MahaRERA Property Intelligence · Mumbai Suburban

New Aishwarya

P51800010734 · promoter Prabhakar Shetty

Certificate SignedDue 31 Jan 2020

Delivery & Registration

MahaRERA registrationP51800010734
Registered on31 Aug 2017
Promoter-declared completion31 Jan 2020
Current statusCertificate Signed
Against todayabout 78 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Prabhakar Shetty is the promoter of record on 74 projects, of which 10 carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+6.

BuildingWingsFloorsDeclared completion
A Wing1G+5-
B Wing1G+6-

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Legal & Litigation

The promoter has declared 1 court case on this project to MahaRERA. 1 is still pending. Litigation can cloud the land title or stall the build — have a lawyer pull the cause list for each and confirm whether it touches the title to your flat. This is declared by the promoter; there may be further cases not on the RERA record.

CourtCase no.YearStatus
High Court28831985Pending

Deadline Extensions

The promoter has had the MahaRERA completion deadline formally extended 1 time. Each extension is the regulator letting the finish line move — the clearest evidence of delivery slippage, straight from the record.

From (declared)To (revised)Stated reason
31 Jan 202031 Jan 2020FINANCIAL CONTRAINS

Location, Land & Connectivity

Located at Kurla, Mumbai Suburban, 400080. Per the filed land record, the plot is bounded to the north by DP road, to the south by CTS no 550-26 of village nahur, to the east by CTS no 579 nahur and to the west by DP road. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~7 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Powai / Hiranandani business park7 km
Andheri MIDC / SEEPZ9 km
Chhatrapati Shivaji Int'l Airport12 km
Bandra Kurla Complex (BKC)14 km
Lower Parel / Worli business district23 km
Nariman Point / Fort30 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Mulund West

Kailash Residency
possession by Aug 2026 · Tridev Shreeji Associates
Ananta
possession by Aug 2026 · K Ajmera Developers
AAI Satidevi Paradise
possession by Sep 2026 · Shreenath Developers
Laizer Elegance
Not filing quarterly progress reports · possession by Sep 2026 · Laizer Builders & Developers
THE NEW Anand Deep CHS LTD
possession by Sep 2026 · Shreejee Buildcon
Tirupati Apartments Chsl
possession by Oct 2026 · Tirupati Aparmtnets CO Operative Housing

Major developers building in Mulund West

Other RERA-registered projects in Mumbai Suburban

NEW Ajay Villa
declared completion Jun 2023 · Sudarsan Developers
NEW Anamika Triveni Fortune
declared completion Dec 2017 · Triveni Developers
NEW Ashwin Chsl
possession by Dec 2026 · Ossia Buildcon Private Limited
NEW Avanti Chsl
possession by Oct 2026 · Balaji Enterprises
NEW Bhagyashree CHS LTD
declared completion Feb 2018 · K. Anand Construction Private Limited
New Brindavan Chsl
possession by Dec 2029 · Shree Mahavir Estates

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026