LEGACY MIHIRA

Devanahalli · LEGACY GLOBAL PROJECTS

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

10%construction reportedQ1 2026 filing
31 Dec 2030declared completionK-RERA registration · read 20 Sep 2026

The record · free to read

Registration read 20 Sep 2026

Progress & dates

The timeline on file.

Promoter-reported construction

K-RERA quarterly filings · Q3 2025 to Q1 2026

declared completion

31 Dec 2030

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

K-RERA registration · read 20 Sep 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

K-RERA · PRM/KA/RERA/1250/303/PR/220725/007945

This project, on the record

The comparable facts of this project, from its own RERA registration record. Each context percentile names its exact comparison set, drawn from Quietlist’s full register store. The paid report adds drawing-read rows to this same table — what the filed plans show about the site, its edges and the unit layouts.

On the register

Declared completion31 December 2030

Values as crawled from the official K-RERA record; context percentiles name their comparison population.

Official Registry Facts

Official project scale

RERA filing

Registration-form facts from the K-RERA detail page: use these to sanity-check the builder brochure, parking allotment, and sanctioned-plan references before relying on plan-extracted approximations.

DisclosureOfficial valueWhy it matters
Approved plan numberSTRRPA/TP/LAO/40/2023-24/25-26Use this to match the sanctioned drawing set shown by the builder.
Plan approval date29-04-2025
Project start date01-07-2025

Legal, Approvals & Project Team

Litigation & compliance

RERA filing

No litigation declared on this project's K-RERA filing.

⚠ 2 of 22 compliance document slots are filed as under process / not yet usable: Proforma of Agreement for Sale, NOC from ESCOMs.

1 additional compliance slots are filed as Not Applicable.

No completion certificate (OC) on file yet — project has not been declared complete.

Named utility/regulatory approvals

Electricity (BESCOM/ESCOM)Not found in catalog
Water & sewage (BWSSB/KWSSB)✓ On file (NOC for Water)
Fire NOCNot found in catalog
Pollution control (KSPCB)Not found in catalog
Environmental clearanceNot found in catalog
Airport Authority height clearanceNot found in catalog

"Not found in catalog" can mean the approval genuinely isn't on file yet, or that it doesn't apply to this project (K-RERA doesn't tell us which). Ask the builder directly for any marked not found before relying on it.

Complaints on this project's K-RERA page (13 complaints listed against this promoter)

ComplaintSubject (as filed)ProjectStatus
CMP/200529/0005940
29-05-2020
Refusal to Honour Terms of Sale AgreementLegacy Vivienda (another project by this promoter)DISPOSED AUTHORITY BENCH5
CMP/201124/0007120
24-11-2020
Refund of Sale Consideration with Interest and CompensationLegacy Vivienda (another project by this promoter)DISPOSED AUTHORITY BENCH5
CMP/210309/0007771
09-03-2021
As per the complaint uploaded.Legacy Vivienda (another project by this promoter)DISPOSED AUTHORITY BENCH5
CMP/210309/0007772
09-03-2021
As per the complaint uploaded.Legacy Vivienda (another project by this promoter)DISPOSED AUTHORITY BENCH5
CMP/210309/0007773
09-03-2021
As mentioned in the complaint uploadedLegacy Vivienda (another project by this promoter)DISPOSED AUTHORITY BENCH5
CMP/210420/0007910
20-04-2021
As per mentioned in the Complaint in the previous page.Legacy Vivienda (another project by this promoter)DISPOSED AUTHORITY FULLBENCH
CMP/210420/0007912
20-04-2021
My Booking of Apartement-G-01 of M/S Legacy Salvador (Legacy Global Projects Pvt Ltd)Legacy Salvador (another project by this promoter)DISPOSED AUTHORITY BENCH4
CMP/210531/0007969
31-05-2021
As per the Complaint uploaded.Legacy Vivienda (another project by this promoter)DISPOSED AUTHORITY BENCH5

Listed on the project's own K-RERA detail page (registration-exact source). Rows on the promoter's other projects are track-record context — read the subject text, it is the complainant's own filed wording.

Statutory approval status

RERA filing

11 further authority slots are marked not applicable by the regulator.

Authority / NOCStatusDateFile

Project team & certifications

RERA filing

K-RERA names 2 project professional/vendor rows across Chartered accountant, Engineer. Use this to cross-check whose certificates, drawings, and contractor commitments support the filing; final reliance still belongs with your lawyer/technical reviewer.

RoleNameRegistration / licenceSinceLocality
Chartered accountantMahaveer Bhansali Jain2336692010Bengaluru Urban, Karnataka - 560010
EngineerB V SrihariAM-83042/11998Bengaluru Urban, Karnataka - 560010

Builder track record

RERA filing

Legacy Global has 12 other K-RERA-registered projects in our records (average reported construction progress 72%). 9 are past their declared completion deadline with no completion certificate recorded — but because K-RERA publishes OCs inconsistently, a project that has actually been finished and handed over still shows up this way, so this overstates real delays, especially for a high-volume established builder.

Read this as a list to spot-check for a pattern of genuinely stalled projects, not as a delay rate — pull up a few of the builder’s other K-RERA registrations and check whether they’ve actually been delivered.

Financials & Construction Progress

Financial disclosures

RERA filing

Latest quarterly filing (2026-Q1): ₹3.46 Cr collected from buyers, ₹0.00 Cr withdrawn from the project's escrow account.

Construction progress1% → 10% (+9 pts)
Buyer collections in available QPRs₹3.46 Cr
  • Construction progress moved from 1% to 10% across the filed QPR window.
  • The builder has drawn 0.00x of buyer collections from escrow (about 0% of the ₹3 Cr collected) — money is largely staying in the regulated escrow account rather than being pulled out ahead of spend, which is the safer direction. A ratio near or above 1.0 would be the one to scrutinise.

QPR figures are developer-filed quarterly disclosures. Collections and withdrawals are not a project valuation; they are a sanity check for whether sales, construction progress, and escrow draws appear directionally aligned.

The estimated cost above is the developer's declared construction cost only (K-RERA's own label: "Estimated Cost of Construction as certified by Engineer") — it excludes land cost, so it isn't comparable to the buyer-collection figures below or to a sale price.

RERA 70% project account is on file: KOTAK MAHINDRA BANK M.G.ROAD IFSC Code : KKBK0008066 Pin Code : 560001. RERA requires 70% of buyer collections to sit in this separate, project-specific account, drawn only against certified construction milestones — confirm your payments are made to THIS account (not a general builder account) and that it appears on your allotment letter.

Location & Connectivity

The nearest major job hub is ~27 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Kempegowda Int'l Airport9 km
Outer Ring Road / Manyata27 km
MG Road / city centre34 km
Whitefield IT hub35 km
Bellandur–Marathahalli belt38 km
Electronic City48 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Built by Legacy Global. View Legacy Global's full track record →
Legacy Global has 13 projects registered in Bangalore, 1 completed, 2 past RERA deadline.

Other projects by this builder in Bangalore

Legacy Cataleya
Past deadline · 92% built · 25% sold
Legacy Vivienda
Past deadline · 46% built · 7% sold
Legacy Maximus
On track · 48% built · 46% sold

Other RERA-registered projects in Abbachikkanahalli

Assetz Promise Of Spring Phase-1

Major developers building in Abbachikkanahalli

Figures are the developer's own quarterly disclosures on the Karnataka RERA register. "Built" is the highest construction % filed; "sold" is booked units over total. Not a claim about the developer's intent. Explore every project on our Bangalore project-health tool.