MahaRERA Property Intelligence · Pune

KANVAS B BUILDING

P52100023770 · NEXT TO LEXICON INSTITITUTE · promoter Anshul Bhosale Realty

Certificate SignedDue 30 Dec 2027

Delivery & Registration

MahaRERA registrationP52100023770
Registered on03 Jan 2020
Promoter-declared completion30 Dec 2027
Current statusCertificate Signed
Against today17 months to the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Anshul Bhosale Realty is the promoter of record on 58 projects, of which 5 carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+13.

BuildingWingsFloorsDeclared completion
B1G+1331 Dec 2026

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Legal & Litigation

The promoter has declared 1 court case on this project to MahaRERA. Litigation can cloud the land title or stall the build — have a lawyer pull the cause list for each and confirm whether it touches the title to your flat. This is declared by the promoter; there may be further cases not on the RERA record.

CourtCase no.YearStatus
Civil Judge Senior Div1102013Issues

Location, Land & Connectivity

Located at NEXT TO LEXICON INSTITITUTE , NAGAR ROAD , Haveli, Pune, 412207. Per the filed land record, the plot is bounded to the north by 663, to the south by 663, to the east by 663 and to the west by 663. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~4 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Kharadi / EON IT Park4 km
Pune Int'l Airport (Lohegaon)6 km
Magarpatta / Hadapsar IT8 km
Pune Junction / city centre12 km
Baner–Balewadi belt21 km
Hinjewadi Rajiv Gandhi IT Park25 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Wagholi

Solvista Phase 1
possession by Sep 2026 · SSL Infrabuild LLP
Aurora 2
possession by Sep 2026 · Magnum Developers
Elite
possession by Sep 2026 · V & J Developers
Enliven Home B Wing Phase 2
possession by Sep 2026 · Siddhivinayak Properties
Godrej Greens
possession by Sep 2026 · Dream World Landmarks LLP
Kharadi Pune Phase I - Tower 1 To 4
possession by Oct 2026 · Lodha Developers Limited

Major developers building in Wagholi

Other RERA-registered projects in Pune

Kapil Akhila
declared completion Dec 2017 · Padmanabh Pioneer Promoters LLP
Kapil Grace
declared completion Sep 2025 · Shree Bal Properties & Finance Pvt L
Kapil Sankalp
declared completion Sep 2020 · Avadhoot Constructions
Kapila CO-Operative Housing Society
declared completion Mar 2025 · Sandip Chandrakant Shitole
Kapila Vastu
possession by Jun 2027 · Kapila Developers & Builders
Kapilashram
declared completion Dec 2019 · Ramrai Buildcon LLP

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026