Neptune Florencia

Mulund West · Sachin M Deshmukh and Nayan A Bheda (AOP)

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 Oct 2021declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Oct 2021

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51800002376

Delivery and registration

When is the project declared for completion?

Neptune Florencia is registered with MahaRERA as P51800002376 and the promoter has declared completion for 30 Oct 2021.

30 Oct 2021

declared completion

59months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51800002376
Registered on31 Jul 2017
Promoter-declared completion30 Oct 2021
Current statusCertificate Signed
Against todayabout 59 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for Neptune Florencia record 18 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 18 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Sachin Deshmukh is the promoter of record on 80 projects registered with MahaRERA, 18 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

80projects

registered with MahaRERA

18flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for Neptune Florencia in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+15.

BuildingWingsFloorsDeclared completion
Neptune Florencia1G+15-

Legal and disputes

What disputes are disclosed?

1 complaint is on the MahaRERA record for Neptune Florencia, with orders passed in 1 of them.

1complaint

1with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 12 Jul 2026

Complaint no.FiledPartiesStatus
CC00600000007863125/03/2019Nitin Hemraj Mota vs Sachin M. Deshmukh & Nayan A. Bheda (AOP)order passed

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 2 times, as recorded on the register.

FromExtended toStated reason
as registered31 Dec 2019We had obtained Commencement Certificate from the Executive Engineer (Building Proposal) of MCGM (Competent Authority) till 12 Floors and also RCC work of the said project has been
31 Dec 201930 Apr 2021Project is in finishing stage and it will take approx. 6 months to handover to customers.

Location, Land & Connectivity

Located at Mulund West, PK Road, Kurla, Mumbai Suburban, 400080. Per the filed land record, the plot is bounded to the north by Valji Laddha Road, to the south by Om Laxmi Sadan CHS Ltd, to the east by OM Shanti CHS Ltd and to the west by Purshottam Kheraj Road. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~2 km away — walking/short-hop distance to a major employment hub — a genuine work-near-home location.

LandmarkStraight-line
Bandra Kurla Complex (BKC)2 km
Chhatrapati Shivaji Int'l Airport4 km
Powai / Hiranandani business park7 km
Andheri MIDC / SEEPZ8 km
Lower Parel / Worli business district9 km
Nariman Point / Fort16 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Mulund West

AAI Satidevi Paradise
possession by Sep 2026 · Shreenath Developers
Laizer Elegance
Not filing quarterly progress reports · possession by Sep 2026 · Laizer Builders & Developers
THE NEW Anand Deep CHS LTD
possession by Sep 2026 · Shreejee Buildcon
Tirupati Apartments Chsl
possession by Oct 2026 · Tirupati Aparmtnets CO Operative Housing
Horizon Garden View
possession by Nov 2026 · Horizon Promoters India LTD
Montana Phase - 3
possession by Dec 2026 · Lohitka Properties LLP

Major developers building in Mulund West

Other RERA-registered projects in Mumbai Suburban

Neptune Flying Kites A Wing - Right Wing
declared completion Dec 2019 · Neptune Ventures AND Developers Private
Neptune Flying Kites B Wing- Left Wing
declared completion Dec 2019 · Neptune Ventures AND Developers Private
Neptunes Lotus
possession by Dec 2027 · Vrutti Developers LLP
Nero
possession by Dec 2026 · Super Construction Company
Nest Residency
declared completion Mar 2026 · Chaitali Kalapi Nagada
Nest Wing B
possession by Mar 2030 · M86 Residency Private Limited

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026