Bangalore/Project record

K-RERA · the public record

Godrej Ananda

Bengaluru North · Universal Metro Properties

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

100%construction reportedQ4 2025 filing
12units not bookedof 806 · Q4 2025 filing
08 Jan 2026declared completionK-RERA registration · read 20 Sep 2026

The record · free to read

Registration read 20 Sep 2026

Progress & dates

The timeline on file.

Promoter-reported construction

K-RERA quarterly filings · Q3 2025 to Q4 2025

declared completion

08 Jan 2026

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

K-RERA registration · read 20 Sep 2026

Inventory & scale

What this registration contains.

STUDIO
110

Filed categories, unchanged · K-RERA registration · read 20 Sep 2026

The whole registration

20.3registered acres

39.6registered units per acre

The average covers the registered land and all registered unit types. It does not describe the space, outlook or surroundings of an individual home.

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

K-RERA · PRM/KA/RERA/1251/309/PR/210331/004084

This project, on the record

The comparable facts of this project, from its own RERA registration record. Each context percentile names its exact comparison set, drawn from Quietlist’s full register store. The paid report adds drawing-read rows to this same table — what the filed plans show about the site, its edges and the unit layouts.

On the register

Declared completion8 January 2026
Land area82,265 sq m (20.3 acres)
Homes registered806
Tower/wing entries3
Unit mix110 × STUDIO

In context

Density39.6 homes per acre
Density in context17th percentile of 525 Bengaluru North projects (median 75.4)

Values as crawled from the official K-RERA record; context percentiles name their comparison population.

Official Registry Facts

Official project scale

RERA filing

Registration-form facts from the K-RERA detail page: use these to sanity-check the builder brochure, parking allotment, and sanctioned-plan references before relying on plan-extracted approximations.

DisclosureOfficial valueWhy it matters
Registered units806Total inventory registered with K-RERA.
Official carpet area2,363 sqmRegulator-disclosed project-level carpet area, not vision-derived room sums.
Registered land area82,265 sqmThe land area attached to this K-RERA registration.
Sanctioned FAR/FSI0.749Higher FAR generally means a denser vertical build, subject to site layout and open-space design.
Registered tower/wing entries3Official tower/wing count in the K-RERA detail page.
Parking total (reconciled)752Separate filed counts; these categories may overlap and are not added together.
Open-parking field171Separate filed counts; these categories may overlap and are not added together.
Garage field0Separate filed counts; these categories may overlap and are not added together.
Project start date31-03-2021

Official inventory & towers

RERA filing

K-RERA registration tables showing the project mix and tower/wing scale. Use this to sanity-check sales claims such as "only large homes", "low density", or "plenty of parking" against the filed inventory.

Registered inventory mix

TypeUnitsShareOfficial carpet area
STUDIO110100%2,363 sqm

Registered tower / wing summary

Tower/wingFloorsUnitsParkingHeight
E28259246-
F28288260-
G28259246-

Official unit register

RERA filing

K-RERA detail-page flat rows: exact unit numbers, official carpet area, UDS, and parking lots. 806 official flat/unit rows, matching the 806 registered units disclosed above. Use this as a checklist against the specific flat number in your cost sheet and draft agreement.

By unit type

Unit typeRowsCarpet areaUDSParking lots
2BHK53049.3-65.2 sqm19.1-24.8 sqm530
3BHK16265.2-65.3 sqm24.8-24.8 sqm162
1BHK11421.5-65.3 sqm8.5-24.8 sqm4 (110 with 0)

By tower / wing

Tower/wingRowsCarpet areaUDSParking lots
F28821.5-65.3 sqm8.5-24.8 sqm232 (56 with 0)
E25921.5-65.3 sqm8.5-24.8 sqm232 (27 with 0)
G25921.5-65.3 sqm8.5-24.8 sqm232 (27 with 0)
Show sample official unit rows
UnitTowerFloorTypeCarpetUDSParking
E00-02E02BHK54.0 sqm20.7 sqm1
E00-03E02BHK49.8 sqm19.3 sqm1
E00-04E02BHK49.8 sqm19.3 sqm1
E00-05E02BHK49.8 sqm19.3 sqm1
E00-06E02BHK49.8 sqm19.3 sqm1
E00-07E02BHK49.3 sqm19.1 sqm1

Legal, Approvals & Project Team

Litigation & compliance

RERA filing

No litigation declared on this project's K-RERA filing.

⚠ 6 of 33 compliance document slots are filed as under process / not yet usable: Proforma For Sale Deed, Section 3(1) Notarized Affidavit, Conversion Certificate under Sec 95 of the KLR Act 1961, Approval/NOC under Sec 14 of the KTCP Act, Bangalore Urban Arts Commission and more.

7 additional compliance slots are filed as Not Applicable.

No completion certificate (OC) on file yet — project has not been declared complete.

Named utility/regulatory approvals

Electricity (BESCOM/ESCOM)✓ On file (BESCOM)
Water & sewage (BWSSB/KWSSB)✓ On file (BWSSB)
Fire NOC✓ On file (Fire Force Department)
Pollution control (KSPCB)✓ On file (KSPCB)
Environmental clearance✓ On file (SEIAA)
Airport Authority height clearance✓ On file (Airport Authority of India)

"Not found in catalog" can mean the approval genuinely isn't on file yet, or that it doesn't apply to this project (K-RERA doesn't tell us which). Ask the builder directly for any marked not found before relying on it.

K-RERA complaint orders (1 complaint against a project of this name on K-RERA's orders register)

PartiesRelief soughtDisposalOrder date
Yash Kashyap Desai vs Godrej AnandaDirect the Respondent to hand over possession within a time-bound period and grant interest for the delay period under Section 18 of RERA, alternatively provide non-monetary relief including parkingAUTHORITY09/03/2026

⚠ Matched by PROJECT NAME (the orders register carries no registration number) — confirm the respondent above is this project's builder before relying on it.

Statutory approval status

RERA filing

10 further authority slots are marked not applicable by the regulator.

Authority / NOCStatusDateFile

Project team & certifications

RERA filing

K-RERA names 3 project professional/vendor rows across Architect, Contractor, Structural engineer. Use this to cross-check whose certificates, drawings, and contractor commitments support the filing; final reliance still belongs with your lawyer/technical reviewer.

RoleNameRegistration / licenceSinceLocality
ArchitectC B VIVEK UTHAIAH-200212, Museum road Blore -01
ContractorGanesh Earth Movers-200623rd cross, HSR Layout Bengaluru
Structural engineerM/s.Prasad Consultants---

Builder track record

RERA filing

Universal Metro has 2 other K-RERA-registered projects in our records (average reported construction progress 72%). 0 are past their declared completion deadline with no completion certificate recorded — but because K-RERA publishes OCs inconsistently, a project that has actually been finished and handed over still shows up this way, so this overstates real delays, especially for a high-volume established builder. That is a lower delayed rate than the K-RERA average across Bengaluru on the same measure.

Read this as a list to spot-check for a pattern of genuinely stalled projects, not as a delay rate — pull up a few of the builder’s other K-RERA registrations and check whether they’ve actually been delivered.

Financials & Construction Progress

Financial disclosures

RERA filing

Latest quarterly filing (2025-Q4): ₹12.43 Cr collected from buyers, ₹0.84 Cr withdrawn from the project's escrow account.

Construction progress99% → 100% (+1 pts)
Units sold/booked as registered794/806 (99%)
Buyer collections in available QPRs₹12.72 Cr
Escrow withdrawals in available QPRs₹0.89 Cr (0.07x collections)
  • 99% of registered units are shown as sold/booked, but no completion certificate is on file yet.
  • Construction progress moved from 99% to 100% across the filed QPR window.
  • The filed unit sales count did not move across the available QPR window because the project was already effectively sold out.
  • The builder has drawn 0.07x of buyer collections from escrow (about 7% of the ₹13 Cr collected) — money is largely staying in the regulated escrow account rather than being pulled out ahead of spend, which is the safer direction. A ratio near or above 1.0 would be the one to scrutinise.

QPR figures are developer-filed quarterly disclosures. Collections and withdrawals are not a project valuation; they are a sanity check for whether sales, construction progress, and escrow draws appear directionally aligned.

Declared construction cost ÷ registered units averages to ₹23.2 lakhs per unit — the developer's own declared construction/development cost, not a sale price. K-RERA filings don't disclose what the builder is charging, so this can't tell you whether you're getting a fair deal — only you comparing your quoted price against comparable listings nearby can answer that.

RERA 70% project account is on file: Axis Bank MAJESTIC (IFSC UTIB0000693, a/c …7991). RERA requires 70% of buyer collections to sit in this separate, project-specific account, drawn only against certified construction milestones — confirm your payments are made to THIS account (not a general builder account) and that it appears on your allotment letter.

Construction photo filings

RERA filing

K-RERA has 1 project-photo upload.

These are developer-uploaded progress photos in the official document catalog. We do not treat them as proof of current site condition; use them as a prompt to ask for newer dated photos or a site visit. Individual filings are listed in the document catalog below.

Location & Connectivity

The nearest major job hub is ~13 km away — a real but liveable commute to the nearest job hub — factor peak-hour traffic.

LandmarkStraight-line
Kempegowda Int'l Airport7 km
Outer Ring Road / Manyata13 km
MG Road / city centre21 km
Whitefield IT hub21 km
Bellandur–Marathahalli belt24 km
Electronic City34 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Built by Universal Metro.
Universal Metro has 3 projects registered in Bangalore, 2 completed.

Other projects by this builder in Bangalore

Godrej Ananda Phase 2
On track · 97% built · 99% sold
Soul@godrej Ananda
On track · 46% built · 97% sold

Other RERA-registered projects in Gummanahalli

Emerald & Luminaire Block At Brigade El Dorado
Dioro & Beryl At Brigade El Dorado

Major developers building in Gummanahalli

Figures are the developer's own quarterly disclosures on the Karnataka RERA register. "Built" is the highest construction % filed; "sold" is booked units over total. Not a claim about the developer's intent. Explore every project on our Bangalore project-health tool.