Mumbai/Project record

MahaRERA · the public record

Arkade Nest

Mulund West · Arkade Developers Pvt. Ltd.

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

100units filed as unsoldInventory · 19 September 2026
30 Jun 2027declared completionMahaRERA registration · read 12 Jul 2026
351registered unitsMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Jun 2027

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51800050953

Delivery and registration

When is the project declared for completion?

Arkade Nest is registered with MahaRERA as P51800050953 and the promoter has declared completion for 30 Jun 2027.

30 Jun 2027

declared completion

9months to go

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51800050953
Registered on15 May 2023
Promoter-declared completion30 Jun 2027
Current statusCertificate Signed
Against today9 months to the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for Arkade Nest record 11 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Filing progress reports — 11 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Arkade Developers is the promoter of record on 31 projects registered with MahaRERA, none of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

31projects

registered with MahaRERA

0flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Construction

How much construction cost has been reported?

In Arkade Nest, ₹111.66 Cr of a declared ₹233.01 Cr estimated project cost is reported as incurred, about 47.9%, as at the last certified filing with MahaRERA.

47.9%

₹111.66 Cr

of ₹233.01 Cr declared cost

Cost incurred as last certified to MahaRERA. It is a financial measure, not a survey of site work, and it can lag on-site reality between filings.

Source · MahaRERA quarterly progress filing · read 12 Jul 2026

Sales

How much has actually been sold?

In Arkade Nest, 235 of 351 homes filed with MahaRERA are recorded as sold or booked (169 with registered agreements and 66 booked), about 67%, and 116 remain available.

67%sold

235 of 351 homes

₹399.47 Cr

committed by buyers

Counts and agreement value as the promoter filed them at the last compliance date; this is the filed inventory, not current availability. Of that agreement value, ₹237.18 Cr (about 59%) is recorded as collected and ₹162.29 Cr as receivable.

Source · MahaRERA sold/unsold inventory filing · read 12 Jul 2026

What buyers actually paid: across 235 registered agreements, the effective carpet rate is ₹23,268/sqft, with eight in ten falling between ₹21,693 and ₹25,224 — computed from the agreement values and carpet areas the promoter filed, not broker quotes.

No units are declared mortgaged, reserved, investor-held or not-for-sale in this inventory filing.

What the filings record, home by home

Read from MahaRERA on 19 September 2026

MahaRERA publishes, home by home, what this promoter filed: which homes are sold and which are not, the RERA carpet area of each, and for the sold ones the registered agreement value — the consideration filed for that specific home. On this project 251 homes carry one, and 100 of the 351 are recorded unsold. Since we started watching this ledger, 80 homes have moved out of the unsold list, most recently on 11 September 2026.

Here is one of those unsold homes, priced against what buyers of the same home on other floors actually filed:

HomeCarpetFiled for the same home on other floorsBased on
802762 sqftRs 23,508 a sq ft typical, over Rs 20,653 to Rs 26,52471 filed at this size

A filed consideration is what was registered for one home. It is not a valuation, and MahaRERA does not publish the date of any of these agreements — read a range as a spread, not as a trend. An unsold row means no sale had been filed for it when we looked, which is a filing state, not a promise that the home is available to you today. One of the two observations is an archived copy whose time is the moment the file was written, not a portal fetch time.

In Arkade Nest, every one of the 100 unsold homes has agreements filed on its own stack. The Price Comparison Report gives each of them its own row — the filed agreements behind that stack listed in full, the government reckoner value the promoter filed against it, and whether it is mortgaged to a lender while still on the unsold list. Built from the filing itself, sent by email.

See the other 99 homes — ₹2,999 →

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+17 and 351 homes are registered across the project.

BuildingWingsFloorsHomesDeclared completion
Wing A1G+851-
Wing B1G+851-
Wing C1G+868-
Wing D1G+866-
Wing E1G+1766-
Wing F1G+1749-

Unit mix on the filing: 351 residential.

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Location, Land & Connectivity

Located at Mulund West, Asha Nagar Park Road, Borivali, Mumbai Suburban, 400080. Per the filed land record, the plot is bounded to the north by Sai Krupa Building and Ground plus 1 structure, to the south by 18 m wide DP Road, to the east by 13 m wide DP Road and to the west by CTS No 709A. These are the boundaries as recorded in the filed land record.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

See every Arkade Developers Pvt. Ltd. project & its RERA track record →

Other RERA-registered projects in Mulund West

AAI Satidevi Paradise
possession by Sep 2026 · Shreenath Developers
Laizer Elegance
Not filing quarterly progress reports · possession by Sep 2026 · Laizer Builders & Developers
THE NEW Anand Deep CHS LTD
possession by Sep 2026 · Shreejee Buildcon
Tirupati Apartments Chsl
possession by Oct 2026 · Tirupati Aparmtnets CO Operative Housing
Horizon Garden View
possession by Nov 2026 · Horizon Promoters India LTD
Montana Phase - 3
possession by Dec 2026 · Lohitka Properties LLP

Major developers building in Mulund West

Other RERA-registered projects in Mumbai Suburban

Arkade Pearl 1
possession by Dec 2026 · Arkade Developers Limited
Arkade Pearl 2
possession by Dec 2026 · Arkade Developers Limited
Arkade Pearl 3
possession by Dec 2026 · Arkade Developers Limited
Arkade Pearl 4
possession by Jun 2027 · Arkade Developers Ltd
Arkade Rare
possession by Dec 2028 · Arkade Developers Limited
Arkade Sapphire
possession by Sep 2029 · Arkade Developers Limited

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026