Pune/Project record

MahaRERA · the public record

Laxmi Heights

Laxminagar · BALAJI DEVELOPERS

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 Dec 2023declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Dec 2023

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52100024348

Delivery and registration

When is the project declared for completion?

Laxmi Heights is registered with MahaRERA as P52100024348 and the promoter has declared completion for 30 Dec 2023.

30 Dec 2023

declared completion

33months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52100024348
Registered on07 Feb 2020
Promoter-declared completion30 Dec 2023
Current statusCertificate Signed
Against todayabout 33 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for Laxmi Heights record 16 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 16 quarterly progress reports on record since registration, with no current default.

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for Laxmi Heights in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+6.

BuildingWingsFloorsDeclared completion
Laxmi Heights1G+631 Dec 2022

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Location, Land & Connectivity

Located at Laxminagar, BEHIND VIIIT COLLEGE, Haveli, Pune, 411038. Per the filed land record, the plot is bounded to the north by S NO 3 HISSA NO 3 PART, to the south by S NO 3 HISSA NO 3 PART, to the east by S NO 3 HISSA NO 3 PART and to the west by EXISTING ROAD. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~102 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Hinjewadi Rajiv Gandhi IT Park102 km
Baner–Balewadi belt103 km
Pune Junction / city centre109 km
Magarpatta / Hadapsar IT113 km
Kharadi / EON IT Park117 km
Pune Int'l Airport (Lohegaon)117 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Balaji Developers is the promoter on 22 MahaRERA-registered projects, of which 5 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

See every Balaji Developers project & its RERA track record →

Other flagged projects by Balaji Developers

Balaji Developers
Past its declared completion datePune
Balaji Developers
Past its declared completion datePune

Other RERA-registered projects in Kothrud

Arunali
possession by Sep 2026 · Badhekar Properties
Guruvaibhav CO-Op.housing Society Limited
possession by Sep 2026 · Shreepad Associates
Prathamesh Co-Op Housing Soc
possession by Sep 2026 · Joshi Associates
State Bank OF India Snehdeep Chsl
possession by Sep 2026 · Kotibhaskar Infrastructures &develop
Vaibhavshree AND Indira Priyadarshani
possession by Sep 2026 · Pride Properties & Infrastructure
Yakshanagari CO Operative Housing Society LTD
possession by Sep 2026 · VSA Intezine LLP

Major developers building in Kothrud

Other RERA-registered projects in Pune

Laxmi Heights
declared completion Jun 2022 · M/S B J Hulawale Properties
Laxmi Heights
declared completion Dec 2025 · Praaj Developers
Laxmi Heights
declared completion Sep 2025 · Samruddhi Gharkul Developers
Laxmi Paradise
possession by Dec 2028 · THE Laxmi Empire
Laxmi Pride
declared completion Jun 2025 · M/S B J Hulawale Properties
Laxmi Puram
possession by Sep 2027 · Not Available

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026