Pune/Project record

MahaRERA · the public record

KP ARCHANA PARADISE PHASE 03

MOHAMADWADI · KANIFNATH PROPERTIES

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

31 Dec 2027declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Dec 2027

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52100078460

Delivery and registration

When is the project declared for completion?

KP ARCHANA PARADISE PHASE 03 is registered with MahaRERA as P52100078460 and the promoter has declared completion for 31 Dec 2027.

31 Dec 2027

declared completion

15months to go

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52100078460
Registered on12 Dec 2024
Promoter-declared completion31 Dec 2027
Current statusCertificate Signed
Against today15 months to the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for KP ARCHANA PARADISE PHASE 03 record 8 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Current QPR default — the promoter has stopped filing the mandatory quarterly progress report (FY 2025-2026).

Promoter record

What else is this promoter on record for?

Kanifnath Properties is the promoter of record on 9 projects registered with MahaRERA, none of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

9projects

registered with MahaRERA

0flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for KP ARCHANA PARADISE PHASE 03 in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+14.

BuildingWingsFloorsDeclared completion
Building-A1G+14-

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Location, Land & Connectivity

Located at MOHAMADWADI, NIBM ANNEX NEAR ARCHANA PARADISE PHASE 01 , Haveli, Pune, 411060. Per the filed land record, the plot is bounded to the north by ROAD, to the south by SR NO 39 HISSA NO 09, to the east by NALA and to the west by ROAD. These are the boundaries as recorded in the filed land record.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Kanifnath Properties is the promoter on 2 MahaRERA-registered projects, with none currently carrying a regulator flag — a reassuring wider track record (matched on the promoter name in the register; it doesn't guarantee this specific project, but a clean portfolio is a good sign).

Other RERA-registered projects in Undri

Arnav Sokande Patil Plaza
possession by Nov 2026 · Sokande Patil Prom & Developers
Raheja Sterling - Tower 3
possession by Nov 2026 · Cavalcade Properties PVT LTD
ARV Regalia
possession by Dec 2026 · Unitree India Realty LLP
Ganga Estoria C
Not filing quarterly progress reports · possession by Dec 2026 · Meenamani Real Venture LLP
Ganga Fernhill Phase 02
possession by Dec 2026 · Meenamani Ganga Builders LLP
Sukhwani Verde
possession by Dec 2026 · Sagar Gurmukh Sukhwani

Major developers building in Undri

Other RERA-registered projects in Pune

KP Heritage
possession by Dec 2026 · K P Associates
KP Supernova
possession by Dec 2029 · Kanifnath Realtors
Kpct
possession by Sep 2026 · Parmar Properties Pvt.ltd.
Kratos Tower
declared completion Aug 2025 · Apus Realties Private Limited
Kripa Heights
possession by Dec 2026 · MS Kripa Developers Through ITS Propriet
Krisanta Skyline
declared completion Jul 2018 · Krisala Developers

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026