MahaRERA Property Intelligence · Mumbai Suburban

GUNDECHA GREENS PHASE 1

P51800001863 · NG Suncity Phase-III, Janupada, Huzefa Nagar · promoter Kashtamandup Developers Pvt

Certificate SignedDue 30 Dec 2022

Delivery & Registration

MahaRERA registrationP51800001863
Registered on29 Jul 2017
Promoter-declared completion30 Dec 2022
Current statusCertificate Signed
Against todayabout 43 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+17.

BuildingWingsFloorsDeclared completion
GUNDECHA GREENS1G+17-

Complaints & Orders

3 complaints are on the MahaRERA record for this project, with orders passed in 3. An adjudicated complaint is the clearest evidence of how this promoter behaves when pushed — read the orders in full.

Complaint no.FiledPartiesStatus
CC00600000009016308/08/2019Range Forest Officer Tulsi vs Kashtamandup Developers Pvt. Ltd.order passed
CC00600000019675122/04/2021NAVEEN KOILA RAO vs Kashtamandup developers pvt. ltdorder passed
CC00600000019678825/04/2021Krishna Parab vs Kashtamandup Developers Pvt. Ltd.order passed

Location, Land & Connectivity

Located at NG Suncity Phase-III, Janupada, Huzefa Nagar, Thakur Village Road, Andheri, Mumbai Suburban, 400101. Per the filed land record, the plot is bounded to the north by Survey no 874-D-2, to the south by Survey no 874-C-10, to the east by Partly by survey no 874-B-1 and survey no 874-C-9 and to the west by Partly by survey no 874-C-6 and survey no 874-C-7. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~9 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Andheri MIDC / SEEPZ9 km
Powai / Hiranandani business park10 km
Chhatrapati Shivaji Int'l Airport13 km
Bandra Kurla Complex (BKC)16 km
Lower Parel / Worli business district24 km
Nariman Point / Fort32 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Kandivali East

Lodha Kandivali Project - Tower 2
possession by Jul 2026 · Lodha Developers Limited
Lodha Kandivali Project - Tower 5
possession by Jul 2026 · Lodha Developers Limited
Vanrai
possession by Jul 2026 · Kaustubh Construction Private Limited
Kanchangiri
possession by Sep 2026 · Goodwill Builders
Aspire
possession by Oct 2026 · M/s Radheshyam Developers
Grande Edifice
possession by Dec 2026 · V6 Enterprises

Major developers building in Kandivali East

Other RERA-registered projects in Mumbai Suburban

Gundecha Rexon Suites Phase 1
possession by Oct 2028 · Anaya Infrastructure PVT LTD
Gundecha Trillium
declared completion Dec 2017 · SEA Princess Realty
Gurbani B
declared completion Jul 2018 · Heena Construction Co
Gurnani Palms Wing A
declared completion Dec 2018 · Interintel Constructions
Guru Ashish
possession by Mar 2027 · Shivcorp Infra OPC Private Limited
Guru Dwarka
possession by Jun 2027 · Bsrd Infrabuild Private Limited

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026