Mumbai/Project record

MahaRERA · the public record

Horizon

Mumbai Suburban · JAYCEE HOMES PRIVATE LIMITED

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

31 Jul 2019declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Jul 2019

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51800007713

Delivery and registration

When is the project declared for completion?

Horizon is registered with MahaRERA as P51800007713 and the promoter has declared completion for 31 Jul 2019.

31 Jul 2019

declared completion

86months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51800007713
Registered on17 Aug 2017
Promoter-declared completion31 Jul 2019
Current statusCertificate Signed
Against todayabout 86 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for Horizon record 9 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 9 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Jaycee Homes is the promoter of record on 4 projects registered with MahaRERA, 1 of which carries a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

4projects

registered with MahaRERA

1flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for Horizon in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+16.

BuildingWingsFloorsDeclared completion
Horizon1G+1631 Jul 2019

Legal and disputes

What disputes are disclosed?

23 complaints are on the MahaRERA record for Horizon, with orders passed in 23 of them.

23complaints

23with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 12 Jul 2026

Complaint no.FiledPartiesStatus
CC00600000004422024/04/2018Kaushal Kishore HUF through Karta Kaushal Kishore vs M/S Jaycee Homes Private Limitedorder passed
CC00600000005531523/07/2018Kaushal Kishore HUF vs M/s. Jaycee Homes Private Limitedorder passed
CC00600000005531623/07/2018Dr.Akbar Mehdi vs M/s. Jaycee Homes Private Limitedorder passed
CC00600000005531723/07/2018Das ARITRA vs M/s. Jaycee Homes Private Limitedorder passed
CC00600000005531823/07/2018Manoj Kumar Mistry vs M/s.jaycee Homes Private Limitedorder passed
CC00600000005531923/07/2018Pinki Kishore vs M/s.Jaycee Homes Private Limitedorder passed
CC00600000005532023/07/2018Shyam Sunder Kedia HuF vs M/s. Jaycee Homes Private Limitedorder passed
CC00600000005532123/07/2018Om Prakash Bharodia vs M/s.Jaycee Homes Private Limitedorder passed
CC00600000005532223/07/2018Ankit Kantilal Dama vs M/s.Jaycee Homes Private Limitedorder passed
CC00600000005532323/07/2018Pratik Brijesh Mittai vs M/s.Jaycee Homes Private Limitedorder passed
CC00600000005532423/07/2018Narendra S MORIANI vs M/s.Jaycee Homes Private Limitedorder passed
CC00600000005532523/07/2018Mukesh Pursnani vs M/s.Jaycee Homes Private Limitedorder passed
CC00600000005532623/07/2018REVATI KARANDE vs M/s.Jaycee Homes Private Limitedorder passed
CC00600000005532723/07/2018Deep OMPRAKASH SHUKLA vs M/s.Jaycee Homes Private Limitedorder passed
CC00600000005532823/07/2018Tarun Chaudhary vs M/s.Jaycee Homes Private Limitedorder passed
CC00600000005544114/02/2019Ankur Sudrania vs Jaycee Homes Private Limitedorder passed
CC00600000005545723/07/2018Mohammed Tarique Sayed vs Jaycee Homes Ltdorder passed
CC00600000005676714/02/2019Vivek Ramesh Bhat vs Jaycee Homes Private Ltd.order passed
CC00600000005676814/02/2019Vilas Ravindra Belwalkar vs Jaycee Homes Pvt. Ltdorder passed
CC00600000005676914/02/2019Nitin Prabhu vs Jaycee Homes Private Limitedorder passed
CC00600000005729514/02/2019Shweta Omkar Parab vs M/s. Jaycee Homes private Limitedorder passed
CC00600000017164429/01/2020Mr. Varun Kurlawala & Mrs. Saroj Kurlawala vs Jaycee Homes Private Limitedorder passed
CC00600000000095402/11/2017SHYAM SUNDER KEDIA HUF vs Jaycee Homes Ltd - Mukesh Bhagtani & Dipesh Bhagtaniorder passed

Location, Land & Connectivity

Located at Andheri, Mumbai Suburban, 400063. Per the filed land record, the plot is bounded to the north by Aarey Road, to the south by CTS No 279, to the east by CTS No 281 and to the west by Adjusting road. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~4 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Andheri MIDC / SEEPZ4 km
Powai / Hiranandani business park7 km
Chhatrapati Shivaji Int'l Airport9 km
Bandra Kurla Complex (BKC)11 km
Lower Parel / Worli business district19 km
Nariman Point / Fort27 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Jaycee Homes Private Limited is the promoter on 4 MahaRERA-registered projects, of which 1 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

Other flagged projects by Jaycee Homes Private Limited

Jaycee Homes Private Limited
FlaggedMumbai Suburban

Other RERA-registered projects in Goregaon East

Matrusmruti
possession by Oct 2026 · Gio Properties
Samarth Nandadeep Heights
possession by Oct 2026 · Samarth Tsquare
Onyx
possession by Nov 2026 · Shreeram Builders
Goregaon Adwait Chsl - Vijay Sadan
possession by Dec 2026 · Prashant Shirsat
Agarwal Floresta - Maple
possession by Dec 2026 · Homewell Realty LLP
Ashwin Heights
possession by Dec 2026 · Westinrely Developers PVT LTD

Major developers building in Goregaon East

Other RERA-registered projects in Mumbai Suburban

Horizon
declared completion Nov 2025 · Ajanta Airavat Infrastructure Limited Li
Horizon Atulya
declared completion Jun 2026 · Horizon Promoters India LTD
Horizon Garden View
possession by Nov 2026 · Horizon Promoters India LTD
Horizon Heights
declared completion Mar 2026 · I.r.developers LLP
Horizon Homes
declared completion Aug 2022 · Horizon Dream Homes Private Limited
Horizon Nitya
possession by Jun 2028 · Horizon Promoters India LTD

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.