MahaRERA · the public record
LODHA AMARA - TOWER 1 - 5, 7 - 19
. · LODHA DEVELOPERS LIMITED
Know the project.
Then choose your home.
The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.
The record · free to read
Registration read 12 Jul 2026Progress & dates
The timeline on file.
Available record
No construction trend to plot.
The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.
declared completion
30 Nov 2019
The registered date and a construction update answer different questions. Neither is a confirmation of possession.
MahaRERA registration · read 12 Jul 2026
From another project
See the report before you buy.
A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.
Read a sample report ↗The source record
The details behind the headline.
MahaRERA · P51700001065
Delivery and registration
When is the project declared for completion?
LODHA AMARA - TOWER 1 - 5, 7 - 19 is registered with MahaRERA as P51700001065 and the promoter has declared completion for 30 Nov 2019.
30 Nov 2019
declared completion
82months past
against the declared date
The completion date and status as they stand on the MahaRERA registration record.
Source · MahaRERA project registration · read 12 Jul 2026
| MahaRERA registration | P51700001065 |
| Registered on | 25 Jul 2017 |
| Promoter-declared completion | 30 Nov 2019 |
| Current status | Certificate Signed |
| Against today | about 82 months past the declared date |
Approvals and compliance
What compliance filings are on record?
MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for LODHA AMARA - TOWER 1 - 5, 7 - 19 record 10 quarterly progress reports since registration.
10quarterly filings
Entries as they appear on MahaRERA's own lists and the project's progress filing.
Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026
- Filing progress reports — 10 quarterly progress reports on record since registration, with no current default.
Sales
Are registered sale-agreement prices available?
No registered sale-agreement price is recorded for LODHA AMARA - TOWER 1 - 5, 7 - 19 in the MahaRERA project file.
Not available
This is what the record does not contain, not a value of zero.
Source · MahaRERA project file · checked 12 Jul 2026
Buildings & Wings
The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+29.
| Building | Wings | Floors | Declared completion |
|---|---|---|---|
| TOWER 1 | 1 | G+27 | 30 Nov 2019 |
| TOWER 2 | 1 | G+27 | 30 Nov 2019 |
| TOWER 3 | 1 | G+27 | 30 Nov 2019 |
| TOWER 4 | 1 | G+27 | 30 Nov 2019 |
| TOWER 5 | 1 | G+27 | 30 Nov 2019 |
| TOWER 7 | 1 | G+27 | 30 Nov 2019 |
| TOWER 8 | 1 | G+27 | 30 Nov 2019 |
| TOWER 9 | 1 | G+27 | 30 Nov 2019 |
| TOWER 10 | 1 | G+27 | 30 Nov 2019 |
| TOWER 11 | 1 | G+27 | 30 Nov 2019 |
| TOWER 12 | 1 | G+27 | 30 Nov 2019 |
| TOWER 13 | 1 | G+27 | 30 Nov 2019 |
| TOWER 14 | 1 | G+27 | 30 Nov 2019 |
| TOWER 15 | 1 | G+27 | 30 Nov 2019 |
| TOWER 16 | 1 | G+27 | 30 Nov 2019 |
| TOWER 17 | 1 | G+29 | 30 Nov 2019 |
| TOWER 18 | 1 | G+29 | 30 Nov 2019 |
| TOWER 19 | 1 | G+29 | 30 Nov 2019 |
Legal and disputes
What disputes are disclosed?
24 complaints are on the MahaRERA record for LODHA AMARA - TOWER 1 - 5, 7 - 19 , with orders passed in 24 of them.
24complaints
24with an order
Counts as disclosed in the project record.
Source · MahaRERA project disclosures · read 12 Jul 2026
| Complaint no. | Filed | Parties | Status |
|---|---|---|---|
| CC006000000000663 | 02/10/2017 | SANJAY SAWANT vs Lodha developrs thane pvt ltd | order passed |
| CC006000000000670 | 20/09/2017 | SACHIN DANDEKAR vs LODHA DEVELOPERS THANE PVT LTD | order passed |
| CC006000000000713 | 05/11/2017 | Surendra V Rawool vs Lodha Amara | order passed |
| CC006000000000750 | 31/12/2017 | Linal Prasenjit Mohite vs Pratik Maurya | order passed |
| CC006000000079343 | 22/05/2019 | Swapnil Kamble vs Macrotech Developers Limited | order passed |
| CC006000000100363 | 01/08/2019 | Nilesh Sadashiv Sonawane vs Macrotech developers limited | order passed |
| CC006000000100367 | 01/08/2019 | Vipin D Ratnaparkhi vs Macrotech developers Limited | order passed |
| CC006000000100368 | 01/08/2019 | SANJIV P. CHAUDHARY vs Macrotech developers limted | order passed |
| CC006000000100373 | 02/08/2019 | Dhiroj K Barad vs Macrotech Developers limited | order passed |
| CC006000000100377 | 02/08/2019 | Vaibhav Narkar vs Macrotech developers limited | order passed |
| CC006000000192699 | 21/02/2020 | Rohil Julaniya vs Macrotech Developers ltd. | order passed |
| CC006000000012749 | 08/01/2018 | CHINMAYA MOHANTY vs LODHA | order passed |
| CC006000000044449 | 11/05/2018 | Dipti Rishabh Arjaria vs LODHA GROUP | order passed |
| CC006000000055764 | 14/09/2018 | Surendra Ramchandra Gurav vs Ishwer Realty and Technologies pvt ltd | order passed |
| CC006000000056148 | 23/09/2018 | SRINIVAS G DASARI vs ANKIT CHANDAK | order passed |
| CC006000000057576 | 07/01/2019 | Sureshkumar Singh vs Lodha Developers Limited | order passed |
| CC006000000057313 | 14/12/2018 | Nutan Lohiya vs Bellismo Developers Pvt Ltd | order passed |
| CC006000000057315 | 14/12/2018 | NUTAN LOHIYA vs Bellissmo Developers Thane Pvt Ltd | order passed |
| CC006000000195952 | 11/02/2021 | CASA FRESCO F TO J CO-OPERATIVE HOUSING SOCIETY LIMITED (society) vs MACROTECH DEVELOPERS LIMITED | order passed |
| CC006000000057829 | 25/01/2019 | PRASHANT MANE vs lodha developer | order passed |
| CC006000000058097 | 14/02/2019 | CHANDAN PREMCHANDANI vs BELLISSIMO DEVELOPERS THANE PRIVATE LIMITED (earlier known as LODHA DEVELOPERS THANE PRIVATE LIMITED | order passed |
| CC006000000354329 | 20/02/2023 | Casa Fresco A to E Co-operative Housing Society (society) vs Macrotech Developers Limited erstwhile name Lodha Developers Ltd. | order passed |
| CC006000000171517 | 14/11/2019 | Casa Fresco A to E Co-operative Housing Society Ltd (society) vs Macrotech Developers Limited | order passed |
| CC12501481 | 02/05/2025 | Hitesh Agarwal vs MACROTECH DEVELOPERS LIMITED | order passed |
A co-operative housing society is recorded as the complainant (CASA FRESCO F TO J CO-OPERATIVE HOUSING SOCIETY LIMITED), and MahaRERA has passed an order.
Legal & Litigation
The promoter has declared 2 court cases on this project to MahaRERA. Litigation can cloud the land title or stall the build — have a lawyer pull the cause list for each and confirm whether it touches the title to your home. This is declared by the promoter; there may be further cases not on the RERA record.
| Court | Case no. | Year | Status |
|---|---|---|---|
| Bombay High Court | 290 | 2016 | Pre Admission |
| Bombay High Court | 1737 | 2016 | Pre Admission |
Location, Land & Connectivity
Located at ., ., Mumbai City, Mumbai City, 400607. Per the filed land record, the plot is bounded to the north by Industrial Area, to the south by 30m HCMTR, to the east by 30m DP Road and to the west by 30 m HCMTR. These are the boundaries as recorded in the filed land record.
Location & connectivity
The nearest major job hub is ~16 km away — a real but liveable commute to the nearest job hub — factor peak-hour traffic.
| Landmark | Straight-line |
|---|---|
| Powai / Hiranandani business park | 16 km |
| Andheri MIDC / SEEPZ | 17 km |
| Chhatrapati Shivaji Int'l Airport | 21 km |
| Bandra Kurla Complex (BKC) | 22 km |
| Lower Parel / Worli business district | 31 km |
| Nariman Point / Fort | 38 km |
Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.