Arihant Avanti Phase II
Village- Padale, Shil and Daighar · ARIHANT SUPERSTRUCTURES LIMITED
Know the project.
Then choose your home.
The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.
The record · free to read
Registration read 12 Jul 2026Progress & dates
The timeline on file.
Available record
No construction trend to plot.
The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.
declared completion
31 Dec 2031
The registered date and a construction update answer different questions. Neither is a confirmation of possession.
MahaRERA registration · read 12 Jul 2026
From another project
See the report before you buy.
A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.
Read a sample report ↗The source record
The details behind the headline.
MahaRERA · P51700078840
Delivery and registration
When is the project declared for completion?
Arihant Avanti Phase II is registered with MahaRERA as P51700078840 and the promoter has declared completion for 31 Dec 2031.
31 Dec 2031
declared completion
63months to go
against the declared date
The completion date and status as they stand on the MahaRERA registration record.
Source · MahaRERA project registration · read 12 Jul 2026
| MahaRERA registration | P51700078840 |
| Registered on | 15 Jan 2025 |
| Promoter-declared completion | 31 Dec 2031 |
| Current status | Certificate Signed |
| Against today | 63 months to the declared date |
Approvals and compliance
What compliance filings are on record?
MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for Arihant Avanti Phase II record 5 quarterly progress reports since registration.
5quarterly filings
Entries as they appear on MahaRERA's own lists and the project's progress filing.
Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026
- Filing progress reports — 5 quarterly progress reports on record since registration, with no current default.
Promoter record
What else is this promoter on record for?
Arihant Superstructures Limited is the promoter of record on 49 projects registered with MahaRERA, 2 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).
49projects
registered with MahaRERA
2flagged
by MahaRERA
Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.
Source · MahaRERA register, all projects · read 12 Jul 2026
Construction
How much construction cost has been reported?
In Arihant Avanti Phase II, ₹9.56 Cr of a declared ₹120.99 Cr estimated project cost is reported as incurred, about 7.9%, as at the last certified filing with MahaRERA.
7.9%
₹9.56 Cr
of ₹120.99 Cr declared cost
Cost incurred as last certified to MahaRERA. It is a financial measure, not a survey of site work, and it can lag on-site reality between filings.
Source · MahaRERA quarterly progress filing · read 12 Jul 2026
Sales
How much has actually been sold?
In Arihant Avanti Phase II, 70 of 401 homes filed with MahaRERA are recorded as sold or booked (30 with registered agreements and 40 booked), about 17%, and 331 remain available.
17%sold
70 of 401 homes
₹32.54 Cr
committed by buyers
Counts and agreement value as the promoter filed them at the last compliance date; this is the filed inventory, not current availability. Of that agreement value, ₹8.93 Cr (about 27%) is recorded as collected and ₹23.61 Cr as receivable. The project registers 444 homes in total, while this sold/unsold inventory filing covers 401 of them.
Source · MahaRERA sold/unsold inventory filing · read 12 Jul 2026
What buyers actually paid: across 70 registered agreements, the effective carpet rate is ₹11,918/sqft, with eight in ten falling between ₹11,060 and ₹13,037 — computed from the agreement values and carpet areas the promoter filed, not broker quotes.
The inventory filing also declares: 43 not for sale.
What the filings record, home by home
Read from MahaRERA on 20 September 2026
MahaRERA publishes, home by home, what this promoter filed: which homes are sold and which are not, the RERA carpet area of each, and for the sold ones the registered agreement value — the consideration filed for that specific home. On this project 96 homes carry one, and 305 of the 444 are recorded unsold. Since we started watching this ledger, 35 homes have moved out of the unsold list, most recently on 11 September 2026.
Here is one of those unsold homes, priced against what buyers of the same home on other floors actually filed:
| Home | Carpet | Filed for the same home on other floors | Based on |
|---|---|---|---|
| 106 | 502 sqft | Rs 58.00 lakh typical, over Rs 53.20 lakh to Rs 64.00 lakh | 17 filed on this stack, floors 8–39 |
A filed consideration is what was registered for one home. It is not a valuation, and MahaRERA does not publish the date of any of these agreements — read a range as a spread, not as a trend. An unsold row means no sale had been filed for it when we looked, which is a filing state, not a promise that the home is available to you today. One of the two observations is an archived copy whose time is the moment the file was written, not a portal fetch time.
In Arihant Avanti Phase II, every one of the 305 unsold homes has agreements filed on its own stack. The Price Comparison Report gives each of them its own row — the filed agreements behind that stack listed in full, the government reckoner value the promoter filed against it, and whether it is mortgaged to a lender while still on the unsold list. Built from the filing itself, sent by email.
Buildings & Wings
The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+41 and 444 homes are registered across the project.
| Building | Wings | Floors | Homes | Declared completion |
|---|---|---|---|---|
| Angelo Building No-1 | 1 | G+41 | 444 | - |
Unit mix on the filing: 444 residential.
Complaints
No buyer complaints were on this project's MahaRERA record at the time of reading.
Location, Land & Connectivity
Located at Village- Padale, Shil and Daighar, Survey No. 57/3 Village Padale, Survey No. 18/2 Village Shil & Survey No. 109/1/A, 109/1/B & 108/2 Village Daighar, Thane, Thane, 421204. Per the filed land record, the plot is bounded to the north by Survey No 57 Hissa No 3, to the south by Adj Survey No 19, to the east by 60 M wide DP Road and to the west by 30 M wide DP Road. These are the boundaries as recorded in the filed land record.