MahaRERA Property Intelligence · Thane

Palava Olivia C

P51700017590 · Palava · promoter Lodha

Certificate SignedDue 28 Aug 2023

Delivery & Registration

MahaRERA registrationP51700017590
Registered on28 Aug 2018
Promoter-declared completion28 Aug 2023
Current statusCertificate Signed
Against todayabout 35 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+13.

BuildingWingsFloorsDeclared completion
Olivia C1G+1328 Aug 2023

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Legal & Litigation

The promoter has declared 2 court cases on this project to MahaRERA. Litigation can cloud the land title or stall the build — have a lawyer pull the cause list for each and confirm whether it touches the title to your flat. This is declared by the promoter; there may be further cases not on the RERA record.

CourtCase no.YearStatus
Civil Court Jd Kalyan586/20162016Hearing Of Order Seven Rule Eleven Application
Civil Judge Sd Kalyan284/152015We Have Filed Sat Ws Along Withn Order Seven Rule Twenty Two Application

Location, Land & Connectivity

Located at Palava, Kalyan Shil Phata Road, Mumbai City, Mumbai City, 421204. Per the filed land record, the plot is bounded to the north by 64 by 1 pt, to the south by 61 pt, to the east by 64 by 1 pt 64 by 3 pt and to the west by 63 by 1 pt 63 by 2 pt. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Lodha Developers Limited is the promoter on 133 MahaRERA-registered projects, of which 3 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

See every Lodha Developers Limited project & its RERA track record →

Other flagged projects by Lodha Developers Limited

Lodha Developers Limited
FlaggedMumbai Suburban
Lodha Developers Limited
FlaggedMumbai Suburban
Lodha Developers Limited
FlaggedMumbai Suburban
Lodha Developers Limited
FlaggedRaigarh
Lodha Developers Limited
FlaggedRaigarh
Lodha Developers Limited
FlaggedRaigarh

Other RERA-registered projects in Dombivali

Balaji Estate
possession by Jul 2026 · M/s. Sai Balaji Buildcon
Jayram Heights
possession by Jul 2026 · Ashapura Enterprises
Pearl B
possession by Jul 2026 · Lodha Developers Limited
Runwal Gardens Phase 4 Bldg No. 33-34
possession by Sep 2026 · Runwal Residency Private Limited
Sai Siddhi Residency
possession by Sep 2026 · Devendra Damodar Patil
Alimkar Heights
possession by Oct 2026 · Alimkar & Sons

Major developers building in Dombivali

Other RERA-registered projects in Thane

Palava - Paseo - D To H
declared completion Jun 2018 · Palava Dwellers Private Limited
Palava Primia E To J
declared completion Feb 2019 · Palava Dwellers Private Limited
Palava Regalia A To F
declared completion Dec 2018 · Palava Dwellers Private Limited
Palava - Retail Shop No 15 To 33 - Car Park Building C1
declared completion Sep 2018 · Palava Dwellers Private Limited
Palava River View E AND F
declared completion Dec 2017 · Lodha Developers Limited
Palava Savana AND Siena
declared completion Feb 2021 · Lodha Developers Limited

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026