Urban Resort Phase-2
REVENUE ESTATE OF VILLAGE DHA NWAPUR, SECTOR-103, GURUGRAM · Whiteland Corporation
Know the project.
Then choose your home.
The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.
The record · free to read
Registration read 20 Sep 2026Progress & dates
The timeline on file.
Available record
No construction trend to plot.
The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.
registration expiry
30 Sep 2031
The registered date and a construction update answer different questions. Neither is a confirmation of possession.
HRERA registration · read 20 Sep 2026
From another project
See the report before you buy.
A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.
Read a sample report ↗The source record
The details behind the headline.
HRERA ·
Escrow account
What has moved through the RERA escrow account?
Across 8 filed quarterly reports, Urban Resort Phase-2 records ₹190.80 Cr paid into and ₹158.30 Cr withdrawn from its RERA escrow account, with a latest recorded balance of ₹2.35 Cr.
₹190.80 Cr
into the escrow account
₹158.30 Cr
withdrawn
₹2.35 Cr
latest balance
Amounts as filed in the developer's own quarterly progress reports to HRERA, summed across the quarters on record.
Source · HRERA quarterly progress reports
Official Unit Inventory
170 apartments filed across 2 carpet-area configurations, 4 towers, carpet areas from 2,009 to 2,106 sq ft. These are the carpet areas the developer filed with HRERA — match the unit a broker quotes you against this table; a "1,650 sq ft" pitch should map to a filed configuration here (carpet area is the RERA-defined saleable floor).
| Carpet area | (metric) | Units of this size |
|---|---|---|
| 2,106 sq ft | 195.7 sq m | 85 |
| 2,009 sq ft | 186.6 sq m | 85 |
Sales Traction, Quarter by Quarter
Units the developer reported booking in each quarterly HRERA filing — the closest public read on real demand.
| Quarter | Units booked | Total units |
|---|---|---|
| 2024 Q3 | 0 | 170 |
| 2024 Q4 | 0 | 170 |
| 2025 Q1 | 38 | 170 |
| 2025 Q2 | 44 | 264 |
| 2025 Q3 | 18 | 264 |
| 2025 Q4 | 22 | 264 |
| 2026 Q1 | 16 | 264 |
| 2026 Q2 | 18 | 264 |
Escrow Account Activity
Money moving through the RERA-mandated escrow account each quarter. Withdrawals from it are statutorily meant to fund construction milestones.
| Quarter | Deposited | Withdrawn | Balance |
|---|---|---|---|
| 2024 Q3 | ₹0 L | ₹0 L | ₹0 L |
| 2024 Q4 | ₹0 L | ₹0 L | ₹0 L |
| 2025 Q1 | ₹22.76 Cr | ₹15.00 Cr | ₹7.76 Cr |
| 2025 Q2 | ₹31.03 Cr | ₹3.35 Cr | ₹5.29 Cr |
| 2025 Q3 | ₹33.98 Cr | ₹37.20 Cr | ₹2.07 Cr |
| 2025 Q4 | ₹31.79 Cr | ₹32.55 Cr | ₹1.31 Cr |
| 2026 Q1 | ₹27.23 Cr | ₹23.10 Cr | ₹5.44 Cr |
| 2026 Q2 | ₹44.01 Cr | ₹47.10 Cr | ₹2.35 Cr |
Builder Record
Elan has 25 other Gurgaon projects on the HRERA register; 2 are past the declared completion date with no OC yet, 9 delivered. Read it as a spot-check list for a pattern, not a delay rate.
- Aspen One — declared 2031-06-30
- Commercial Colony — declared 2023-09-13 · OC on record
- Commercial Project — declared 2022-09-13 · OC on record
- Elan Empire — declared 2026-04-14
Location & Connectivity
The nearest major job hub is ~10 km away — a manageable everyday commute to a major job hub.
| Landmark | Straight-line |
|---|---|
| Udyog Vihar | 10 km |
| Cyber City / DLF Cyber Hub | 10 km |
| Golf Course Road belt | 13 km |
| IGI Airport, Delhi | 13 km |
| IMT Manesar | 16 km |
| Connaught Place, Delhi | 27 km |
Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.