MahaRERA Property Intelligence · Thane

PARVATI HEIGHTS

P51700015874 · PADALE · promoter Hasti Buildcon

Certificate SignedDue 30 Dec 2022

Delivery & Registration

MahaRERA registrationP51700015874
Registered on28 Mar 2018
Promoter-declared completion30 Dec 2022
Current statusCertificate Signed
Against todayabout 43 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Hasti Buildcon is the promoter of record on 6 projects, of which 1 carries a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+20.

BuildingWingsFloorsDeclared completion
PARVATI HEIGHTS1G+2031 Dec 2021

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Deadline Extensions

The promoter has had the MahaRERA completion deadline formally extended 2 times. Each extension is the regulator letting the finish line move — the clearest evidence of delivery slippage, straight from the record.

From (declared)To (revised)Stated reason
30 Dec 202231 Mar 2024Our Project is registered on 28/03/2018 under the name & style of " PARVATI HEIGHTS" with first completion date of 31/12/2021. The Project is situated at SURVEY NO 61/6 at Thane
30 Dec 202230 Sep 2024To, MahaRERA Dear Sir/Madam, Regarding Project PARVATI HEIGHTS registered with Maharera with Registration Number P51700015874. The date of completion of project is 31.03.2024.

Location, Land & Connectivity

Located at PADALE, KALAYN SHIL ROAD, Kurla, Mumbai Suburban, 421204. Per the filed land record, the plot is bounded to the north by SURVEY NO 60, to the south by KALYAN SHIL ROAD, to the east by SURVEY NO 61 HISA NO 5 and to the west by SURVEY NO 57. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~16 km away — a real but liveable commute to the nearest job hub — factor peak-hour traffic.

LandmarkStraight-line
Powai / Hiranandani business park16 km
Andheri MIDC / SEEPZ20 km
Chhatrapati Shivaji Int'l Airport21 km
Bandra Kurla Complex (BKC)22 km
Lower Parel / Worli business district29 km
Nariman Point / Fort35 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Dombivali

Balaji Estate
possession by Jul 2026 · M/s. Sai Balaji Buildcon
Jayram Heights
possession by Jul 2026 · Ashapura Enterprises
Pearl B
possession by Jul 2026 · Lodha Developers Limited
Runwal Gardens Phase 4 Bldg No. 33-34
possession by Sep 2026 · Runwal Residency Private Limited
Sai Siddhi Residency
possession by Sep 2026 · Devendra Damodar Patil
Alimkar Heights
possession by Oct 2026 · Alimkar & Sons

Major developers building in Dombivali

Other RERA-registered projects in Thane

Parvati Nandan Co-Operative Housing Society Limited
declared completion May 2024 · Johnson Jesudas Nadar
Parvati Niwas
declared completion Dec 2025 · Aadarsh Developers
Parvati Park CO OP HSG SOC LTD
possession by Dec 2027 · Shreyas Enterprises AND Construction
Pataskar Eclat Building NO 3
declared completion Dec 2025 · Pataskar Developers Pvt. LTD
Patel Colossus Phase 1
declared completion Dec 2022 · Patel Group & Co
Patel Colossus Phase II
declared completion Dec 2023 · Patel Group & Co

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026