569.4-101.7 sqm44.0-61.2 sqm95
Tower A8188.0-101.7 sqm53.5-61.7 sqm81
Show sample official unit rows
UnitTowerFloorTypeCarpetUDSParking
A-101Tower A13BHK+3T101.7 sqm61.2 sqm1
A-102Tower A13BHK+3T101.7 sqm61.1 sqm1
A-103Tower A13BHK+3T101.7 sqm61.1 sqm1
A-104Tower A13BHK+3T101.7 sqm61.1 sqm1
A-105Tower A13BHK+3T101.7 sqm61.7 sqm1
A-106Tower A13BHK+2T88.0 sqm53.7 sqm1

Legal, Approvals & Project Team

Litigation & compliance

RERA filing

No litigation declared on this project's K-RERA filing.

⚠ 5 of 31 compliance document slots are filed as under process / not yet usable: Urban Land Ceiling, Change of Land Use, District Magistrate, Conversion Certificate under section 95 of the KLR Act 1964, JD AFFIDAVIT CUM DECLARATION.

1 additional compliance slots are filed as Not Applicable.

No completion certificate (OC) on file yet — project has not been declared complete.

Named utility/regulatory approvals

Electricity (BESCOM/ESCOM)✓ On file (Electricity Permission Letter)
Water & sewage (BWSSB/KWSSB)✓ On file (Water Permission Letter)
Fire NOCNot found in catalog
Pollution control (KSPCB)Not found in catalog
Environmental clearanceNot found in catalog
Airport Authority height clearance✓ On file (Airport Authority of India)

"Not found in catalog" can mean the approval genuinely isn't on file yet, or that it doesn't apply to this project (K-RERA doesn't tell us which). Ask the builder directly for any marked not found before relying on it.

K-RERA complaint orders (3 complaints against a project of this name on K-RERA's orders register)

PartiesRelief soughtDisposalOrder date
ABHIJIT CHATTERJEE vs CASA GRANDE GARDEN CITY BUILDERS PVT LTDNoneAUTHORITY28/03/2024
TIRTH NATH JHA vs CASA GRANDE GARDEN CITY BUILDERS PVT. LTD.,Please help me to get refund of booking amount of Rs. 1 lakh.AUTHORITY14/02/2024
Mrs Rashmi Yatish Amin vs Casagrand Zaidena. Direct the Respondent to cancel the allotment and refund the entire amount of Rs.9,34,006/- with applicable interest. b. Grant costs of this proceedings. c. Impose a penalty on the RespondentAUTHORITY10/03/2026

⚠ Matched by PROJECT NAME (the orders register carries no registration number) — confirm the respondent above is this project's builder before relying on it.

Complaints on this project's K-RERA page (8 complaints listed against this promoter)

ComplaintSubject (as filed)ProjectStatus
CMP/200816/0006368
16-08-2020
Delay in Handover of Apartment C204 - CASAGRAND ROYCE ProjectCasagrand Royce (another project by this promoter)DISPOSED AUTHORITY BENCH4
CMP/211201/0008654
01-12-2021
DELAYED COMPLETION BREACH OF TRUST FINANCIAL LOSSES SUFFERED BY COMPLAINANTSCasagrand Royce (another project by this promoter)DISPOSED AUTHORITY BENCH4
CMP/220321/0009178
21-03-2022
Builder refuses to pay interset for the amount refunded after 4 yearsCasagrand Royce (another project by this promoter)DISPOSED AUTHORITY BENCH5
CMP/220616/0009641
16-06-2022
Delay In hand over which was expected to be done by 9th of March 2022Casagrand Florella (another project by this promoter)DISPOSED AUTHORITY BENCH4
CMP/220706/0009722
06-07-2022
Builder not refunding the booking amount due to unavailability of the unitCasagrand Florella Phase 2 (another project by this promoter)DISPOSED AUTHORITY BENCH4
CMP/221104/0010175
04-11-2022
Builder not delivering the apartment flat C306 to date even after the expiry of the RERA Extended due date (15th July 2022) and denied to pay delay compensationCasa Grande Lorenza (another project by this promoter)DISPOSED AUTHORITY BENCH5
CMP/221107/0010222
07-11-2022
Builder not delivering the apartment flat C306 to date even after the expiry of the RERA Extended due date (15th July 2022) and denied to pay delay compensationCasa Grande Lorenza (another project by this promoter)DISPOSED AUTHORITY BENCH5
CMP/221221/0010496
21-12-2022
Builder not adhering to the agreed and adding new clause in the sale deedCasagrand Florella (another project by this promoter)DISPOSED AUTHORITY BENCH5

Listed on the project's own K-RERA detail page (registration-exact source). Rows on the promoter's other projects are track-record context — read the subject text, it is the complainant's own filed wording.

Statutory approval status

RERA filing

4 of 6 applicable approvals are on file; still outstanding: KSPCB- PCB (10 Acres to 125 Acres) and KSPCB- MOEF (Above 50 Acres). Environmental clearance and pollution-control clearance (KSPCB) is among them — a high-importance clearance, so confirm it has been granted (not just applied for) before you book.

4 further authority slots are marked not applicable by the regulator.

Authority / NOCStatusDateFile
Water supply and sewage boardApproved29-12-2022Thalaghatapura BWSSB NOC (1).pdf
KSPCB- PCB (10 Acres to 125 Acres)To Be Applied-View NOC
KSPCB- MOEF (Above 50 Acres)To Be Applied-View NOC
KPTCL- BESCOMApproved14-02-2023BESCOM NOC thalaghattapura (1).pdf
Fire and SafetyApproved14-03-2023Thalaghattapura Fire NOC (1).pdf
Airport Authority of IndiaApproved08-02-2023Thala AAI (1).pdf

Project team & certifications

RERA filing

K-RERA names 4 project professional/vendor rows across Chartered accountant, Engineer, Architect, Contractor. Use this to cross-check whose certificates, drawings, and contractor commitments support the filing; final reliance still belongs with your lawyer/technical reviewer.

RoleNameRegistration / licenceSinceLocality
Chartered accountantNARAYANA RAO M2279482014Bengaluru Urban, Karnataka - 560068
EngineerShivaraj G NaikBCC/B6-365-E1582013Bengaluru Urban, Karnataka - 560002
ArchitectDILIP NADIGCA/95/192462013Bengaluru Urban, Karnataka - 560025
ContractorCASA GRANDE GARDEN CITY BUILDERS PVT LTD-2015Bengaluru Urban, Karnataka - 560042

Builder track record

RERA filing

Casagrand has 20 other K-RERA-registered projects in our records — grouped across the several project-specific entities this developer registers under (e.g. this project is filed as “Casa Grande”) (average reported construction progress 39%). 11 are past their declared completion deadline with no completion certificate recorded — but because K-RERA publishes OCs inconsistently, a project that has actually been finished and handed over still shows up this way, so this overstates real delays, especially for a high-volume established builder.

Read this as a list to spot-check for a pattern of genuinely stalled projects, not as a delay rate — pull up a few of the builder’s other K-RERA registrations and check whether they’ve actually been delivered.

Financials & Construction Progress

Financial disclosures

RERA filing

Latest quarterly filing (2026-Q1): ₹0.49 Cr collected from buyers, ₹0.00 Cr withdrawn from the project's escrow account.

Construction progress55% → 65% (+10 pts)
Units sold/booked as registered286/286 (100%)
Buyer collections in available QPRs₹526.72 Cr
Escrow withdrawals in available QPRs₹3.90 Cr (0.01x collections)
  • 100% of registered units are shown as sold/booked, but no completion certificate is on file yet.
  • Construction progress moved from 55% to 65% across the filed QPR window.
  • The builder has drawn 0.01x of buyer collections from escrow (about 1% of the ₹527 Cr collected) — money is largely staying in the regulated escrow account rather than being pulled out ahead of spend, which is the safer direction. A ratio near or above 1.0 would be the one to scrutinise.

QPR figures are developer-filed quarterly disclosures. Collections and withdrawals are not a project valuation; they are a sanity check for whether sales, construction progress, and escrow draws appear directionally aligned.

Declared construction cost ÷ registered units averages to ₹36.6 lakhs per unit — the developer's own declared construction/development cost, not a sale price. K-RERA filings don't disclose what the builder is charging, so this can't tell you whether you're getting a fair deal — only you comparing your quoted price against comparable listings nearby can answer that.

RERA 70% project account is on file: ICICI Bank Ulsoor Branch IFSC Code : ICIC0003904 Pin Code : 560008. RERA requires 70% of buyer collections to sit in this separate, project-specific account, drawn only against certified construction milestones — confirm your payments are made to THIS account (not a general builder account) and that it appears on your allotment letter.

Location & Connectivity

The nearest major job hub is ~15 km away — a real but liveable commute to the nearest job hub — factor peak-hour traffic.

LandmarkStraight-line
Electronic City15 km
MG Road / city centre15 km
Bellandur–Marathahalli belt19 km
Outer Ring Road / Manyata22 km
Whitefield IT hub27 km
Kempegowda Int'l Airport42 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Built by Casa Grande. View Casa Grande's full track record →
Casa Grande has 20 projects registered in Bangalore, 3 past RERA deadline.

Other projects by this builder in Bangalore

Casagrand Flamingo
Past deadline · 68% built · 100% sold
Casagrand Meridian
Past deadline · 80% built · 100% sold
Casagrand Amor
On track · 40% built · 70% sold
Casagrand Estancia
On track · 5% built · 64% sold

Other RERA-registered projects in Talaghattapura

Major developers building in Talaghattapura

Figures are the developer's own quarterly disclosures on the Karnataka RERA register. "Built" is the highest construction % filed; "sold" is booked units over total. Not a claim about the developer's intent. Explore every project on our Bangalore project-health tool.

Own a unit in Casagrand Zaiden?

Sell directly to Quietlist's pre-screened buyer list — flat fee, no broker commission.

List your unit →

Last checked against the RERA register: 20 Sep 2026