MahaRERA Property Intelligence · Mumbai Suburban

Parijat Height

P51800005096 · promoter Mohammed Ismail Zahiruddin

Certificate SignedDue 01 Jan 2021

Delivery & Registration

MahaRERA registrationP51800005096
Registered on09 Aug 2017
Promoter-declared completion01 Jan 2021
Current statusCertificate Signed
Against todayabout 66 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+17.

BuildingWingsFloorsDeclared completion
Parijat Height1G+17-

Complaints & Orders

1 complaint is on the MahaRERA record for this project, with orders passed in 1. An adjudicated complaint is the clearest evidence of how this promoter behaves when pushed — read the orders in full.

Complaint no.FiledPartiesStatus
CC00600000042874306/01/2024BASHIRODDIN ASHABODDIN INAMDAR vs MOHAMMED ISMAIL SHAIKHorder passed

Location, Land & Connectivity

Located at Panvel, Raigarh, 400101. Per the filed land record, the plot is bounded to the north by Well To Do Building, to the south by 60 Feet Road, to the east by Devrath Building and to the west by Chinmay Building. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~12 km away — a real but liveable commute to the nearest job hub — factor peak-hour traffic.

LandmarkStraight-line
Andheri MIDC / SEEPZ12 km
Powai / Hiranandani business park15 km
Chhatrapati Shivaji Int'l Airport16 km
Bandra Kurla Complex (BKC)19 km
Lower Parel / Worli business district26 km
Nariman Point / Fort34 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Kandivali East

Lodha Kandivali Project - Tower 2
possession by Jul 2026 · Lodha Developers Limited
Lodha Kandivali Project - Tower 5
possession by Jul 2026 · Lodha Developers Limited
Vanrai
possession by Jul 2026 · Kaustubh Construction Private Limited
Kanchangiri
possession by Sep 2026 · Goodwill Builders
Aspire
possession by Oct 2026 · M/s Radheshyam Developers
Grande Edifice
possession by Dec 2026 · V6 Enterprises

Major developers building in Kandivali East

Other RERA-registered projects in Mumbai Suburban

Parijat Hill View Realty LLP
declared completion Jun 2024 · M/s Parijat Hill View Realty LLP
Parijat, Mrugendra Chsl
possession by Mar 2029 · N. K. Lifestyle
Parijat Sahanivas
possession by Dec 2028 · Bapat Constructions Private Limited
Parijat Towers
declared completion Jun 2023 · Better Builders AND Infrastructure Priva
Parijatak CO OP HSG SOC LTD
declared completion Dec 2021 · Sunrise Housing
Parimal
possession by Oct 2029 · Majestic Royale City Developers

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026