Mumbai/Project record

MahaRERA · the public record

SHREE KRUSHNA TOWER

Tambe Nagar, Mulund West · MAGNAACASA REALTY PVT. LTD.

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

34units filed as unsoldInventory · 17 September 2026
28 Dec 2025declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

28 Dec 2025

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51800022998

Delivery and registration

When is the project declared for completion?

SHREE KRUSHNA TOWER is registered with MahaRERA as P51800022998 and the promoter has declared completion for 28 Dec 2025.

28 Dec 2025

declared completion

9months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51800022998
Registered on11 Nov 2019
Promoter-declared completion28 Dec 2025
Current statusCertificate Signed
Against todayabout 9 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for SHREE KRUSHNA TOWER record 25 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Current QPR default — the promoter has stopped filing the mandatory quarterly progress report (FY 2025-2026).

Promoter record

What else is this promoter on record for?

Magnaacasa Realty is the promoter of record on 5 projects registered with MahaRERA, none of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

5projects

registered with MahaRERA

0flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

What the filings record, home by home

Read from MahaRERA on 17 September 2026

MahaRERA publishes, home by home, what this promoter filed: which homes are sold and which are not, the RERA carpet area of each, and for the sold ones the registered agreement value — the consideration filed for that specific home. On this project 325 homes carry one, and 34 of the 359 are recorded unsold.

Here is one of those unsold homes, priced against what buyers of the same home on other floors actually filed:

HomeCarpetFiled for the same home on other floorsBased on
B 202395 sqftRs 66.22 lakh typical, over Rs 4.80 lakh to Rs 80.07 lakh148 filed at this size

A filed consideration is what was registered for one home. It is not a valuation, and MahaRERA does not publish the date of any of these agreements — read a range as a spread, not as a trend. An unsold row means no sale had been filed for it when we looked, which is a filing state, not a promise that the home is available to you today. Only one observation of this ledger so far: no change can be reported yet.

In SHREE KRUSHNA TOWER, every one of the 34 unsold homes has agreements filed on its own stack. The Price Comparison Report gives each of them its own row — the filed agreements behind that stack listed in full, the government reckoner value the promoter filed against it, and whether it is mortgaged to a lender while still on the unsold list. Built from the filing itself, sent by email.

See the other 33 homes — ₹2,999 →

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+23.

BuildingWingsFloorsDeclared completion
SHREE KRUSHNA TOWER1G+23-

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 1 time, as recorded on the register.

FromExtended toStated reason
as registered28 Dec 2025We have made significant progress in the project, with the work for Wings B, C and D which is now fully completed. Currently, we are in the process of preparing the Occupation Cert

Location, Land & Connectivity

Located at Tambe Nagar, Mulund West, Astik Manek Road, Sarojini Cross Road, Mumbai, Mumbai Suburban, 400080. Per the filed land record, the plot is bounded to the north by CTS No 746 Pt, to the south by Astik Manek Road, to the east by CTS No 723E and to the west by CTS No 751 Harmony Tower. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~9 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Powai / Hiranandani business park9 km
Andheri MIDC / SEEPZ10 km
Chhatrapati Shivaji Int'l Airport14 km
Bandra Kurla Complex (BKC)15 km
Lower Parel / Worli business district24 km
Nariman Point / Fort31 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Magnaacasa Realty Pvt. Ltd. is the promoter on 2 MahaRERA-registered projects, with none currently carrying a regulator flag — a reassuring wider track record (matched on the promoter name in the register; it doesn't guarantee this specific project, but a clean portfolio is a good sign).

Other flagged projects by Magnaacasa Realty Pvt. Ltd.

Magnaacasa Realty Pvt. Ltd.
FlaggedMumbai Suburban

Other RERA-registered projects in Mulund West

AAI Satidevi Paradise
possession by Sep 2026 · Shreenath Developers
Laizer Elegance
Not filing quarterly progress reports · possession by Sep 2026 · Laizer Builders & Developers
THE NEW Anand Deep CHS LTD
possession by Sep 2026 · Shreejee Buildcon
Tirupati Apartments Chsl
possession by Oct 2026 · Tirupati Aparmtnets CO Operative Housing
Horizon Garden View
possession by Nov 2026 · Horizon Promoters India LTD
Montana Phase - 3
possession by Dec 2026 · Lohitka Properties LLP

Major developers building in Mulund West

Other RERA-registered projects in Mumbai Suburban

Shree Mahalakshmi Saburi
possession by May 2027 · Shree Mahalakshmi Constructions
Shree Mallinath Darshan
declared completion Dec 2024 · Shree Panav Developers
Shree Manik Vishwa
declared completion Jun 2026 · Anil Gangaram Sawant
Shree Matru Krupa
possession by Mar 2028 · Shree Bharani Projects LLP
Shree Matruchhaya CHS LTD
declared completion Mar 2018 · K T Group
Shree Neha Chsl
declared completion Sep 2025 · Hari OM SAI Grihanrmiti PVT LTD

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026