GALAXY VINEET

BAVDHAN · VINEET CONSTRUCTIONS

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

28 Feb 2021declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

28 Feb 2021

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52100012001

Delivery and registration

When is the project declared for completion?

GALAXY VINEET is registered with MahaRERA as P52100012001 and the promoter has declared completion for 28 Feb 2021.

28 Feb 2021

declared completion

67months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52100012001
Registered on01 Sep 2017
Promoter-declared completion28 Feb 2021
Current statusCertificate Signed
Against todayabout 67 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for GALAXY VINEET record 15 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 15 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Vineet Constructions is the promoter of record on 8 projects registered with MahaRERA, 3 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

8projects

registered with MahaRERA

3flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for GALAXY VINEET in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+16.

BuildingWingsFloorsDeclared completion
GALAXY VINEET1G+16-

Legal and disputes

What disputes are disclosed?

10 complaints are on the MahaRERA record for GALAXY VINEET, with orders passed in 10 of them.

10complaints

10with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 12 Jul 2026

Complaint no.FiledPartiesStatus
CC00500000000032116/10/2017hrishikesh raman phadke vs ROSHAN DUSANEorder passed
CC00500000001196011/12/2018PRADIP THATTE vs Roshan dushaneorder passed
CC00500000001200826/09/2018Jagdish S Shetty vs Roshan Ramesh Dusaneorder passed
CC00500000002264414/02/2019Roopesh saxena vs M/s Swet Realtorsorder passed
CC00500000002264514/02/2019Prakash G Patil vs M/s Swet Realtorsorder passed
CC00500000002264614/02/2019Vivek Kulkarni vs Swet Reyaletrsorder passed
CC00500000002271101/03/2019Nikhil S Naik vs M/s Swet realtors pvt ltdorder passed
CC00500000002271301/03/2019Kiran Subhash Shinde vs M/s Swet Realtors Pvt Ltdorder passed
CC00500000002280926/03/2019Nikhil Kokitkar & Pallavi Kokitkar vs M/s. Swet Realtors Mr. Amit Ashok Thepadeorder passed
CC00500000002298918/05/2019Shri Suresh Ramchandra Pawar vs Vinit Costructionorder passed

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 1 time, as recorded on the register.

FromExtended toStated reason
as registered31 Aug 2020The construction of the building has been completed fully. Out of 3 lifts, 1 lift is operational and installation of 2 Lift is in process, Fire fighting system and Solar system wor

Location, Land & Connectivity

Located at BAVDHAN, BAVDHAN, Mulshi, Pune, 411021. Per the filed land record, the plot is bounded to the north by S NO 349, to the south by RAMNADI AND TEMPLE, to the east by RAMNADI and to the west by S NO 351. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~5 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Baner–Balewadi belt5 km
Hinjewadi Rajiv Gandhi IT Park9 km
Pune Junction / city centre10 km
Magarpatta / Hadapsar IT16 km
Pune Int'l Airport (Lohegaon)17 km
Kharadi / EON IT Park18 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Bavdhan

Purva Aspire
possession by Sep 2026 · Puravankara Limited
Marvel Selva Ridge Villa 6, 9, 11, 12
Developer in insolvency (NCLT) · possession by Dec 2026 · Marvel Omega Builders PVT LTD
Reelicon Fairy Bell
possession by Dec 2026 · Reelicon Red Homes Private Limited
Green Mint
possession by Dec 2026 · Sunil Vishwanath Salunke
Neelanchal Phase I
Not filing quarterly progress reports · possession by Dec 2026 · Pinnacle Vastunirman Pvt. Ltd
Neelanchal Phase II
possession by Dec 2026 · Pinnacle Vastunirman Pvt. Ltd

Major developers building in Bavdhan

Other RERA-registered projects in Pune

Ganaraj Paradise
possession by Feb 2028 · Uni Gravity Developers LLP
Gandhakuti
declared completion Jun 2019 · Pandit Javdekar Associates
Gandharv Galaxia
declared completion Dec 2024 · Gandharv Realty
Gandharv Gokulam
possession by Dec 2029 · Gandharv Corp
Gandharv Leela
possession by Dec 2030 · Gandharv Developers
Gandharv Marigold Building A
possession by Jan 2027 · Yogesh Properties Throu Prop Vijaya Vina

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026