MahaRERA Property Intelligence · Palghar

WONDER RESIDENCY C WING BUILDING NO 2

P99000020475 · GOKHIVIRE, VASAI · promoter New Galaxy Enterprises

Certificate SignedDue 30 Mar 2022

Delivery & Registration

MahaRERA registrationP99000020475
Registered on15 Apr 2019
Promoter-declared completion30 Mar 2022
Current statusCertificate Signed
Against todayabout 52 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, New Galaxy Enterprises is the promoter of record on 50 projects, of which 11 carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+8.

BuildingWingsFloorsDeclared completion
WONDER RESIDENCY C WING1G+831 Mar 2020

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Location, Land & Connectivity

Located at GOKHIVIRE, VASAI, WONDER RESIDENCY C WING, FATHER WADI BUS STOP, Vasai, Palghar, 401208. Per the filed land record, the plot is bounded to the north by NORTH, to the south by SOUTH, to the east by EAST and to the west by WEST. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~64 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Andheri MIDC / SEEPZ64 km
Powai / Hiranandani business park66 km
Chhatrapati Shivaji Int'l Airport68 km
Bandra Kurla Complex (BKC)71 km
Lower Parel / Worli business district78 km
Nariman Point / Fort86 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Vasai East

Samruddhi Ind. Estate
possession by Jul 2026 · Krisha Buildtech LLP
Armaan Crystal Uptown
possession by Aug 2026 · Armaan Housing LLP
Nakshatra Aarambh
possession by Sep 2026 · JSB Shelters LLP
AAI Chandika Hills
possession by Sep 2026 · Shivam Builders & Developers
Dreams Heights Building NO- I
possession by Sep 2026 · Lodha Builders AND Developers
Trinity Oasis
possession by Sep 2026 · Harsh Tirupati Developers LLP

Major developers building in Vasai East

Other RERA-registered projects in Palghar

Y. K. Nagar NX
declared completion Dec 2017 · Shree Ashtavinayak Builders
Yark Hills
possession by Dec 2027 · R R Builders & Developers
Yash Apartment
declared completion Dec 2025 · Kush Ramsingar Vishwakarma
Yash Apartment
declared completion Mar 2025 · Ramsingar Yadav
Yash Padma
possession by Dec 2026 · SAI Shraddha Enterprises
Yash Padma Phase II
possession by Dec 2030 · SAI Shraddha Enterprises

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026