MahaRERA Property Intelligence · Thane

Lodha Amara - Tower 36 37

P51700013961 · . · promoter Lodha

Certificate SignedDue 30 Dec 2022

Delivery & Registration

MahaRERA registrationP51700013961
Registered on02 Nov 2017
Promoter-declared completion30 Dec 2022
Current statusCertificate Signed
Against todayabout 43 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+28.

BuildingWingsFloorsDeclared completion
Tower 361G+2831 Dec 2021
Tower 371G+2831 Dec 2021

Complaints & Orders

3 complaints are on the MahaRERA record for this project, with orders passed in 3. An adjudicated complaint is the clearest evidence of how this promoter behaves when pushed — read the orders in full.

Complaint no.FiledPartiesStatus
CC00600000001218728/11/2017Panchali Chakraborty vs Pratik Mauryaorder passed
CC00600000019685130/04/2021Amit Vijay Patil vs M/s.Macrotech Developers Ltdorder passed
CC1250424301/12/2025LODHA DEVELOPERS LIMITED vs Adhik S Pawarorder passed

Legal & Litigation

The promoter has declared 2 court cases on this project to MahaRERA. Litigation can cloud the land title or stall the build — have a lawyer pull the cause list for each and confirm whether it touches the title to your flat. This is declared by the promoter; there may be further cases not on the RERA record.

CourtCase no.YearStatus
Bombay High Court17372016Pre Admission
Bombay High Court2902016Pre Admission

Location, Land & Connectivity

Located at ., ., Mumbai City, Mumbai City, 400607. Per the filed land record, the plot is bounded to the north by Internal Road, to the south by Wing - W29 W30, to the east by Internal Road and to the west by Wing - W35. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~16 km away — a real but liveable commute to the nearest job hub — factor peak-hour traffic.

LandmarkStraight-line
Powai / Hiranandani business park16 km
Andheri MIDC / SEEPZ17 km
Chhatrapati Shivaji Int'l Airport21 km
Bandra Kurla Complex (BKC)22 km
Lower Parel / Worli business district31 km
Nariman Point / Fort38 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Lodha Developers Limited is the promoter on 171 MahaRERA-registered projects, of which 9 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

See every Lodha Developers Limited project & its RERA track record →

Other flagged projects by Lodha Developers Limited

Lodha Developers Limited
FlaggedThane
Lodha Developers Limited
FlaggedThane
Lodha Developers Limited
FlaggedThane
Lodha Developers Limited
FlaggedThane
Lodha Developers Limited
FlaggedThane
Lodha Developers Limited
FlaggedThane

Other RERA-registered projects in Thane

Godrej Exquisite
possession by Sep 2026 · Godrej Macbricks Private Limited
Lodha Crown Kolshet-Tower 1
possession by Sep 2026 · Lodha Developers Limited
Odysseus
possession by Sep 2026 · Sagar Enterprise
Unique Vistas Mhada Building NO. 1,2,3
possession by Sep 2026 · Madhu Harshad Doshi
Unique Vistas Mhada Buildingno. 4 5 6 7
possession by Sep 2026 · Madhu Harshad Doshi
Daffodil
possession by Dec 2026 · Shree Tirupati Greenfield Developers

Major developers building in Thane

Other RERA-registered projects in Thane

Lodha Amara - Tower 38 And 39
declared completion Jul 2024 · Lodha Developers Limited
Lodha Amara -Tower 42 And 43
possession by Dec 2027 · Lodha Developers Limited
Lodha Amara Tower 44
possession by Jun 2028 · Lodha Developers Limited
Lodha Amara - Tower 45
declared completion Jul 2024 · Lodha Developers Limited
Lodha Amara - Tower 46
declared completion Jul 2024 · Lodha Developers Limited
Lodha Amara Tower 47 And 48
possession by Jun 2029 · Lodha Developers Limited

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026