31 May 2022declared completionK-RERA registration · read 20 Sep 2026
54registered unitsK-RERA registration · read 20 Sep 2026

The record · free to read

Registration read 20 Sep 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 May 2022

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

K-RERA registration · read 20 Sep 2026

Inventory & scale

What this registration contains.

Filed categories, unchanged · K-RERA registration · read 20 Sep 2026

The whole registration

4.2registered acres

12.8registered units per acre

The average covers the registered land and all registered unit types. It does not describe the space, outlook or surroundings of an individual home.

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

K-RERA · PRM/KA/RERA/1251/446/PR/180516/001716

This project, on the record

The comparable facts of this project, from its own RERA registration record. Each context percentile names its exact comparison set, drawn from Quietlist’s full register store. The paid report adds drawing-read rows to this same table — what the filed plans show about the site, its edges and the unit layouts.

On the register

Declared completion31 May 2022
Land area17,020 sq m (4.2 acres)
Homes registered54
Tower/wing entries8

In context

Density12.8 homes per acre
Density in context4th percentile of 1119 Bengaluru East projects (median 75.5)

Values as crawled from the official K-RERA record; context percentiles name their comparison population.

Official Registry Facts

Official project scale

RERA filing

Registration-form facts from the K-RERA detail page: use these to sanity-check the builder brochure, parking allotment, and sanctioned-plan references before relying on plan-extracted approximations.

DisclosureOfficial valueWhy it matters
Registered units54Total inventory registered with K-RERA.
Registered land area17,020 sqmThe land area attached to this K-RERA registration.
Sanctioned FAR/FSI0.9Higher FAR generally means a denser vertical build, subject to site layout and open-space design.
Registered tower/wing entries8Official tower/wing count in the K-RERA detail page.
Parking total (reconciled)54Separate filed counts; these categories may overlap and are not added together.
Open-parking field15Separate filed counts; these categories may overlap and are not added together.
Garage field0Separate filed counts; these categories may overlap and are not added together.
Project start date12-01-2018

Official inventory & towers

RERA filing

K-RERA registration tables showing the project mix and tower/wing scale. Use this to sanity-check sales claims such as "only large homes", "low density", or "plenty of parking" against the filed inventory.

Registered tower / wing summary

Tower/wingFloorsUnitsParkingHeight
Block 1255-
Block 2266-
Block 3255-
Block 421414-
Block 521010-
Block 6255-
Block 7244-
Block 8255-

Official unit register

RERA filing

K-RERA detail-page flat rows: exact unit numbers, official carpet area, UDS, and parking lots. 54 official flat/unit rows, matching the 54 registered units disclosed above. Use this as a checklist against the specific flat number in your cost sheet and draft agreement.

By unit type

Unit typeRowsCarpet areaUDSParking lots
3BHK33167.3-167.4 sqm165.6-168.0 sqm33
4BHK21193.8-195.6 sqm186.7-192.2 sqm21

By tower / wing

Tower/wingRowsCarpet areaUDSParking lots
Block 414167.3-167.4 sqm165.6-168.0 sqm14
Block 510167.3-167.4 sqm165.6-168.0 sqm10
Block 26193.8-195.6 sqm186.7-192.2 sqm6
Block 15195.6 sqm186.7-189.2 sqm5
Block 35195.6 sqm186.7-189.2 sqm5
Block 65167.3 sqm165.6-168.0 sqm5
Block 85195.6 sqm186.7-189.2 sqm5
Block 74167.3 sqm165.6-168.0 sqm4
Show sample official unit rows
UnitTowerFloorTypeCarpetUDSParking
A01Block 104BHK195.6 sqm189.2 sqm1
A02Block 104BHK195.6 sqm186.7 sqm1
A03Block 104BHK195.6 sqm186.7 sqm1
A04Block 104BHK195.6 sqm186.7 sqm1
A05Block 104BHK195.6 sqm189.2 sqm1
B01Block 204BHK193.8 sqm192.2 sqm1

Legal, Approvals & Project Team

Litigation & compliance

RERA filing

No litigation declared on this project's K-RERA filing.

4 of 22 compliance document slots are filed as Not Applicable; the remaining 18 slots have usable uploaded filings.

No completion certificate (OC) on file yet — project has not been declared complete.

⚠ Registration validity has lapsed: originally due 31 May 2022, extended (Covid Extension) to 28 Feb 2023 — both dates have passed with no OC on file.

Named utility/regulatory approvals

Electricity (BESCOM/ESCOM)Not found in catalog
Water & sewage (BWSSB/KWSSB)Not found in catalog
Fire NOCNot found in catalog
Pollution control (KSPCB)✓ On file (KSPCB)
Environmental clearance✓ On file (SEIAA)
Airport Authority height clearanceNot found in catalog

"Not found in catalog" can mean the approval genuinely isn't on file yet, or that it doesn't apply to this project (K-RERA doesn't tell us which). Ask the builder directly for any marked not found before relying on it.

K-RERA enforcement record (the regulator's own defaulter list & penalty orders)

⚠ Listed on K-RERA's official DEFAULTER list.

Project team & certifications

RERA filing

K-RERA names 2 project professional/vendor rows across Architect, Structural engineer. Use this to cross-check whose certificates, drawings, and contractor commitments support the filing; final reliance still belongs with your lawyer/technical reviewer.

RoleNameRegistration / licenceSinceLocality
ArchitectSpace matrix-2001TEL:+91804049 4000, Sankey Road
Structural engineerDesigntree service consultants PVT Ltd---

Builder track record

RERA filing

Assetz has 15 other K-RERA-registered projects in our records — grouped across the several project-specific entities this developer registers under (e.g. this project is filed as “Assetz Value”) (average reported construction progress 80%). 11 are past their declared completion deadline with no completion certificate recorded — but because K-RERA publishes OCs inconsistently, a project that has actually been finished and handed over still shows up this way, so this overstates real delays, especially for a high-volume established builder.

Read this as a list to spot-check for a pattern of genuinely stalled projects, not as a delay rate — pull up a few of the builder’s other K-RERA registrations and check whether they’ve actually been delivered.

Financials & Construction Progress

Financial disclosures

RERA filing

⚠ No quarterly financial disclosures (collections, escrow withdrawals) on record, despite no completion certificate yet — meaning we can't verify the project's cashflows against its construction progress. Worth asking the builder directly why no quarterly filings are available.

Declared construction cost ÷ registered units averages to ₹142.3 lakhs per unit — the developer's own declared construction/development cost, not a sale price. K-RERA filings don't disclose what the builder is charging, so this can't tell you whether you're getting a fair deal — only you comparing your quoted price against comparable listings nearby can answer that.

RERA 70% project account is on file: Karnataka Bank Ltd. Overseas Branch (IFSC KARB0000118, a/c …3700). RERA requires 70% of buyer collections to sit in this separate, project-specific account, drawn only against certified construction milestones — confirm your payments are made to THIS account (not a general builder account) and that it appears on your allotment letter.

Construction photo filings

RERA filing

K-RERA has 1 project-photo upload.

These are developer-uploaded progress photos in the official document catalog. We do not treat them as proof of current site condition; use them as a prompt to ask for newer dated photos or a site visit. Individual filings are listed in the document catalog below.

Location & Connectivity

The nearest major job hub is ~6 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Outer Ring Road / Manyata6 km
MG Road / city centre13 km
Kempegowda Int'l Airport14 km
Whitefield IT hub15 km
Bellandur–Marathahalli belt16 km
Electronic City26 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Built by Assetz Value. View Assetz Value's full track record →
Assetz Value has 3 projects registered in Bangalore.

Other projects by this builder in Bangalore

Soul & Soil - Phase 2A
No filings
Soul & Soil - Phase 2B
No filings

Other RERA-registered projects in Gummanahalli

Emerald & Luminaire Block At Brigade El Dorado
Dioro & Beryl At Brigade El Dorado

Major developers building in Gummanahalli

Figures are the developer's own quarterly disclosures on the Karnataka RERA register. "Built" is the highest construction % filed; "sold" is booked units over total. Not a claim about the developer's intent. Explore every project on our Bangalore project-health tool.