MahaRERA · the public record
VIJAY ENCLAVE
Village Kavesar, Ghodbunder Road · VIJAY CITISPACE PVT. LTD.
Know the project.
Then choose your home.
The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.
The record · free to read
Registration read 12 Jul 2026Progress & dates
The timeline on file.
Available record
No construction trend to plot.
The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.
declared completion
30 Mar 2025
The registered date and a construction update answer different questions. Neither is a confirmation of possession.
MahaRERA registration · read 12 Jul 2026
From another project
See the report before you buy.
A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.
Read a sample report ↗The source record
The details behind the headline.
MahaRERA · P51700008755
Delivery and registration
When is the project declared for completion?
VIJAY ENCLAVE is registered with MahaRERA as P51700008755 and the promoter has declared completion for 30 Mar 2025.
30 Mar 2025
declared completion
18months past
against the declared date
The completion date and status as they stand on the MahaRERA registration record.
Source · MahaRERA project registration · read 12 Jul 2026
| MahaRERA registration | P51700008755 |
| Registered on | 19 Aug 2017 |
| Promoter-declared completion | 30 Mar 2025 |
| Current status | Certificate Signed |
| Against today | about 18 months past the declared date |
Approvals and compliance
What compliance filings are on record?
MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for VIJAY ENCLAVE record 31 quarterly progress reports since registration.
31quarterly filings
Entries as they appear on MahaRERA's own lists and the project's progress filing.
Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026
- NCLT / insolvency — the promoter is (or was) before the NCLT for insolvency — the gravest RERA flag; buyer money and possession are at real risk.
- Filing progress reports — 31 quarterly progress reports on record since registration, with no current default.
Sales
Are registered sale-agreement prices available?
No registered sale-agreement price is recorded for VIJAY ENCLAVE in the MahaRERA project file.
Not available
This is what the record does not contain, not a value of zero.
Source · MahaRERA project file · checked 12 Jul 2026
Buildings & Wings
The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+34.
| Building | Wings | Floors | Declared completion |
|---|---|---|---|
| BUILDING NO 4 Floor 1 TO 30 | 1 | G+34 | 31 Mar 2024 |
| BUILDING NO 4 Floor 31 TO 40 | 1 | G+9 | - |
| BUILDING NO 5 Floor 1 TO 30 | 1 | G+34 | 31 Mar 2024 |
| BUILDING NO 5 Floor 31 TO 40 | 1 | G+9 | - |
Legal and disputes
What disputes are disclosed?
15 complaints are on the MahaRERA record for VIJAY ENCLAVE, with orders passed in 15 of them.
15complaints
15with an order
Counts as disclosed in the project record.
Source · MahaRERA project disclosures · read 12 Jul 2026
| Complaint no. | Filed | Parties | Status |
|---|---|---|---|
| CC006000000089836 | 04/01/2022 | Yogesh Boghani vs Ateev Gala | order passed |
| CC006000000110839 | 28/09/2019 | Raghavendra kandakur vs ateev gala | order passed |
| CC006000000110881 | 15/09/2019 | Venketesh Iyer vs Ateev Gala | order passed |
| CC006000000196673 | 15/04/2021 | Vinayak Jagannath Harnekar vs Vijay Citispace Private Limited | order passed |
| CC006000000196723 | 15/04/2021 | PRASAD VILAS BHATKAR vs VIJAY CITISPACE | order passed |
| CC006000000197433 | 09/08/2021 | Shailesh Mangesh Shinde vs Vijay Cityspace Pvt Ltd | order passed |
| CC006000000197930 | 07/08/2021 | Sandeep Patil vs ATEEV GALA | order passed |
| CC006000000197933 | 08/08/2021 | CC000000197933 vs Ateev Gala | order passed |
| CC006000000197999 | 15/08/2021 | Gourav Tyagi vs Ms Vijay CitiSpace Pvt Ltd | order passed |
| CC006000000198571 | 07/10/2021 | NITIN BHOJWANI vs VIJAY CITISPACE PRIVATE LIMITED | order passed |
| CC006000000198627 | 10/10/2021 | Vinaykumar J Pal vs VIJAY CITISPACE PVT. LTD. | order passed |
| CC006000000198711 | 18/10/2021 | Dimple Duggal vs Ateev Gala | order passed |
| CC006000000198992 | 27/11/2021 | Muthuganesh Konar vs P51700008755 | order passed |
| CC006000000198984 | 27/11/2021 | Prabir Karmokar vs Ateev Gala | order passed |
| CC006000000396556 | 05/07/2023 | MADHURA BHATE vs Vijay Citispace Pvt Ltd/ JM financial | order passed |
Legal & Litigation
The promoter has declared 9 court cases on this project to MahaRERA. 9 are still pending. Litigation can cloud the land title or stall the build — have a lawyer pull the cause list for each and confirm whether it touches the title to your home. This is declared by the promoter; there may be further cases not on the RERA record.
| Court | Case no. | Year | Status |
|---|---|---|---|
| District Consumer Dispute Redressal Forum Thane | 192 | 2010 | Pending |
| Civil Judge J D Thane | 334 | 2011 | Pending |
| Civil Judge S D Thane | 694 | 2011 | Pending |
| Civil Judge S D Thane | 690 | 2012 | Pending |
| Civil Judge Sd Thane | 548 | 2017 | Pending |
| Ncdrc | 2531 | 2017 | Pending |
| Ncdrc | 3213 | 2017 | Pending |
| District Judge Thane | 64 | 2018 | Pending |
| Nclt Mumbai | CP IB NO 3352 OF 2019 | 2019 | Pending |
Location, Land & Connectivity
Located at Village Kavesar, Ghodbunder Road, Waghbil Road, Mumbai City, Mumbai City, 400607. Per the filed land record, the plot is bounded to the north by VIJAY GALAXY PROJECT, to the south by BOUNDARY OF PATLIPADA VILLAGE, to the east by VIJAY NAGARI PROJECT and to the west by GHODBUNDER ROAD. These are the boundaries as recorded in the filed land record.
Location & connectivity
The nearest major job hub is ~17 km away — a real but liveable commute to the nearest job hub — factor peak-hour traffic.
| Landmark | Straight-line |
|---|---|
| Powai / Hiranandani business park | 17 km |
| Andheri MIDC / SEEPZ | 18 km |
| Chhatrapati Shivaji Int'l Airport | 21 km |
| Bandra Kurla Complex (BKC) | 24 km |
| Lower Parel / Worli business district | 32 km |
| Nariman Point / Fort | 40 km |
Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.