30 Jun 2028declared completionMahaRERA registration · read 12 Jul 2026
13registered unitsMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Jun 2028

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · PR1180002500362

Delivery and registration

When is the project declared for completion?

MARU MANSION is registered with MahaRERA as PR1180002500362 and the promoter has declared completion for 30 Jun 2028.

30 Jun 2028

declared completion

21months to go

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationPR1180002500362
Registered on25 Jul 2025
Promoter-declared completion30 Jun 2028
Current statusCertificate Signed
Against today21 months to the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for MARU MANSION record 1 quarterly progress report since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Filing progress reports — 1 quarterly progress report on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Ferro Build is the promoter of record on 5 projects registered with MahaRERA, none of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

5projects

registered with MahaRERA

0flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Construction

How much construction cost has been reported?

In MARU MANSION, ₹1.26 Cr of a declared ₹1.89 Cr estimated project cost is reported as incurred, about 66.7%, as at the last certified filing with MahaRERA.

66.7%

₹1.26 Cr

of ₹1.89 Cr declared cost

Cost incurred as last certified to MahaRERA. It is a financial measure, not a survey of site work, and it can lag on-site reality between filings.

Source · MahaRERA quarterly progress filing · read 12 Jul 2026

Sales

How much has actually been sold?

In MARU MANSION, 0 of 1 homes filed with MahaRERA are recorded as sold or booked, about 0%, and 1 remain available.

0%sold

0 of 1 homes

Counts as the promoter filed them at the last compliance date; this is the filed inventory, not current availability. The project registers 13 homes in total, while this sold/unsold inventory filing covers 1 of them.

Source · MahaRERA sold/unsold inventory filing · read 12 Jul 2026

The units recorded as unsold on the filing. The reckoner value is the government's ready-reckoner assessment the promoter filed against that unit, the figure stamp duty is charged on. It is not a price anyone paid, not an asking price, and not a valuation of the home.

FloorUnitCarpetGovt reckoner value
Floor 1102388 sqft (36.07 sqm)₹53.23 Lakh

The inventory filing also declares: 2 not for sale.

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for MARU MANSION in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+5 and 13 homes are registered across the project.

BuildingWingsFloorsHomesDeclared completion
MARU MANSION1G+513-

Unit mix on the filing: 13 residential.

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Location, Land & Connectivity

Located at MALAD WEST, Mamledarwadi road No.6, Andheri, Mumbai Suburban, 400064. Per the filed land record, the plot is bounded to the north by By CTS No. 789,788 & 792, to the south by By 9.15 M WIDE PUBLIC ROAD., to the east by By CTS No. 797 and to the west by By CTS No. 790. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~7 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Andheri MIDC / SEEPZ7 km
Powai / Hiranandani business park10 km
Chhatrapati Shivaji Int'l Airport11 km
Bandra Kurla Complex (BKC)14 km
Lower Parel / Worli business district21 km
Nariman Point / Fort29 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Ferro Build is the promoter on 4 MahaRERA-registered projects, with none currently carrying a regulator flag — a reassuring wider track record (matched on the promoter name in the register; it doesn't guarantee this specific project, but a clean portfolio is a good sign).

Other flagged projects by Ferro Build

Ferro Build
FlaggedMumbai Suburban
Ferro Build
FlaggedMumbai Suburban

Other RERA-registered projects in Malad West

Shree Hari Krupa
possession by Sep 2026 · Mamtora Foundation
Shreeji Plaza Wing B
possession by Sep 2026 · Siddharth Enterprises
Linkpark
possession by Oct 2026 · Adarsh Industrial Estate Private Limited
Bhagat Grandeur
possession by Dec 2026 · Chirag Agro Fins Private Limited
Liberty Heights
possession by Dec 2026 · VP Casa Constructions LLP
Lovely Chs. LTD
possession by Dec 2026 · Jinam Realtors

Major developers building in Malad West

Other RERA-registered projects in Mumbai Suburban

Maruti
declared completion Mar 2024 · Invention Realtors Private Limited
Maruti
possession by Sep 2027 · Sarvoday Builders And Developers
Maruti Bhuvan
declared completion Mar 2024 · Suresh Prabhushankar Sharma
Maruti Residency
possession by Dec 2026 · OM Construction
Marve Apartment CHS LTD
declared completion Dec 2023 · OM SRI MAA Shakti I Namah
Marvel Gold - Phase II - Colloseum
declared completion Oct 2024 · Swaroop Constructions Private Limited

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026