MahaRERA Property Intelligence · Thane

KALYAN NAGARI

P51700016054 · BHIWANDI · promoter Honest Developers

Certificate SignedDue 30 Mar 2024

Delivery & Registration

MahaRERA registrationP51700016054
Registered on13 Apr 2018
Promoter-declared completion30 Mar 2024
Current statusCertificate Signed
Against todayabout 28 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Honest Developers is the promoter of record on 9 projects, of which none currently carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+14.

BuildingWingsFloorsDeclared completion
DAFFODIL AND DREAM FLOWER1G+14-
DAISY1G+11-

Complaints & Orders

1 complaint is on the MahaRERA record for this project, with orders passed in 1. An adjudicated complaint is the clearest evidence of how this promoter behaves when pushed — read the orders in full.

Complaint no.FiledPartiesStatus
CC00600000057081409/07/2024M/S HONEST DEVELOPERS vs ANITA TIRTHRAJ DUBEYorder passed

Deadline Extensions

The promoter has had the MahaRERA completion deadline formally extended 1 time. Each extension is the regulator letting the finish line move — the clearest evidence of delivery slippage, straight from the record.

From (declared)To (revised)Stated reason
30 Mar 202430 Sep 2023Due to Covid-19 the project was not able to get completed in time. We would like to request you to further grant us extension for 12 months

Location, Land & Connectivity

Located at BHIWANDI, KON VILLAGE, Mumbai City, Mumbai City, 421302. Per the filed land record, the plot is bounded to the north by SURVEY NO 200, to the south by SURVEY NO 193, to the east by SURVEY NO 193 and to the west by SURVEY NO 193. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~26 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Powai / Hiranandani business park26 km
Andheri MIDC / SEEPZ28 km
Chhatrapati Shivaji Int'l Airport31 km
Bandra Kurla Complex (BKC)32 km
Lower Parel / Worli business district41 km
Nariman Point / Fort47 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Honest Developers is the promoter on 2 MahaRERA-registered projects, with none currently carrying a regulator flag — a reassuring wider track record (matched on the promoter name in the register; it doesn't guarantee this specific project, but a clean portfolio is a good sign).

Other flagged projects by Honest Developers

Other RERA-registered projects in Bhiwandi

Neelkanth Sadan
possession by Jul 2026 · Shreeji Enterprises
Hill Spring
possession by Aug 2026 · Asha Infratech
Nazir Heights
possession by Sep 2026 · A M Constructions
Rose Residency
possession by Sep 2026 · Kunal Ramesh Karaniya
Saniya Heights
possession by Sep 2026 · Moonshine Realtors PVT LTD
Upper Thane-Casa Eden
possession by Sep 2026 · Lodha Developers Limited

Major developers building in Bhiwandi

Other RERA-registered projects in Thane

Kalyan Orchid
possession by Jun 2031 · S K Properties
Kalyan Rajashree Cooperative Housing Society LTD
possession by Dec 2028 · SAI Jagat Buildcon
Kalyan Residency
possession by Dec 2028 · SM Life Space Private Limited
Kalyan Square
possession by Dec 2027 · Kagvin Ventures
Kalyan Surabhi
declared completion Jun 2026 · Kalyan Buildcon
Kalyan Vatika
possession by Dec 2027 · Kalyan Avenue

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.