Mumbai/Project record

MahaRERA · the public record

Keshavpada

Mulund West · Namah Realtor

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

61units filed as unsoldInventory · 16 September 2026
31 Dec 2025declared completionMahaRERA registration · read 12 Jul 2026
207registered unitsMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Dec 2025

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51800009189

Delivery and registration

When is the project declared for completion?

Keshavpada is registered with MahaRERA as P51800009189 and the promoter has declared completion for 31 Dec 2025.

31 Dec 2025

declared completion

9months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51800009189
Registered on22 Aug 2017
Promoter-declared completion31 Dec 2025
Current statusCertificate Signed
Against todayabout 9 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for Keshavpada record 34 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Current QPR default — the promoter has stopped filing the mandatory quarterly progress report (FY 2025-2026).

Promoter record

What else is this promoter on record for?

Namah Realtor is the promoter of record on 9 projects registered with MahaRERA, 2 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

9projects

registered with MahaRERA

2flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

How much has actually been sold?

In Keshavpada, 20 of 84 homes filed with MahaRERA are recorded as sold or booked (14 with registered agreements and 6 booked), about 24%, and 64 remain available.

24%sold

20 of 84 homes

₹17.89 Cr

committed by buyers

Counts and agreement value as the promoter filed them at the last compliance date; this is the filed inventory, not current availability. Of that agreement value, ₹9.52 Cr (about 53%) is recorded as collected and ₹8.37 Cr as receivable. The project registers 207 homes in total, while this sold/unsold inventory filing covers 84 of them.

Source · MahaRERA sold/unsold inventory filing · read 12 Jul 2026

What buyers actually paid: across 20 registered agreements, the effective carpet rate is ₹14,868/sqft, with eight in ten falling between ₹13,572 and ₹16,381 — computed from the agreement values and carpet areas the promoter filed, not broker quotes.

The inventory filing also declares: 123 reserved.

What the filings record, home by home

Read from MahaRERA on 16 September 2026

MahaRERA publishes, home by home, what this promoter filed: which homes are sold and which are not, the RERA carpet area of each, and for the sold ones the registered agreement value — the consideration filed for that specific home. On this project 23 homes carry one, and 61 of the 207 are recorded unsold. Since we started watching this ledger, 3 homes have moved out of the unsold list, most recently on 08 September 2026.

Here is one of those unsold homes, priced against what buyers of the same home on other floors actually filed:

HomeCarpetFiled for the same home on other floorsBased on
1802659 sqftRs 1.0108 cr typical, over Rs 88.00 lakh to Rs 1.1160 cr14 filed at this size

A filed consideration is what was registered for one home. It is not a valuation, and MahaRERA does not publish the date of any of these agreements — read a range as a spread, not as a trend. An unsold row means no sale had been filed for it when we looked, which is a filing state, not a promise that the home is available to you today. One of the two observations is an archived copy whose time is the moment the file was written, not a portal fetch time.

In Keshavpada, every one of the 61 unsold homes has agreements filed on its own stack. The Price Comparison Report gives each of them its own row — the filed agreements behind that stack listed in full, the government reckoner value the promoter filed against it, and whether it is mortgaged to a lender while still on the unsold list. Built from the filing itself, sent by email.

See the other 60 homes — ₹2,999 →

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+29 and 207 homes are registered across the project.

BuildingWingsFloorsHomesDeclared completion
Keshavpada1G+1212330 Dec 2023
Orchid Solitaire1G+298430 Dec 2023

Unit mix on the filing: 207 residential.

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 2 times, as recorded on the register.

FromExtended toStated reason
as registered30 Jun 2023We have obtained amended plans and re-endorsed CC attached following which COVID affected our work. We request you to issue us an extension towards completion of work. Kindly oblig
30 Jun 202331 Dec 2025Obtained further CC on 4th September 2023 (cc copy enclosed). We have obtained consent in the prescribed format from more than 51% allottee/s. Kindly oblige.

Location, Land & Connectivity

Located at Mulund West, P.K.Road, Borivali, Mumbai Suburban, 400080. Per the filed land record, the plot is bounded to the north by CTS 1111, to the south by CTS 1115, to the east by CTS 1480 and to the west by SAS Boundary of Village Nahur. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~7 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Powai / Hiranandani business park7 km
Andheri MIDC / SEEPZ9 km
Chhatrapati Shivaji Int'l Airport13 km
Bandra Kurla Complex (BKC)14 km
Lower Parel / Worli business district23 km
Nariman Point / Fort30 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Mulund West

AAI Satidevi Paradise
possession by Sep 2026 · Shreenath Developers
Laizer Elegance
Not filing quarterly progress reports · possession by Sep 2026 · Laizer Builders & Developers
THE NEW Anand Deep CHS LTD
possession by Sep 2026 · Shreejee Buildcon
Tirupati Apartments Chsl
possession by Oct 2026 · Tirupati Aparmtnets CO Operative Housing
Horizon Garden View
possession by Nov 2026 · Horizon Promoters India LTD
Montana Phase - 3
possession by Dec 2026 · Lohitka Properties LLP

Major developers building in Mulund West

Other RERA-registered projects in Mumbai Suburban

Keva
possession by Nov 2027 · Pinal Realty LLP
Kevli Plaza – A Wing AND Kevli Darshan – B Wing
possession by Dec 2028 · M/s R K AND Company PVT LTD
KEY Tech Park
possession by Dec 2026 · M/s Keytech
Khadija Hitech Tower
declared completion Dec 2021 · Hitech Hafizi Town Developers
Khaliliya Complex
possession by Dec 2026 · Dani Builders AND Developers
Khandelwal Acropolis
possession by Dec 2030 · Shree Krishna SAI Development Corporatio

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026