MahaRERA Property Intelligence · Mumbai Suburban
P51800050999 · Mulund West · promoter Aishwarya Associates Llp
| MahaRERA registration | P51800050999 |
| Registered on | 19 May 2023 |
| Promoter-declared completion | 29 Apr 2027 |
| Current status | Certificate Signed |
| Against today | 9 months to the declared date |
MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.
Across MahaRERA, Aishwarya Associates Llp is the promoter of record on 12 projects, of which 3 carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.
Of 49 homes filed with MahaRERA, 9 are sold/booked and 40 remain available (~18% sold) — early in sales — more choice of units now, but confirm the developer has the pre-sales to fund the build. Buyers have committed ₹12.19 Cr in agreement value so far. Of that, ₹9.15 Cr (~75%) is already collected, ₹3.05 Cr receivable — a read on how far along these sales really are. Note: the project registers 72 homes in total, but this sold/unsold inventory filing covers only 49 of them — the other 23 aren't in the ledger yet. Ask the builder what they are (an unreleased phase, held-back stock, or non-saleable/car-park units) before reading too much into the percentage. This is the promoter's own reported inventory as at the last compliance filing; confirm current availability directly.
What buyers actually paid: across 9 registered agreements, the effective carpet rate is ₹21,464/sqft (typical range ₹20,741–₹23,190) — computed from the agreement values and carpet areas the promoter filed, not broker quotes. Compare your quote against this before negotiating.
The unsold units on the filing — if you're quoted a unit NOT on this list, ask why it shows as sold/booked on the RERA record:
| Floor | Unit | Carpet | Reckoner value |
|---|---|---|---|
| Floor 11 | 1103 | 348 sqft (32.33 sqm) | ₹87.06 Lakh |
| Floor 11 | 1105 | 724 sqft (67.26 sqm) | ₹1.81 Cr |
| Floor 12 | 1204 | 732 sqft (68 sqm) | ₹1.83 Cr |
| Floor 12 | 1205 | 724 sqft (67.26 sqm) | ₹1.81 Cr |
| Floor 13 | 1305 | 724 sqft (67.26 sqm) | ₹1.81 Cr |
| Floor 14 | 1401 | 725 sqft (67.35 sqm) | ₹1.81 Cr |
| Floor 14 | 1405 | 724 sqft (67.26 sqm) | ₹1.81 Cr |
| Floor 15 | 1504 | 732 sqft (68 sqm) | ₹1.83 Cr |
| Floor 15 | 1505 | 724 sqft (67.26 sqm) | ₹1.81 Cr |
| Floor 16 | 1603 1604 | 1,029 sqft (95.6 sqm) | ₹2.57 Cr |
| Floor 16 | 1605 | 724 sqft (67.26 sqm) | ₹1.81 Cr |
| Floor 17 | 1703 | 493 sqft (45.8 sqm) | ₹1.23 Cr |
| Floor 17 | 1704 | 732 sqft (68 sqm) | ₹1.83 Cr |
| Floor 17 | 1705 | 724 sqft (67.26 sqm) | ₹1.81 Cr |
| Floor 18 | 1801 | 725 sqft (67.35 sqm) | ₹1.81 Cr |
| Floor 18 | 1803 | 493 sqft (45.8 sqm) | ₹1.23 Cr |
| Floor 18 | 1804 | 732 sqft (68 sqm) | ₹1.83 Cr |
| Floor 18 | 1805 | 724 sqft (67.26 sqm) | ₹1.81 Cr |
| Floor 19 | 1901 | 725 sqft (67.35 sqm) | ₹1.81 Cr |
| Floor 19 | 1902 | 745 sqft (69.21 sqm) | ₹1.86 Cr |
| Floor 19 | 1903 | 493 sqft (45.8 sqm) | ₹1.23 Cr |
| Floor 19 | 1904 | 732 sqft (68 sqm) | ₹1.83 Cr |
| Floor 19 | 1905 | 724 sqft (67.26 sqm) | ₹1.81 Cr |
| Floor 20 | 2001 | 725 sqft (67.35 sqm) | ₹1.81 Cr |
| Floor 20 | 2002 | 745 sqft (69.21 sqm) | ₹1.86 Cr |
| Floor 20 | 2004 | 732 sqft (68 sqm) | ₹1.83 Cr |
| Floor 20 | 2005 | 724 sqft (67.26 sqm) | ₹1.81 Cr |
| Floor 21 | 2101 | 725 sqft (67.35 sqm) | ₹1.81 Cr |
| Floor 21 | 2102 | 745 sqft (69.21 sqm) | ₹1.86 Cr |
| Floor 21 | 2103 | 493 sqft (45.8 sqm) | ₹1.23 Cr |
| Floor 21 | 2104 | 732 sqft (68 sqm) | ₹1.83 Cr |
| Floor 21 | 2105 | 724 sqft (67.26 sqm) | ₹1.81 Cr |
| Floor 6 | 603 | 350 sqft (32.48 sqm) | ₹87.41 Lakh |
| Floor 7 | 701 | 725 sqft (67.35 sqm) | ₹1.81 Cr |
| Floor 7 | 702 | 864 sqft (80.31 sqm) | ₹2.16 Cr |
| Floor 7 | 705 | 540 sqft (50.17 sqm) | ₹1.35 Cr |
| Floor 8 | 801 | 725 sqft (67.35 sqm) | ₹1.81 Cr |
| Floor 8 | 802 | 723 sqft (67.17 sqm) | ₹1.81 Cr |
| Floor 8 | 803 | 343 sqft (31.87 sqm) | ₹85.63 Lakh |
| Floor 9 | 905 | 724 sqft (67.26 sqm) | ₹1.81 Cr |
⚠ The inventory filing also declares: 23 not for sale. Before booking, confirm YOUR unit appears in none of these lists and get any lender NOC in writing.
The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+17 and 72 homes are registered across the project.
| Building | Wings | Floors | Homes | Declared completion |
|---|---|---|---|---|
| Aishwarya Optima | 1 | G+17 | 72 | - |
Unit mix on the filing: 72 residential.
No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.
The promoter has had the MahaRERA completion deadline formally extended 1 time. Each extension is the regulator letting the finish line move — the clearest evidence of delivery slippage, straight from the record.
| From (declared) | To (revised) | Stated reason |
|---|---|---|
| 30 Apr 2026 | 29 Apr 2027 | No Inventory Sold - Due to change in Team we are taking Extension for additional 12 Months |
Located at Mulund West, Murar Road, Thane, Thane, 400080. Per the filed land record, the plot is bounded to the north by CTS No 1121, to the south by Murar Road, to the east by CTS No 1132 B and to the west by 44 Feet Wide Road. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.
The nearest major job hub is ~8 km away — a manageable everyday commute to a major job hub.
| Landmark | Straight-line |
|---|---|
| Powai / Hiranandani business park | 8 km |
| Andheri MIDC / SEEPZ | 10 km |
| Chhatrapati Shivaji Int'l Airport | 13 km |
| Bandra Kurla Complex (BKC) | 15 km |
| Lower Parel / Worli business district | 23 km |
| Nariman Point / Fort | 31 km |
Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.
🔒 The verdict & buyer playbook · Compliance report
The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.
🔒 Unit-by-unit guidance · Unit Guidance report
Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.
🔒 Full financial records — escrow, funding & the document catalog · Compliance report
The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.
Should you buy in Aishwarya Optima?
This page is the free MahaRERA filing summary. The full RERA Property Intelligence Report gives you the full regulatory standing, declared court litigation, buyer-complaint and adjudication history, quarterly-progress-report discipline, the builder's MahaRERA-wide track record, the building/tower breakdown, and the sanctioned layout plan. See a real one first:
Sample: Lodha Kandivali – Tower 2 → · browse all sample reports →
Compliance Report · ₹999
The regulator’s filing record, read · 1 working day
Scan with any UPI app to pay · quietlist@kotak
Unit Guidance Report · ₹2,999
Everything, down to which unit · 1 working day
Not useful to your decision? Full refund — no questions asked.
Scan with any UPI app to pay · quietlist@kotak
Paying from outside India? Pay $15 (Compliance) or $39 (Unit Guidance) via PayPal, or email hello@quietlist.in for a card invoice. Prefer to talk first, or have a portfolio to check? Same address. An information aid for your own due diligence, not legal or investment advice.
Free · Watch this project
We'll email you when this project's RERA record changes.
Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.
Last checked against the RERA register: 27 Jul 2026