Bangalore/Project record

K-RERA · the public record

Provident Ecopolitan Phase 2

Bengaluru North · Provident White Oaks

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

24%construction reportedQ3 2025 filing
2units not bookedof 128 · Q3 2025 filing
30 Jun 2028declared completionK-RERA registration · read 20 Sep 2026

The record · free to read

Registration read 20 Sep 2026

Progress & dates

The timeline on file.

Promoter-reported construction

K-RERA quarterly filings · Q3 2025 to Q3 2025

declared completion

30 Jun 2028

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

K-RERA registration · read 20 Sep 2026

Inventory & scale

What this registration contains.

3 BHK Grand
18
2 BHK 2T Grand
28
3 BHK Grand
14
2 BHK 2T
36
1 BHK
18
3 BHK 2T
14

Filed categories, unchanged · K-RERA registration · read 20 Sep 2026

The whole registration

0.9registered acres

142.1registered units per acre

The average covers the registered land and all registered unit types. It does not describe the space, outlook or surroundings of an individual home.

From another project · Prestige Park Grove

A larger advertised area. Almost the same carpet area.

In Tower 14, E4 has 141 sq ft more saleable area than E2. Its carpet area is only 0.46 sq m larger. The report puts the two layouts side by side.

This illustrates the report format. These findings concern the named sample, not this project.

Read the sample report ↗
Prestige Park Grove · Tower 14 comparison · approved sample report
Prestige Park Grove · Tower 14 comparison · approved sample report

The source record

The details behind the headline.

K-RERA · PRM/KA/RERA/1251/309/PR/110823/006163

This project, on the record

The comparable facts of this project, from its own RERA registration record. Each context percentile names its exact comparison set, drawn from Quietlist’s full register store. The paid report adds drawing-read rows to this same table — what the filed plans show about the site, its edges and the unit layouts.

On the register

Declared completion30 June 2028
Land area3,646 sq m (0.9 acres)
Homes registered128
Tower/wing entries1
Unit mix32 × 3 BHK Grand, 28 × 2 BHK 2T Grand, 36 × 2 BHK 2T, 18 × 1 BHK, 14 × 3 BHK 2T

In context

Density142.1 homes per acre
Density in context95th percentile of 525 Bengaluru North projects (median 75.4)

Values as crawled from the official K-RERA record; context percentiles name their comparison population.

Official Registry Facts

Official project scale

RERA filing

Registration-form facts from the K-RERA detail page: use these to sanity-check the builder brochure, parking allotment, and sanctioned-plan references before relying on plan-extracted approximations.

DisclosureOfficial valueWhy it matters
Registered units128Total inventory registered with K-RERA.
Official carpet area8,250 sqmRegulator-disclosed project-level carpet area, not vision-derived room sums.
Official built-up area12,410 sqmUseful scale context when comparing density and project cost.
Registered land area3,646 sqmThe land area attached to this K-RERA registration.
Sanctioned FAR/FSI~26.23Sanctioned floor-area ratio (≈95,641 sqm sanctioned FAR area ÷ 3,646 sqm land) — higher means a denser vertical build.
Registered tower/wing entries1Official tower/wing count in the K-RERA detail page.
Parking total (reconciled)128Separate filed counts; these categories may overlap and are not added together.
Covered-parking field1,383Separate filed counts; these categories may overlap and are not added together.
Open-parking field230Separate filed counts; these categories may overlap and are not added together.
Garage field0Separate filed counts; these categories may overlap and are not added together.
Approved plan numberDO3-KIADB-00210/22-23/BPUse this to match the sanctioned drawing set shown by the builder.
Plan approval date12-06-2023
Project start date01-05-2024

Official inventory & towers

RERA filing

K-RERA registration tables showing the project mix and tower/wing scale. Use this to sanity-check sales claims such as "only large homes", "low density", or "plenty of parking" against the filed inventory.

Registered inventory mix

TypeUnitsShareOfficial carpet area
3 BHK Grand1814%85 sqm
2 BHK 2T Grand2822%61 sqm
3 BHK Grand1411%85 sqm
2 BHK 2T3628%55 sqm
1 BHK1814%38 sqm
3 BHK 2T1411%77 sqm

Registered tower / wing summary

Tower/wingFloorsUnitsParkingHeight
Wing 51912812859.95 m

Official unit register

RERA filing

K-RERA detail-page flat rows: exact unit numbers, official carpet area, UDS, and parking lots. 128 official flat/unit rows, matching the 128 registered units disclosed above. Use this as a checklist against the specific flat number in your cost sheet and draft agreement.

By unit type

Unit typeRowsCarpet areaUDSParking lots
2 BHK6456.0-61.8 sqm24.1-26.6 sqm64
3 BHK4677.2-86.0 sqm33.2-37.0 sqm46
1 BHK1838.1 sqm16.4 sqm18

By tower / wing

Tower/wingRowsCarpet areaUDSParking lots
Wing 512838.1-86.0 sqm16.4-37.0 sqm128
Show sample official unit rows
UnitTowerFloorTypeCarpetUDSParking
W5 - 205Wing 521 BHK38.1 sqm16.4 sqm1
W5 - 206Wing 522 BHK56.0 sqm24.1 sqm1
W5 - 207Wing 522 BHK56.0 sqm24.1 sqm1
W5 - 208Wing 523 BHK85.3 sqm36.7 sqm1
W5 - 305Wing 531 BHK38.1 sqm16.4 sqm1
W5 - 306Wing 532 BHK56.0 sqm24.1 sqm1

Legal, Approvals & Project Team

Litigation & compliance

RERA filing

No litigation declared on this project's K-RERA filing.

20 of 43 compliance document slots are filed as Not Applicable; the remaining 23 slots have usable uploaded filings.

No completion certificate (OC) on file yet — project has not been declared complete.

Named utility/regulatory approvals

Electricity (BESCOM/ESCOM)✓ On file (ESCOM/Electricity)
Water & sewage (BWSSB/KWSSB)✓ On file (KWSSB/Water)
Fire NOC✓ On file (Fire Force Department)
Pollution control (KSPCB)✓ On file (KSPCB)
Environmental clearance✓ On file (SEIAA)
Airport Authority height clearance✓ On file (Airport Authority of India)

"Not found in catalog" can mean the approval genuinely isn't on file yet, or that it doesn't apply to this project (K-RERA doesn't tell us which). Ask the builder directly for any marked not found before relying on it.

Statutory approval status

RERA filing

10 further authority slots are marked not applicable by the regulator.

Authority / NOCStatusDateFile

Project team & certifications

RERA filing

K-RERA names 4 project professional/vendor rows across Chartered accountant, Engineer, Architect, Contractor. Use this to cross-check whose certificates, drawings, and contractor commitments support the filing; final reliance still belongs with your lawyer/technical reviewer.

RoleNameRegistration / licenceSinceLocality
Chartered accountantM Padmanabha Bhat253051990Bengaluru Urban, Karnataka - 560093
EngineerShantharaju. KLIC No. KIADB/Str.Engr/034/2020-212014Bengaluru Urban, Karnataka - 560042
ArchitectKembhavi ArchitectureBCC/BL-3.6 A-2569/2014-152014Bengaluru Urban, Karnataka - 560041
ContractorKalpataru Project international-1981Bengaluru Urban, Karnataka - 560025

Builder track record

RERA filing

Provident has 17 other K-RERA-registered projects in our records — grouped across the several project-specific entities this developer registers under (e.g. this project is filed as “Provident White”) (average reported construction progress 23%). 5 are past their declared completion deadline with no completion certificate recorded — but because K-RERA publishes OCs inconsistently, a project that has actually been finished and handed over still shows up this way, so this overstates real delays, especially for a high-volume established builder. That is a lower delayed rate than the K-RERA average across Bengaluru on the same measure.

Read this as a list to spot-check for a pattern of genuinely stalled projects, not as a delay rate — pull up a few of the builder’s other K-RERA registrations and check whether they’ve actually been delivered.

Financials & Construction Progress

Financial disclosures

RERA filing

Latest quarterly filing (2025-Q3): ₹3.46 Cr collected from buyers, ₹8.12 Cr withdrawn from the project's escrow account. This quarter the escrow withdrawal (₹8.12 Cr) exceeded buyer collections (₹3.46 Cr) — worth asking the builder to reconcile against certified construction milestones, which is what RERA requires escrow draws to track.

Construction progress24% → 24% (+0 pts)
Units sold/booked as registered126/128 (98%)
Buyer collections in available QPRs₹3.46 Cr
Escrow withdrawals in available QPRs₹8.12 Cr (2.34x collections)
  • 98% of registered units are shown as sold/booked, but no completion certificate is on file yet.
  • The filed unit sales count did not move across the available QPR window because the project was already effectively sold out.
  • Across available QPR rows, escrow withdrawals are 2.34x buyer collections. Ask the builder to reconcile this against certified project costs and prior-period balances.
  • In the latest QPR, escrow withdrawal exceeds buyer collections for that quarter. This can be normal if prior balance existed, but it needs a clean explanation.

QPR figures are developer-filed quarterly disclosures. Collections and withdrawals are not a project valuation; they are a sanity check for whether sales, construction progress, and escrow draws appear directionally aligned.

Declared construction cost ÷ registered units averages to ₹38.1 lakhs per unit — the developer's own declared construction/development cost, not a sale price. K-RERA filings don't disclose what the builder is charging, so this can't tell you whether you're getting a fair deal — only you comparing your quoted price against comparable listings nearby can answer that.

RERA 70% project account is on file: HDFC Kasturba Gandhi Marg Branch IFSC Code : HDFC0000009 Pin Code : 560001. RERA requires 70% of buyer collections to sit in this separate, project-specific account, drawn only against certified construction milestones — confirm your payments are made to THIS account (not a general builder account) and that it appears on your allotment letter.

Location & Connectivity

The nearest major job hub is ~14 km away — a real but liveable commute to the nearest job hub — factor peak-hour traffic.

LandmarkStraight-line
Kempegowda Int'l Airport5 km
Outer Ring Road / Manyata14 km
MG Road / city centre22 km
Whitefield IT hub22 km
Bellandur–Marathahalli belt25 km
Electronic City35 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Built by Provident White. View Provident White's full track record →
Provident White has 6 projects registered in Bangalore.

Other projects by this builder in Bangalore

Provident Ecopolitan Phase 1
Filing overdue · 42% built · 99% sold
Provident Ecopolitan Phase 1A
No filings
Provident Ecopolitan Phase 3
No filings
Provident Ecopolitan Phase 4
No filings
Provident Ecopolitan Phase 5
On track · 9% built · 98% sold

Other RERA-registered projects in Gummanahalli

Emerald & Luminaire Block At Brigade El Dorado
Dioro & Beryl At Brigade El Dorado

Major developers building in Gummanahalli

Figures are the developer's own quarterly disclosures on the Karnataka RERA register. "Built" is the highest construction % filed; "sold" is booked units over total. Not a claim about the developer's intent. Explore every project on our Bangalore project-health tool.