MahaRERA · the public record
Guardian Eastern Meadows - Phase 1
Off Nagar Road · Guardian Promoters & Developers Private Limited
Know the project.
Then choose your home.
The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.
The record · free to read
Registration read 12 Jul 2026Progress & dates
The timeline on file.
Available record
No construction trend to plot.
The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.
declared completion
30 Jun 2023
The registered date and a construction update answer different questions. Neither is a confirmation of possession.
MahaRERA registration · read 12 Jul 2026
From another project
See the report before you buy.
A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.
Read a sample report ↗The source record
The details behind the headline.
MahaRERA · P52100007435
Delivery and registration
When is the project declared for completion?
Guardian Eastern Meadows - Phase 1 is registered with MahaRERA as P52100007435 and the promoter has declared completion for 30 Jun 2023.
30 Jun 2023
declared completion
39months past
against the declared date
The completion date and status as they stand on the MahaRERA registration record.
Source · MahaRERA project registration · read 12 Jul 2026
| MahaRERA registration | P52100007435 |
| Registered on | 17 Aug 2017 |
| Promoter-declared completion | 30 Jun 2023 |
| Current status | Certificate Signed |
| Against today | about 39 months past the declared date |
Approvals and compliance
What compliance filings are on record?
MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for Guardian Eastern Meadows - Phase 1 record 24 quarterly progress reports since registration.
24quarterly filings
Entries as they appear on MahaRERA's own lists and the project's progress filing.
Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026
- Filing progress reports — 24 quarterly progress reports on record since registration, with no current default.
Promoter record
What else is this promoter on record for?
Guardian Promoters Developers is the promoter of record on 10 projects registered with MahaRERA, 1 of which carries a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).
10projects
registered with MahaRERA
1flagged
by MahaRERA
Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.
Source · MahaRERA register, all projects · read 12 Jul 2026
Sales
Are registered sale-agreement prices available?
No registered sale-agreement price is recorded for Guardian Eastern Meadows - Phase 1 in the MahaRERA project file.
Not available
This is what the record does not contain, not a value of zero.
Source · MahaRERA project file · checked 12 Jul 2026
Buildings & Wings
The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+14.
| Building | Wings | Floors | Declared completion |
|---|---|---|---|
| A1 | 1 | G+12 | 31 Dec 2020 |
| B1 | 1 | G+12 | 31 Dec 2020 |
| C1 | 1 | G+12 | 31 Dec 2020 |
| B4 | 1 | G+14 | 31 Dec 2020 |
| A8 | 1 | G+14 | 31 Dec 2020 |
Legal and disputes
What disputes are disclosed?
26 complaints are on the MahaRERA record for Guardian Eastern Meadows - Phase 1, with orders passed in 26 of them.
26complaints
26with an order
Counts as disclosed in the project record.
Source · MahaRERA project disclosures · read 12 Jul 2026
| Complaint no. | Filed | Parties | Status |
|---|---|---|---|
| CC005000000022738 | 03/03/2019 | Sunil Sasidharan Pillai vs Manish Sabade | order passed |
| CC005000000022745 | 04/03/2019 | Madhuri Gupta vs Guardian Promoters and Developers Private Limited | order passed |
| CC005000000022823 | 24/04/2019 | Deepanshu Chopra vs Manish Sabde | order passed |
| CC005000000023117 | 16/11/2019 | Sainath Kotgire vs Manish Sabade | order passed |
| CC005000000023198 | 03/07/2019 | DEVENDER SINGH GARHA vs MANISH SABADE | order passed |
| CC005000000064841 | 01/02/2023 | DATTA TUKARAM MANDALE vs Manish Murlidhar Sabade | order passed |
| CC005000000269545 | 17/10/2023 | Tejashree NIranjan Rane vs M/s Guardian Promoters and Developers Pvt. ltd. | order passed |
| CC005000000269547 | 17/10/2023 | Lalit Joshi vs Guardian Promoters & Developers Private Limited | order passed |
| CC005000000269551 | 17/10/2023 | Gurpreet Pannu vs M/S Guardian Promoters and Developers Pvt. Ltd. | order passed |
| CC005000000269557 | 17/10/2023 | Chintan Shah vs M/S Guardian Promoters and Developers Pvt. Ltd | order passed |
| CC005000000269552 | 17/10/2023 | Sreekumer Nair vs M/S Guardian Promoters and Developers Pvt.Ltd. | order passed |
| CC005000000269583 | 17/10/2023 | Usha Padmale vs M/S Guardian Developers and Promoters Pvt Ltd | order passed |
| CC005000000269598 | 17/10/2023 | Rohit Gupta vs M/S Guardian Promoters & Developers Pvt Ltd | order passed |
| CC005000000269588 | 17/10/2023 | Rupesh Sharma vs M/S Guardian Promoters and Developers Pvt Ltd | order passed |
| CC005000000269607 | 17/10/2023 | Arun Singh vs M/S Guardian Promoters & Developers Pvt Ltd | order passed |
| CC005000000269601 | 17/10/2023 | Kaushal Sharma vs M/s Guardian Promoters & Developers Pvt Ltd | order passed |
| CC005000000269597 | 17/10/2023 | Viren Kawade vs M/S Guardian Promoters and Developers Prv Ltd | order passed |
| CC005000000269600 | 17/10/2023 | Nilesh Kumar vs M/S Guardian Promoters & Develoers Pvt Ltd | order passed |
| CC005000000269599 | 17/10/2023 | Nilesh More vs M/S Guardia Promoters & Developers Pvt Ltd | order passed |
| CC005000000269606 | 17/10/2023 | Aparna Dubey vs M/S Guardian Promoters & Developers Pvt Ltd | order passed |
| CC005000000269605 | 17/10/2023 | Atul Nandgavali vs M/S Guardian Promoters & Developers Pvt Ltd | order passed |
| CC005000000269602 | 17/10/2023 | Darbesh Yadav vs M/S Guardian Promoters & Developers PVT LTD | order passed |
| CC005000000269603 | 17/10/2023 | Avdhut Dalavi vs M/S Guardian Promoters & Developers Pvt Ltd | order passed |
| CC005000000471442 | 06/08/2024 | Sonal Ramkumar Varma vs M/s Guardian Promoter & Developers Pvt.LTD | order passed |
| CC005000000471443 | 06/08/2024 | Vinod Tukaram Manerajure vs M/s Guardian Promoters & Developers Pvt Ltd | order passed |
| CC12501294 | 19/04/2025 | KEDARNATH BALAJI PILAJI vs Guardian Promoters & Developers Private Limited | order passed |
Deadline Extensions
The MahaRERA completion deadline for this project has been formally extended 1 time, as recorded on the register.
| From | Extended to | Stated reason |
|---|---|---|
| as registered | 31 Dec 2022 | Due to corona-virus and lockdown |
Location, Land & Connectivity
Located at Off Nagar Road, Grant Road, Haveli, Pune, 412207. Per the filed land record, the plot is bounded to the north by Part of land bearing GAT No 1344-1-1 and 1344-1-2, to the south by Part of land bearing GAT No 1344-3, to the east by 18 Mrts Proposed Lay out Road and to the west by By Road and Boundary of Kharadi wagholi Village. These are the boundaries as recorded in the filed land record.
Location & connectivity
The nearest major job hub is ~2 km away — walking/short-hop distance to a major employment hub — a genuine work-near-home location.
| Landmark | Straight-line |
|---|---|
| Kharadi / EON IT Park | 2 km |
| Pune Int'l Airport (Lohegaon) | 4 km |
| Magarpatta / Hadapsar IT | 6 km |
| Pune Junction / city centre | 9 km |
| Baner–Balewadi belt | 19 km |
| Hinjewadi Rajiv Gandhi IT Park | 23 km |
Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.