MahaRERA Property Intelligence · Thane

PLATINUM HERITAGE

P51700005172 · patlipada · promoter Darshan Sagar Developers

Certificate SignedDue 31 May 2019

Delivery & Registration

MahaRERA registrationP51700005172
Registered on10 Aug 2017
Promoter-declared completion31 May 2019
Current statusCertificate Signed
Against todayabout 86 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Darshan Sagar Developers is the promoter of record on 95 projects, of which 14 carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+15.

BuildingWingsFloorsDeclared completion
ROCK CASTLE1G+15-
EDEN CASTLE1G+15-

Complaints & Orders

11 complaints are on the MahaRERA record for this project, with orders passed in 11. An adjudicated complaint is the clearest evidence of how this promoter behaves when pushed — read the orders in full.

Complaint no.FiledPartiesStatus
CC00600000002395219/06/2018Nitendra singh kushwah / Ankur kushwah vs Suhail nooraniorder passed
CC00600000007903025/04/2019Darshan Sagar Developers vs Ms. Chandra Venakateswaran adn 80 othersorder passed
CC00600000009009514/08/2019DILIP SADASHIV SHINDE vs Sanjeev Malikorder passed
CC00600000009011916/07/2019Deepesh Kapoor vs Darshan Sagar Developersorder passed
CC00600000017146914/11/2019EDENCATLEOWNERSASSOCIATION vs M/S DARSHAN SAGA DEVELOPERSorder passed
CC00600000019661524/06/2021EDEN CASTLE OWNERS ASSOCIATION vs DARSHAN SAGAR DEVELOPERSorder passed
CC00600000033397720/01/2023Darshan Sagar Developers vs Mr.Vikas Dabhadeorder passed
CC00600000033397820/01/2023Darshan Sagar Developers vs Mr.Vikas Dabhadeorder passed
CC00600000033397920/01/2023Darshan Sagar Developers vs Mr.Vikas Dabhadeorder passed
CC00600000033398020/01/2023Darshan Sagar Developers vs Mr.Vikas Dabhadeorder passed
CC00600000033398220/01/2023Darshan Sagar Developers vs Mr.Vikas Dabhadeorder passed

Deadline Extensions

The promoter has had the MahaRERA completion deadline formally extended 1 time. Each extension is the regulator letting the finish line move — the clearest evidence of delivery slippage, straight from the record.

From (declared)To (revised)Stated reason
31 May 201931 May 2019Occupancy certificate is granted for building no. 1 and construction of building no. 2 is completed. Certain portion of project land declared as excess land as per provisions of Ur

Location, Land & Connectivity

Located at patlipada, hiranandani estate, Kurla, Mumbai Suburban, 400607. Per the filed land record, the plot is bounded to the north by 20 MTR DP ROAD, to the south by LAKE, to the east by HUTMENTS and to the west by HIRANANDANI HOSPITAL. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~17 km away — a real but liveable commute to the nearest job hub — factor peak-hour traffic.

LandmarkStraight-line
Powai / Hiranandani business park17 km
Andheri MIDC / SEEPZ18 km
Chhatrapati Shivaji Int'l Airport22 km
Bandra Kurla Complex (BKC)24 km
Lower Parel / Worli business district32 km
Nariman Point / Fort40 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Thane

Godrej Exquisite
possession by Sep 2026 · Godrej Macbricks Private Limited
Lodha Crown Kolshet-Tower 1
possession by Sep 2026 · Lodha Developers Limited
Odysseus
possession by Sep 2026 · Sagar Enterprise
Unique Vistas Mhada Building NO. 1,2,3
possession by Sep 2026 · Madhu Harshad Doshi
Unique Vistas Mhada Buildingno. 4 5 6 7
possession by Sep 2026 · Madhu Harshad Doshi
Daffodil
possession by Dec 2026 · Shree Tirupati Greenfield Developers

Major developers building in Thane

Other RERA-registered projects in Thane

Platinum Mansionz
possession by Dec 2029 · Experio Ventures
Platinum Oakwoods
possession by Dec 2029 · Escaso Ventures
Platinum Palm Woods
declared completion Dec 2022 · Palacio Ventures
Platinum Residency
possession by Dec 2027 · Keyrock Homes
Platinum Sagar Jewel Wing D AND E
declared completion Nov 2020 · Platinum Sagar Homes
Platinum Sicily
possession by Dec 2029 · Escaso Ventures

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026