Hillside, Viva, Pirangut

Aditya Nisarg · K Raheja Corp Real Estate Private Limited

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

6units filed as unsoldInventory · 18 September 2026
30 Sep 2024declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Sep 2024

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52100046903

Delivery and registration

When is the project declared for completion?

Hillside, Viva, Pirangut is registered with MahaRERA as P52100046903 and the promoter has declared completion for 30 Sep 2024.

30 Sep 2024

declared completion

24months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52100046903
Registered on19 Sep 2022
Promoter-declared completion30 Sep 2024
Current statusCertificate Signed
Against todayabout 24 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for Hillside, Viva, Pirangut record 9 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Filing progress reports — 9 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Raheja Developers is the promoter of record on 55 projects registered with MahaRERA, 4 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

55projects

registered with MahaRERA

4flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

How much has actually been sold?

In Hillside, Viva, Pirangut, 6 of 12 plots filed with MahaRERA are recorded as sold or booked, about 50%, and 6 remain available.

50%sold

6 of 12 plots

Counts as the promoter filed them at the last compliance date; this is the filed inventory, not current availability.

Source · MahaRERA sold/unsold inventory filing · read 12 Jul 2026

What the filings record, plot by plot

Read from MahaRERA on 18 September 2026

MahaRERA publishes, plot by plot, what this promoter filed: which plots are sold and which are not, the filed area of each, and for the sold ones the registered agreement value — the consideration filed for that specific plot. On this project 6 plots carry one, and 6 of the 12 are recorded unsold.

A filed consideration is what was registered for one plot. It is not a valuation, and MahaRERA does not publish the date of any of these agreements — read a range as a spread, not as a trend. An unsold row means no sale had been filed for it when we looked, which is a filing state, not a promise that the plot is available to you today. Only one observation of this ledger so far: no change can be reported yet.

In Hillside, Viva, Pirangut, 0 of the 6 unsold plots have agreements filed on their own stack. The Price Comparison Report gives each of them its own row — the filed agreements behind that stack listed in full, the government reckoner value the promoter filed against it, and whether it is mortgaged to a lender while still on the unsold list. Built from the filing itself, sent by email.

See the other 6 plots — ₹2,999 →

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Legal & Litigation

The promoter has declared 3 court cases on this project to MahaRERA. Litigation can cloud the land title or stall the build — have a lawyer pull the cause list for each and confirm whether it touches the title to your plot. This is declared by the promoter; there may be further cases not on the RERA record.

CourtCase no.YearStatus
Civil Judge Senior Division Pune20852010Ongoing
Additional District Court2242016Ongoing
Civil Judge Senior Division20852010Ongoing

Location, Land & Connectivity

Located at Aditya Nisarg, Lavle Paud Road, Andheri, Mumbai Suburban, 412115. Per the filed land record, the plot is bounded to the north by 12 and 15 mtr wide road, to the south by Adjoining Plot - Gat Nos 570 and 571, to the east by Adjoining Plot-Gat No 559 and to the west by Nova. These are the boundaries as recorded in the filed land record.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

K Raheja Corp Real Estate Private Limited is the promoter on 11 MahaRERA-registered projects, of which 4 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

See every K Raheja Corp Real Estate Private Limited project & its RERA track record →

Other flagged projects by K Raheja Corp Real Estate Private Limited

K Raheja Corp Real Estate Private Limited
FlaggedPune
K Raheja Corp Real Estate Private Limited
FlaggedPune
K Raheja Corp Real Estate Private Limited
Deregistered by MahaRERAPune
K Raheja Corp Real Estate Private Limited
FlaggedPune
K Raheja Corp Real Estate Private Limited
FlaggedPune
K Raheja Corp Real Estate Private Limited
Deregistered by MahaRERAPune

Other RERA-registered projects in Bhugaon

Manas Valley Phase II
possession by Oct 2026 · Balaji Kimaya Associates
Plot NO. B-01 TO B-21 Viva,pirangut,pune
possession by Nov 2026 · Pact Real Estate Private Limited
Frangipani, Viva, Pirangut
Deregistered by MahaRERA · possession by Nov 2026 · K Raheja Corp Real Estate Private Limite
Asmi Pride
possession by Dec 2026 · M/S Icon Developers
Madhuban
possession by Dec 2026 · NG Rathi Estate
Plumeria, Viva, Pirangut
Deregistered by MahaRERA · possession by Dec 2026 · K Raheja Corp Real Estate Private Limite

Major developers building in Bhugaon

Other RERA-registered projects in Pune

Hilltop Street 123 LCL 0029
declared completion Dec 2021 · Lavasa Corporation Ltd
Hilltop Street 124, Valley View Ct 3, 11 LCL 0030
declared completion Dec 2021 · Lavasa Corporation Ltd
Hilltop Street 93,95,99,105,107,109,111 LCL 0023
declared completion Dec 2021 · Lavasa Corporation Ltd
Hillview
declared completion Dec 2021 · Venkateshwara Builders
Hillview Residency Building D
possession by Jun 2027 · Kumar Beharay Properties LLP
Hillview Residency Building E
possession by Jun 2027 · Kumar Beharay Properties LLP

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026