Mumbai/Project record

MahaRERA · the public record

MONTANA PHASE - 2

MULUND · LOHITKA PROPERTIES LLP

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

26units filed as unsoldInventory · 12 September 2026
30 Dec 2024declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Dec 2024

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51800014539

Delivery and registration

When is the project declared for completion?

MONTANA PHASE - 2 is registered with MahaRERA as P51800014539 and the promoter has declared completion for 30 Dec 2024.

30 Dec 2024

declared completion

21months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51800014539
Registered on08 Dec 2017
Promoter-declared completion30 Dec 2024
Current statusCertificate Signed
Against todayabout 21 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for MONTANA PHASE - 2 record 29 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 29 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Lohitka Properties Llp is the promoter of record on 4 projects registered with MahaRERA, 1 of which carries a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

4projects

registered with MahaRERA

1flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

What the filings record, home by home

Read from MahaRERA on 12 September 2026

MahaRERA publishes, home by home, what this promoter filed: which homes are sold and which are not, the RERA carpet area of each, and for the sold ones the registered agreement value — the consideration filed for that specific home. On this project 124 homes carry one, and 26 of the 150 are recorded unsold.

Here is one of those unsold homes, priced against what buyers of the same home on other floors actually filed:

HomeCarpetFiled for the same home on other floorsBased on
1041,065 sqftRs 2.3450 cr typical, over Rs 1.8472 cr to Rs 3.0950 cr33 filed on this stack, floors 2–39

A filed consideration is what was registered for one home. It is not a valuation, and MahaRERA does not publish the date of any of these agreements — read a range as a spread, not as a trend. An unsold row means no sale had been filed for it when we looked, which is a filing state, not a promise that the home is available to you today. Only one observation of this ledger so far: no change can be reported yet.

In MONTANA PHASE - 2, 25 of the 26 unsold homes have agreements filed on their own stack. The Price Comparison Report gives each of them its own row — the filed agreements behind that stack listed in full, the government reckoner value the promoter filed against it, and whether it is mortgaged to a lender while still on the unsold list. Built from the filing itself, sent by email.

See the other 25 homes — ₹2,999 →

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+44.

BuildingWingsFloorsDeclared completion
SIERRA1G+44-

Legal and disputes

What disputes are disclosed?

2 complaints are on the MahaRERA record for MONTANA PHASE - 2, with orders passed in 1 of them.

2complaints

1with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 12 Jul 2026

Complaint no.FiledPartiesStatus
CC00600000007819821/02/2019Mr. Jimit B. Mehta & Mr. Bipinchandra S. Mehta vs Lohitka Properties LLPorder passed
CC1240042016/10/2024Leena Thakker vs LOHITKA PROPERTIES LLPpending / no order on file

Location, Land & Connectivity

Located at MULUND, LBS ROAD, Andheri, Mumbai Suburban, 400080. Per the filed land record, the plot is bounded to the north by MS NATIONAL SCHRADER DUNCAN LTD, to the south by 18 MTR WIDE DP ROAD AS PER DP PLAN OF MCGM, to the east by LBS ROAD and to the west by TANSA PIPELINE. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~7 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Powai / Hiranandani business park7 km
Andheri MIDC / SEEPZ8 km
Chhatrapati Shivaji Int'l Airport12 km
Bandra Kurla Complex (BKC)14 km
Lower Parel / Worli business district22 km
Nariman Point / Fort30 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Lohitka Properties LLP is the promoter on 4 MahaRERA-registered projects, of which 1 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

Other flagged projects by Lohitka Properties LLP

Lohitka Properties LLP
FlaggedMumbai Suburban
Lohitka Properties LLP
FlaggedMumbai Suburban

Other RERA-registered projects in Mulund West

AAI Satidevi Paradise
possession by Sep 2026 · Shreenath Developers
Laizer Elegance
Not filing quarterly progress reports · possession by Sep 2026 · Laizer Builders & Developers
THE NEW Anand Deep CHS LTD
possession by Sep 2026 · Shreejee Buildcon
Tirupati Apartments Chsl
possession by Oct 2026 · Tirupati Aparmtnets CO Operative Housing
Horizon Garden View
possession by Nov 2026 · Horizon Promoters India LTD
Montana Phase - 3
possession by Dec 2026 · Lohitka Properties LLP

Major developers building in Mulund West

Other RERA-registered projects in Mumbai Suburban

Montana Phase - 3
possession by Dec 2026 · Lohitka Properties LLP
Montana Phase - 4
possession by Dec 2026 · Lohitka Properties LLP
Monte Verita North Annexe
declared completion Sep 2025 · M/s B G Shirke Redevelopment And Gas Pvt
Monte Verita West Tower
possession by Mar 2027 · B G Shirke Redevelopment And GAS P L
Moongipa Arcade
possession by Dec 2028 · Moongipa Realty Private Limited
Moongipa Landmark
declared completion Oct 2018 · Moongipa Realty Private Limited

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026