Mumbai/Project record

MahaRERA · the public record

SODAH SADAN

Matunga · UNISPACE LANDMARK PRIVATE LIMITED

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 Jun 2023declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Jun 2023

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51900006024

Delivery and registration

When is the project declared for completion?

SODAH SADAN is registered with MahaRERA as P51900006024 and the promoter has declared completion for 30 Jun 2023.

30 Jun 2023

declared completion

39months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51900006024
Registered on14 Aug 2017
Promoter-declared completion30 Jun 2023
Current statusCertificate Signed
Against todayabout 39 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for SODAH SADAN record 24 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Filing progress reports — 24 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Unispace Landmark is the promoter of record on 2 projects registered with MahaRERA, 1 of which carries a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

2projects

registered with MahaRERA

1flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for SODAH SADAN in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+25.

BuildingWingsFloorsDeclared completion
SODAH SADAN1G+25-

Legal and disputes

What disputes are disclosed?

3 complaints are on the MahaRERA record for SODAH SADAN, with orders passed in 3 of them.

3complaints

3with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 12 Jul 2026

Complaint no.FiledPartiesStatus
CC00600000019640828/07/2022Dharmesh Sodah vs Unispace Landmark Pvt. Ltd.order passed
CC00600000020987102/02/2022Vivek Manohar Nayak vs M/s Unispace Landmark Pvt Ltdorder passed
CC00600000035447523/02/2023ATUL HIRALAL SHAH vs MS UNISPACE LANDMARK PVT LTDorder passed

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 4 times, as recorded on the register.

FromExtended toStated reason
as registered31 Dec 2020Please be informed that, our Project is MCGM Estate plot under 33(7) DCR- Re-development scheme whereby to reach to Commencement Certificate., major period lapses from the date of
31 Dec 202031 Dec 2020Sir / Madam, Please be informed that, our Project is MCGM Estate plot under 33(7) DCR- Re-development scheme whereby to reach to Commencement Certificate., major period lapses fr
31 Dec 202031 Mar 2022Our Project is MCGM Estate Plot under DCR 33(7) re-development scheme. It is not a freehold land. Therefore we need to obtain No. of N.O.C.s from M.C.G.M. Estate / MHADA Department
31 Mar 202230 Jun 2023The Construction industry is one of the main sectors that provide important contribution for the development of an economy. However, many projects experienced extensive delays due

Location, Land & Connectivity

Located at Matunga, Ward FNorth, Mumbai City, 400019. Per the filed land record, the plot is bounded to the north by 60FT SEWRI WADALA ROAD NO 7 , to the south by EXISTING BUILDING, to the east by 15FT MCGM ROAD and to the west by EXISTING BUILDING . These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~4 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Lower Parel / Worli business district4 km
Bandra Kurla Complex (BKC)4 km
Chhatrapati Shivaji Int'l Airport7 km
Powai / Hiranandani business park11 km
Andheri MIDC / SEEPZ11 km
Nariman Point / Fort12 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Matunga

Balkrishna Hills
possession by Sep 2026 · Oriental Contractors Private Limited
Gulraj Paradise
possession by Sep 2026 · M/S Reliable Construction
Signare
Past its declared completion date · possession by Sep 2026 · Tejukaya Buildcon
Chhaya
possession by Dec 2026 · Fortune Realty
Jade Acharya
possession by Dec 2026 · Raghavendra Acharya & Others
Shayona
possession by Dec 2026 · Devesh Narendra Jani

Major developers building in Matunga

Other RERA-registered projects in Mumbai City

SOM Niwas
declared completion Sep 2025 · Naman Developers
Sonas Tower
declared completion Dec 2017 · Shree Devijugai Developers
South Tower
declared completion Dec 2025 · Glider Buildcon Realtors Private Ltd
Soutth Bay
possession by Dec 2026 · M/s. Sambhav Shelters
Space Residency
declared completion Dec 2024 · Space Builders
Spee Skytower Wing A And B
declared completion Mar 2024 · Spee Realtor

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026