Pune/Project record

MahaRERA · the public record

ALFA LIFESCAPES PHASE - 2

WAGHOLI · TRINITY LANDMARKS

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

25 Jun 2027declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

25 Jun 2027

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52100021374

Delivery and registration

When is the project declared for completion?

ALFA LIFESCAPES PHASE - 2 is registered with MahaRERA as P52100021374 and the promoter has declared completion for 25 Jun 2027.

25 Jun 2027

declared completion

9months to go

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52100021374
Registered on24 Jun 2019
Promoter-declared completion25 Jun 2027
Current statusCertificate Signed
Against today9 months to the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for ALFA LIFESCAPES PHASE - 2 record 30 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Current QPR default — the promoter has stopped filing the mandatory quarterly progress report (FY 2025-2026).

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for ALFA LIFESCAPES PHASE - 2 in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+4.

BuildingWingsFloorsDeclared completion
B WING1G+3-
C WING1G+4-

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 1 time, as recorded on the register.

FromExtended toStated reason
as registered25 Jun 2027In accordance with circular no 28, we hereby apply for extension of our project u/s 7(3) in Format B. The project was delayed for reasons beyond our control on account of various r

Location, Land & Connectivity

Located at WAGHOLI, KESANAD WAGHOLI ROAD, Pune City, Pune, 412207. Per the filed land record, the plot is bounded to the north by PART OF GAT NO 868, to the south by 36 MTR ROAD, to the east by 30 MTR ROAD and to the west by EXISTING BUILDING. These are the boundaries as recorded in the filed land record.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Trinity Landmarks is the promoter on 2 MahaRERA-registered projects, with none currently carrying a regulator flag — a reassuring wider track record (matched on the promoter name in the register; it doesn't guarantee this specific project, but a clean portfolio is a good sign).

Other flagged projects by Trinity Landmarks

Other RERA-registered projects in Wagholi

Aurora 2
possession by Sep 2026 · Magnum Developers
Elite
possession by Sep 2026 · V & J Developers
Enliven Home B Wing Phase 2
possession by Sep 2026 · Siddhivinayak Properties
Godrej Greens
possession by Sep 2026 · Dream World Landmarks LLP
Kharadi Pune Phase I - Tower 1 To 4
possession by Oct 2026 · Lodha Developers Limited
Defence Colony Pune Phase4
possession by Nov 2026 · Defence Colony Pune

Major developers building in Wagholi

Other RERA-registered projects in Pune

Alfaz Life Style
possession by Jun 2027 · Zakiruddin Gaffar Sayyed
Alliance Sarthak
possession by Dec 2029 · Alliance Buildcon
Allura Tower
possession by Dec 2026 · Geet Govind Realty
Alpha C
declared completion Sep 2025 · Raichandani Constructions Private Limite
Alpine 21
possession by Oct 2029 · Arise Associates
Alpine Astonia
declared completion Apr 2026 · Alpine Landmarks LLP

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026