MahaRERA · the public record
Elanor - Tower 1
Dhokali · LODHA DEVELOPERS LIMITED
Know the project.
Then choose your home.
The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.
The record · free to read
Registration read 12 Jul 2026Progress & dates
The timeline on file.
Available record
No construction trend to plot.
The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.
declared completion
31 Dec 2031
The registered date and a construction update answer different questions. Neither is a confirmation of possession.
MahaRERA registration · read 12 Jul 2026
From another project
See the report before you buy.
A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.
Read a sample report ↗The source record
The details behind the headline.
MahaRERA · P51700046312
Delivery and registration
When is the project declared for completion?
Elanor - Tower 1 is registered with MahaRERA as P51700046312 and the promoter has declared completion for 31 Dec 2031.
31 Dec 2031
declared completion
63months to go
against the declared date
The completion date and status as they stand on the MahaRERA registration record.
Source · MahaRERA project registration · read 12 Jul 2026
| MahaRERA registration | P51700046312 |
| Registered on | 22 Jun 2022 |
| Promoter-declared completion | 31 Dec 2031 |
| Current status | Certificate Signed |
| Against today | 63 months to the declared date |
Approvals and compliance
What compliance filings are on record?
MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for Elanor - Tower 1 record 17 quarterly progress reports since registration.
17quarterly filings
Entries as they appear on MahaRERA's own lists and the project's progress filing.
Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026
- Filing progress reports — 17 quarterly progress reports on record since registration, with no current default.
Construction
How much construction cost has been reported?
In Elanor - Tower 1, ₹5.45 Cr of a declared ₹151.63 Cr estimated project cost is reported as incurred, about 3.6%, as at the last certified filing with MahaRERA.
3.6%
₹5.45 Cr
of ₹151.63 Cr declared cost
Cost incurred as last certified to MahaRERA. It is a financial measure, not a survey of site work, and it can lag on-site reality between filings.
Source · MahaRERA quarterly progress filing · read 12 Jul 2026
Sales
How much has actually been sold?
In Elanor - Tower 1, 0 of 1 homes filed with MahaRERA are recorded as sold or booked, about 0%, and 1 remain available.
0%sold
0 of 1 homes
Counts as the promoter filed them at the last compliance date; this is the filed inventory, not current availability.
Source · MahaRERA sold/unsold inventory filing · read 12 Jul 2026
The units recorded as unsold on the filing. The reckoner value is the government's ready-reckoner assessment the promoter filed against that unit, the figure stamp duty is charged on. It is not a price anyone paid, not an asking price, and not a valuation of the home.
| Floor | Unit | Carpet | Govt reckoner value |
|---|---|---|---|
| Floor 11 | 1103 | 1,176 sqft (109.25 sqm) | ₹1.01 Cr |
No units are declared mortgaged, reserved, investor-held or not-for-sale in this inventory filing.
Sales
Are registered sale-agreement prices available?
No registered sale-agreement price is recorded for Elanor - Tower 1 in the MahaRERA project file.
Not available
This is what the record does not contain, not a value of zero.
Source · MahaRERA project file · checked 12 Jul 2026
Buildings & Wings
The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+0 and 1 homes are registered across the project.
| Building | Wings | Floors | Homes | Declared completion |
|---|---|---|---|---|
| A2 Tower - 1 | 1 | G+0 | 1 | - |
Unit mix on the filing: 1 residential.
Complaints
No buyer complaints were on this project's MahaRERA record at the time of reading.
Legal & Litigation
The promoter has declared 1 court case on this project to MahaRERA. Litigation can cloud the land title or stall the build — have a lawyer pull the cause list for each and confirm whether it touches the title to your home. This is declared by the promoter; there may be further cases not on the RERA record.
| Court | Case no. | Year | Status |
|---|---|---|---|
| - | 1737 | 2016 | Ongoing |
Deadline Extensions
The MahaRERA completion deadline for this project has been formally extended 2 times, as recorded on the register.
| From | Extended to | Stated reason |
|---|---|---|
| as registered | 30 Dec 2030 | Due to management decisions and planning, there was a delay in launching the project even after obtaining the RERA number, which resulted in a late start of construction work. As o |
| 30 Dec 2030 | 31 Dec 2031 | Due to management decisions and planning, there was a delay in launching the project even after obtaining the RERA number, which resulted in a late start of construction work. As o |
Location, Land & Connectivity
Located at Dhokali, Dhokali, Mumbai City, Mumbai City, 400607. Per the filed land record, the plot is bounded to the north by Amenity Plot 5B, to the south by Internal Road, to the east by RG No 1 and to the west by Tower -2. These are the boundaries as recorded in the filed land record.