MahaRERA · the public record
Chistiya Palace
AGRIPADA WEST · Rensar Infra Pvt.Ltd
Know the project.
Then choose your home.
The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.
The record · free to read
Registration read 12 Jul 2026Progress & dates
The timeline on file.
Available record
No construction trend to plot.
The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.
declared completion
30 Jun 2026
The registered date and a construction update answer different questions. Neither is a confirmation of possession.
MahaRERA registration · read 12 Jul 2026
From another project
See the report before you buy.
A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.
Read a sample report ↗The source record
The details behind the headline.
MahaRERA · P51900005473
Delivery and registration
When is the project declared for completion?
Chistiya Palace is registered with MahaRERA as P51900005473 and the promoter has declared completion for 30 Jun 2026.
30 Jun 2026
declared completion
3months past
against the declared date
The completion date and status as they stand on the MahaRERA registration record.
Source · MahaRERA project registration · read 12 Jul 2026
| MahaRERA registration | P51900005473 |
| Registered on | 11 Aug 2017 |
| Promoter-declared completion | 30 Jun 2026 |
| Current status | Certificate Signed |
| Against today | about 3 months past the declared date |
Approvals and compliance
What compliance filings are on record?
MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for Chistiya Palace record 36 quarterly progress reports since registration.
36quarterly filings
Entries as they appear on MahaRERA's own lists and the project's progress filing.
Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026
- Current QPR default — the promoter has stopped filing the mandatory quarterly progress report (FY 2025-2026).
Construction
How much construction cost has been reported?
In Chistiya Palace, ₹13.91 Cr of a declared ₹18.85 Cr estimated project cost is reported as incurred, about 73.8%, as at the last certified filing with MahaRERA.
73.8%
₹13.91 Cr
of ₹18.85 Cr declared cost
Cost incurred as last certified to MahaRERA. It is a financial measure, not a survey of site work, and it can lag on-site reality between filings.
Source · MahaRERA quarterly progress filing · read 12 Jul 2026
Sales
How much has actually been sold?
In Chistiya Palace, 14 of 16 homes filed with MahaRERA are recorded as sold or booked (11 with registered agreements and 3 booked), about 88%, and 2 remain available.
88%sold
14 of 16 homes
₹39.46 Cr
committed by buyers
Counts and agreement value as the promoter filed them at the last compliance date; this is the filed inventory, not current availability. Of that agreement value, ₹30.05 Cr (about 76%) is recorded as collected and ₹9.41 Cr as receivable.
Source · MahaRERA sold/unsold inventory filing · read 12 Jul 2026
What buyers actually paid: across 14 registered agreements, the effective carpet rate is ₹24,648/sqft, with eight in ten falling between ₹21,203 and ₹28,008 — computed from the agreement values and carpet areas the promoter filed, not broker quotes.
The units recorded as unsold on the filing. The reckoner value is the government's ready-reckoner assessment the promoter filed against that unit, the figure stamp duty is charged on. It is not a price anyone paid, not an asking price, and not a valuation of the home.
| Floor | Unit | Carpet | Govt reckoner value |
|---|---|---|---|
| Floor 11 | 1101 | 1,573 sqft (146.17 sqm) | ₹3.36 Cr |
| Floor 20 | 2001 | 1,559 sqft (144.83 sqm) | ₹3.33 Cr |
No units are declared mortgaged, reserved, investor-held or not-for-sale in this inventory filing.
What the filings record, home by home
Read from MahaRERA on 13 September 2026
MahaRERA publishes, home by home, what this promoter filed: which homes are sold and which are not, the RERA carpet area of each, and for the sold ones the registered agreement value — the consideration filed for that specific home. On this project 14 homes carry one, and 2 of the 16 are recorded unsold.
A filed consideration is what was registered for one home. It is not a valuation, and MahaRERA does not publish the date of any of these agreements — read a range as a spread, not as a trend. An unsold row means no sale had been filed for it when we looked, which is a filing state, not a promise that the home is available to you today. Only one observation of this ledger so far: no change can be reported yet. This observation is an archived copy whose time is the moment the file was written, not a portal fetch time.
In Chistiya Palace, 0 of the 2 unsold homes have agreements filed on their own stack. The Price Comparison Report gives each of them its own row — the filed agreements behind that stack listed in full, the government reckoner value the promoter filed against it, and whether it is mortgaged to a lender while still on the unsold list. Built from the filing itself, sent by email.
Buildings & Wings
The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+27 and 16 homes are registered across the project.
| Building | Wings | Floors | Homes | Declared completion |
|---|---|---|---|---|
| Chistiya Palace | 1 | G+27 | 16 | - |
Unit mix on the filing: 16 residential.
Legal and disputes
What disputes are disclosed?
3 complaints are on the MahaRERA record for Chistiya Palace, with orders passed in 3 of them.
3complaints
3with an order
Counts as disclosed in the project record.
Source · MahaRERA project disclosures · read 12 Jul 2026
| Complaint no. | Filed | Parties | Status |
|---|---|---|---|
| CC006000000530718 | 08/06/2024 | Rais Kasam Shaikh vs Rensar Infra Pvt.Ltd | order passed |
| CC12503131 | 05/09/2025 | Imtiyaz Zakaria vs Rensar Infra Pvt.Ltd | order passed |
| CC12601732 | 26/03/2026 | bashiroddin ashaboddin inamdar vs Rensar Infra Pvt.Ltd | order passed |
Legal & Litigation
The promoter has declared 1 court case on this project to MahaRERA. Litigation can cloud the land title or stall the build — have a lawyer pull the cause list for each and confirm whether it touches the title to your home. This is declared by the promoter; there may be further cases not on the RERA record.
| Court | Case no. | Year | Status |
|---|---|---|---|
| Maharera Appellate Tribunal Mumbai | AT06/00500/25 | 2025 | Ongoing |
Deadline Extensions
The MahaRERA completion deadline for this project has been formally extended 3 times, as recorded on the register.
| From | Extended to | Stated reason |
|---|---|---|
| as registered | 31 Jul 2023 | BY VIRTUE OF DEVELOPMENT CONTROL AND PROMOTION REGULATION, 2034, THE PROMOTER IS NOW, FURTHER ENTITLED TO ADDITIONAL FSI FOR WHICH THE PROMOTER HAS REVISED THE PLANS AND APPLIED TO |
| 31 Jul 2023 | 30 Jun 2025 | We hereby submit Justification and Reasons for Extension of the project u/s 7(3) to fulfil directions given by the Hon’ble Bombay High Court as explained hereunder:- 1. That the p |
| 30 Jun 2025 | 30 Jun 2026 | We are clear and committed that our project will get completed by 30.06.2026. We have got consent of more than 51% allottees of the project which is in compliance of the requireme |
Location, Land & Connectivity
Located at AGRIPADA WEST, 4, MOTLIBAI STREET, Andheri, Mumbai Suburban, 400011. Per the filed land record, the plot is bounded to the north by Zaveri Mansion CS No 1-1876, to the south by Aqdas Mahal 9-1876, to the east by Motlibai Street and to the west by Agripada Police Station CS No 1901. These are the boundaries as recorded in the filed land record.
Location & connectivity
The nearest major job hub is ~2 km away — walking/short-hop distance to a major employment hub — a genuine work-near-home location.
| Landmark | Straight-line |
|---|---|
| Lower Parel / Worli business district | 2 km |
| Nariman Point / Fort | 6 km |
| Bandra Kurla Complex (BKC) | 11 km |
| Chhatrapati Shivaji Int'l Airport | 13 km |
| Andheri MIDC / SEEPZ | 18 km |
| Powai / Hiranandani business park | 18 km |
Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.