Mumbai/Project record

MahaRERA · the public record

SAPTASHREE GALICIA

KOLSHET · SAPTASHREE REALITY PRIVATE LIMITED

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

89units filed as unsoldInventory · 19 September 2026
31 May 2028declared completionMahaRERA registration · read 12 Jul 2026
165registered unitsMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 May 2028

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51700054273

Delivery and registration

When is the project declared for completion?

SAPTASHREE GALICIA is registered with MahaRERA as P51700054273 and the promoter has declared completion for 31 May 2028.

31 May 2028

declared completion

20months to go

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51700054273
Registered on15 Jan 2024
Promoter-declared completion31 May 2028
Current statusCertificate Signed
Against today20 months to the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for SAPTASHREE GALICIA record 9 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Filing progress reports — 9 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Saptashree Reality is the promoter of record on 3 projects registered with MahaRERA, none of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

3projects

registered with MahaRERA

0flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Construction

How much construction cost has been reported?

In SAPTASHREE GALICIA, ₹20.50 Cr of a declared ₹40.74 Cr estimated project cost is reported as incurred, about 50.3%, as at the last certified filing with MahaRERA.

50.3%

₹20.50 Cr

of ₹40.74 Cr declared cost

Cost incurred as last certified to MahaRERA. It is a financial measure, not a survey of site work, and it can lag on-site reality between filings.

Source · MahaRERA quarterly progress filing · read 12 Jul 2026

Sales

How much has actually been sold?

In SAPTASHREE GALICIA, 40 of 131 homes filed with MahaRERA are recorded as sold or booked (34 with registered agreements and 6 booked), about 31%, and 91 remain available.

31%sold

40 of 131 homes

₹24.57 Cr

committed by buyers

Counts and agreement value as the promoter filed them at the last compliance date; this is the filed inventory, not current availability. Of that agreement value, ₹12.40 Cr (about 50%) is recorded as collected and ₹12.17 Cr as receivable. The project registers 165 homes in total, while this sold/unsold inventory filing covers 131 of them.

Source · MahaRERA sold/unsold inventory filing · read 12 Jul 2026

What buyers actually paid: across 40 registered agreements, the effective carpet rate is ₹13,187/sqft, with eight in ten falling between ₹12,554 and ₹17,195 — computed from the agreement values and carpet areas the promoter filed, not broker quotes.

The inventory filing also declares: 34 not for sale.

What the filings record, home by home

Read from MahaRERA on 19 September 2026

MahaRERA publishes, home by home, what this promoter filed: which homes are sold and which are not, the RERA carpet area of each, and for the sold ones the registered agreement value — the consideration filed for that specific home. On this project 42 homes carry one, and 89 of the 165 are recorded unsold. Since we started watching this ledger, 4 homes have moved out of the unsold list, most recently on 11 September 2026.

Here is one of those unsold homes, priced against what buyers of the same home on other floors actually filed:

HomeCarpetFiled for the same home on other floorsBased on
Shop-005401 sqftRs 53.23 lakh typical, over Rs 51.36 lakh to Rs 57.36 lakh15 filed at this size

A filed consideration is what was registered for one home. It is not a valuation, and MahaRERA does not publish the date of any of these agreements — read a range as a spread, not as a trend. An unsold row means no sale had been filed for it when we looked, which is a filing state, not a promise that the home is available to you today. One of the two observations is an archived copy whose time is the moment the file was written, not a portal fetch time.

In SAPTASHREE GALICIA, 86 of the 89 unsold homes have agreements filed on their own stack. The Price Comparison Report gives each of them its own row — the filed agreements behind that stack listed in full, the government reckoner value the promoter filed against it, and whether it is mortgaged to a lender while still on the unsold list. Built from the filing itself, sent by email.

See the other 88 homes — ₹2,999 →

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+19 and 165 homes are registered across the project.

BuildingWingsFloorsHomesDeclared completion
SAPTASHREE GALICIA1G+19165-

Unit mix on the filing: 148 residential and 17 non-residential (shops/offices).

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Location, Land & Connectivity

Located at KOLSHET, KOLSHET ROAD, Thane, Thane, 400607. Per the filed land record, the plot is bounded to the north by HANUMAN TEMPLE, to the south by TMC WWORKSHOP, to the east by BOMBAY WIREROPES COMPANY and to the west by TMC ROAD. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~17 km away — a real but liveable commute to the nearest job hub — factor peak-hour traffic.

LandmarkStraight-line
Powai / Hiranandani business park17 km
Andheri MIDC / SEEPZ18 km
Chhatrapati Shivaji Int'l Airport22 km
Bandra Kurla Complex (BKC)24 km
Lower Parel / Worli business district32 km
Nariman Point / Fort39 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Saptashree Reality Private Limited is the promoter on 2 MahaRERA-registered projects, with none currently carrying a regulator flag — a reassuring wider track record (matched on the promoter name in the register; it doesn't guarantee this specific project, but a clean portfolio is a good sign).

Other RERA-registered projects in Kolshet

Godrej Exquisite
possession by Sep 2026 · Godrej Macbricks Private Limited
Lodha Crown Kolshet-Tower 1
possession by Sep 2026 · Lodha Developers Limited
Odysseus
possession by Sep 2026 · Sagar Enterprise
Unique Vistas Mhada Building NO. 1,2,3
possession by Sep 2026 · Madhu Harshad Doshi
Unique Vistas Mhada Buildingno. 4 5 6 7
possession by Sep 2026 · Madhu Harshad Doshi
Daffodil
possession by Dec 2026 · Shree Tirupati Greenfield Developers

Major developers building in Kolshet

Other RERA-registered projects in Thane

Saptashree Global Tech Center
possession by Dec 2028 · Saptashree Tech World
Saptshrungi Developers
possession by Mar 2028 · Saptshrungi Developers
Sara Heights
possession by Dec 2026 · Shete's Construction
Saras Icon
possession by Mar 2028 · Saras Infra
Saras Residency
possession by Dec 2027 · Balaji Group Builders & Developers
Saraswati Coral
possession by Jun 2028 · Shree RAM Infra

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026