OLYMPIA C D

P51800012383 · Mulund West · promoter Nirmal Developers

Certificate SignedDue 30 Dec 2025

Delivery & Registration

MahaRERA registrationP51800012383
Registered on01 Sep 2017
Promoter-declared completion30 Dec 2025
Current statusCertificate Signed
Against todayabout 7 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Nirmal Developers is the promoter of record on 66 projects, of which 40 carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+59.

BuildingWingsFloorsDeclared completion
Olympia C D1G+5931 Dec 2024

Complaints & Orders

63 complaints are on the MahaRERA record for this project, with orders passed in 63. An adjudicated complaint is the clearest evidence of how this promoter behaves when pushed — read the orders in full.

Complaint no.FiledPartiesStatus
CC00600000000143423/10/2017RAMCHANDRA L. BADGE vs NIRMAL DEVELOPERSorder passed
CC00600000005596527/08/2018Karthik Ganesh Jaganmohan vs Nirmal Developersorder passed
CC00600000001258427/12/2017SHRI. HRISHIKESH DEVRAM MINDHE THROUGH HIS C. A. SHRI. DEVRAM SADASHIV MINDHE vs NIRMAL DEVELOPERSorder passed
CC00600000002346722/02/2018ESAKKITHAI THEVAR AND ESAKKINATHAN THEVAR vs NIRMAL DEVELOPERSorder passed
CC00600000002350826/02/2018Nirmal Developer Olympiya Aggrieved BuyerAssociation vs Nirmal Developersorder passed
CC00600000004414918/04/2018DEEPALI J. MURJANI vs NIRMAL DEVELOPERSorder passed
CC00600000014101003/10/2019Kailash Chandra Bhatt vs M/s. Nirmal Developersorder passed
CC00600000014110903/10/2019Mrs. Bhavika Sanjay Gujaria vs M/s. Nirmal Developersorder passed
CC00600000014114703/10/2019Mr. Gautham Aravindan vs M/s. Nirmal Developersorder passed
CC00600000004448419/05/2018PRERNA CHOWDHARY vs NIRMAL LIFESTYLE MULUND PVT LTDorder passed
CC00600000004448519/05/2018PRERNA CHOWDHARY vs NIRMAL LIFESTYLE MULUND PVT LTDorder passed
CC00600000005461423/05/2018PRAKASH VASANT KAJARI vs NIRMAL DEVELOPERSorder passed
CC00600000005469230/05/2018B H PANDIT vs NIRMAL DEVELOPERSorder passed
CC00600000005545521/07/2018Binu Nair and Mrs. Sumtha Nair vs Nirmal Developersorder passed
CC00600000019613223/02/2021Ms. Immaculate C. Correia vs M/s Nirmal Developers Partnershiporder passed
CC00600000005647110/10/2018Mohan Pednekar vs Nirmal Developersorder passed
CC00600000005647410/10/2018Sachin Kambli vs Nirmal Developersorder passed
CC00600000005719506/12/2018Neha Govind Saool vs Nirmal Developers/ Dharmesh Jainorder passed
CC00600000005725911/12/2018Swati Patil vs Nirmal Developersorder passed
CC00600000019786002/08/2021Swati Chandrakant Patil vs Nirmal Developerorder passed
CC00600000005743426/12/2018Hemant Mahajan vs Nirmal Developersorder passed
CC00600000005802209/02/2019VINOD KUMAR PANDEY vs NIRMAL DEVELOPERSorder passed
CC00600000006815723/02/2019Kamal Suresh Patil vs Nirmal developerorder passed
CC00600000007839508/03/2019Arvind Ambekar vs Dharmesh Jainorder passed
CC00600000007918306/05/2019JAGANNATH PADAVE vs NIRMAL DEVELOPERSorder passed
CC00600000007911106/07/2019Nayanaa Vaidya vs Nirmal Developersorder passed
CC00600000019242003/02/2020NAYANAA VAIDYA vs NIRMAL DEVELOPERSorder passed
CC00600000007928013/05/2019Kavita Malhotra vs Nirmal Developersorder passed
CC00600000009002808/07/2019Mangala Mande vs NIRMAL DEVELOPERSorder passed
CC00600000019241903/02/2020Mangala Mande vs Nirmal Developersorder passed
CC00600000016140605/11/2019Nirmal Developer Olympia Aggrieved Buyer Association vs Nirmal Developers and Lucarative Properties Pvt Ltdorder passed
CC00600000018205703/01/2020POONAM ROHAN KAGE vs NIRMAL DEVELOPERSorder passed
CC00600000019219115/01/2020Daniel Thomas Valayil vs Nirmal Develpersorder passed
CC00600000019223920/01/2020MR.BHARAT PUNAMCHAND SHAH& MRS. NILA BHARAT SHAH & MR. HARSHIT BHARAT SHAH vs NIRMAL DEVELOPERorder passed
CC00600000019245805/02/2020Gauri Thatte vs Nirmal Developersorder passed
CC00600000019288605/03/2020Nilesh Maru vs Nirmal Developersorder passed
CC00600000019288805/03/2020P N KUTTY NAIR SHEKHARAN vs Nirmal Developersorder passed
CC00600000019278011/03/2020BINU NAIR & SUMITHA NAIR vs NIRMAL DEVELOPERSorder passed
CC00600000019307819/03/2020MATHEW K ALEX AND RUBY MATHEW vs NIRMAL DEVELOPERS, SHAPOORJI PALLONJI AND COMPANY PVT LTDorder passed
CC00600000019316218/09/2020Kamlesh Lachhman Tilwani and Lachhman Jiwatram Tilwani vs Nirmal Developersorder passed
CC00600000019347008/08/2020Ashish Kumar Singh vs Nirmal Developersorder passed
CC00600000019648825/03/2021Lucrative Properties Private Limited vs P.N. Kutty Nair Shekharanorder passed
CC00600000019649325/03/2021Lucrative Properties Private Limited vs Nilesh Maruorder passed
CC00600000019649525/03/2021Lucrative Properties Private Limited vs Gauri Thatteorder passed
CC00600000019649625/03/2021Lucrative Properties Private Limited vs Mathew K Alexorder passed
CC00600000021036111/03/2022Shapoorji Pallonji Development Managers Private Limited vs Mohammad Feeroz Ahmadorder passed
CC00600000022077211/04/2022Lucrative Properties Private Limited vs Mohammad Feeroz Ahmedorder passed
CC00600000019730618/06/2021Mohammad Feeroz Ahmad vs Nirmal Developersorder passed
CC00600000019762016/07/2021RAJESH SHINDE vs NIRMAL DEVEOPERSorder passed
CC00600000019778928/07/2021Narayan Dhokre vs Nirmal Developersorder passed
CC00600000019840522/09/2021Manasi Dalvi vs Nirmal Developersorder passed
CC00600000019791006/08/2021C J Rana,C J Rana and D J Rana vs Nirmal Developersorder passed
CC00600000019899912/11/2021Suryakant Dattaram Bhogle vs M/s. Nirmal Developersorder passed
CC00600000020981925/01/2022SANTOSHKUMAR S HALAKATTI vs NIRMAL DEVELOPERSorder passed
CC00600000021008709/03/2022Ms. Preeti Girish vs M/s. Nirmal Developersorder passed
CC00600000008993201/07/2019Mr. Mahesh S. Singh vs Shapoorji Pallonji Development Managers Private Limitedorder passed
CC00600000026194008/08/2022Kavissh M Tantry vs Nirmal Developersorder passed
CC00600000030289708/10/2022Arun Nishad vs Shapoorji Pallonji Real Estateorder passed
CC00600000039614809/06/2023Kavita Ramchandra Girkar vs NIRMAL DEVELOPERSorder passed
CC00600000047992306/04/2024SANDEEP DHANVANTRI SHAH vs NIRMAL DEVELOPERSorder passed
CC1240036407/10/2024Kasturi Sanjay Nalavade vs Nirmal Developersorder passed
CC1250176829/05/2025Anand Navalkar vs Nirmal Developersorder passed
CC1250390907/11/2025Harshil Mankad vs Sandeep Dhanvantri Shahorder passed

Legal & Litigation

The promoter has declared 9 court cases on this project to MahaRERA. 3 are still pending. Litigation can cloud the land title or stall the build — have a lawyer pull the cause list for each and confirm whether it touches the title to your flat. This is declared by the promoter; there may be further cases not on the RERA record.

CourtCase no.YearStatus
City Civil Court At Mumbai1090101994Pending
City Civil Court At Mumbai1092721994Pending
Small Cause Court At Dhobi Talao Mumbai111/1382012Pending
State Consumer Disputes Redressal Commission MumbaiCC/280 /20162016Next Hearing In The Month Of August
State Consumer Disputes Redressal Commission MumbaiCC/615/20162016Next Hearing In The Month Of August
State Consumer Disputes Redressal Commission MumbaiCC/672 /20162016Next Hearing In The Month Of September
State Consumer Disputes Redressal Commission MumbaiCC/819/20162016Next Hearing In The Month Of July
State Consumer Disputes Redressal Commission MumbaiCC/1176 /20162016Next Hearing In The Month Of July
State Consumer Disputes Redressal Commission MumbaiCC/5/172017Next Hearing In The Month Of July

Location, Land & Connectivity

Located at Mulund West, Vaishali Nagar, Kurla, Mumbai Suburban, 400080. Per the filed land record, the plot is bounded to the north by NALLAH, to the south by 13 M W ROAD, to the east by Proposed Building and to the west by Proposed building A B. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~8 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Powai / Hiranandani business park8 km
Andheri MIDC / SEEPZ9 km
Chhatrapati Shivaji Int'l Airport13 km
Bandra Kurla Complex (BKC)14 km
Lower Parel / Worli business district23 km
Nariman Point / Fort30 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Mulund West

Kailash Residency
possession by Aug 2026 · Tridev Shreeji Associates
Ananta
possession by Aug 2026 · K Ajmera Developers
AAI Satidevi Paradise
possession by Sep 2026 · Shreenath Developers
Laizer Elegance
Not filing quarterly progress reports · possession by Sep 2026 · Laizer Builders & Developers
THE NEW Anand Deep CHS LTD
possession by Sep 2026 · Shreejee Buildcon
Tirupati Apartments Chsl
possession by Oct 2026 · Tirupati Aparmtnets CO Operative Housing

Major developers building in Mulund West

Other RERA-registered projects in Mumbai Suburban

Olympus
declared completion Dec 2024 · Vaibhavlaxmi Builders And Developers
OM Aarti
declared completion Dec 2025 · C H Patil AND Sons LLP
OM Amar Shakti
possession by Dec 2027 · Shree Shakti Realty
Om Ambe Smruti
possession by Dec 2026 · Oscar Infrastructure Private Limited
OM Dhanlaxmi Heights
possession by Dec 2026 · V P Realty
Om Ganesh Krupa
declared completion Jun 2019 · Dharma Construction

What to verify (QPR non-filer)

  1. Cross-check the developer's last QPR filing date on the MahaRERA portal — non-filing can indicate stalled construction.
  2. Visit the site (or request a third-party inspection report) to verify actual construction progress.
  3. If no QPR has been filed for more than two quarters, file a complaint with MahaRERA for non-disclosure.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026