Pune/Project record

MahaRERA · the public record

SAVITRI HEIGHTS

Pune · BALAJI DEVELOPERS

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

12 Dec 2023declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

12 Dec 2023

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52100013729

Delivery and registration

When is the project declared for completion?

SAVITRI HEIGHTS is registered with MahaRERA as P52100013729 and the promoter has declared completion for 12 Dec 2023.

12 Dec 2023

declared completion

33months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52100013729
Registered on25 Oct 2017
Promoter-declared completion12 Dec 2023
Current statusCertificate Signed
Against todayabout 33 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for SAVITRI HEIGHTS record 25 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 25 quarterly progress reports on record since registration, with no current default.

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for SAVITRI HEIGHTS in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+3.

BuildingWingsFloorsDeclared completion
SAVITRI HEIGHTS1G+3-

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Location, Land & Connectivity

Located at Haveli, Pune, 411028. Per the filed land record, the plot is bounded to the north by S NO 86 PART, to the south by S NO 86 PART, to the east by ROAD and to the west by S NO 86 PART. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~5 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Magarpatta / Hadapsar IT5 km
Pune Junction / city centre8 km
Kharadi / EON IT Park9 km
Pune Int'l Airport (Lohegaon)12 km
Baner–Balewadi belt18 km
Hinjewadi Rajiv Gandhi IT Park23 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Balaji Developers is the promoter on 22 MahaRERA-registered projects, of which 5 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

See every Balaji Developers project & its RERA track record →

Other flagged projects by Balaji Developers

Balaji Developers
Past its declared completion datePune
Balaji Developers
Past its declared completion datePune

Other RERA-registered projects in Hadapsar

Kumar Parc Residences - A1
possession by Nov 2026 · Kumar Properties Infratech Developers Pv
ARV Royale Phase II
possession by Dec 2026 · Vedant Properties
Amanora Crown Towers
possession by Dec 2026 · City Realty & Development Private Li
Elina Premium
possession by Dec 2026 · Binawat Realty LLP
Freedom High Street
possession by Dec 2026 · Dilip Baburao Tupe
Kohinoor Artize Wing B
possession by Dec 2026 · Shivayogi Kashinath Chikhale

Major developers building in Hadapsar

Other RERA-registered projects in Pune

Sayaji Apartment
possession by Dec 2027 · Sudit Developers
SB Sai Sanskruti
possession by Oct 2027 · S B SAI Associates
SBM Myra
declared completion Dec 2017 · SBM Properties
School Street 19, 33, Portofino Street 60 LCL 0021
declared completion Dec 2017 · Lavasa Corporation Ltd
Seeta Co-Operative Housing Society Limited
possession by Dec 2027 · D&t Properties Unit-3
Seeta-Govind
declared completion Nov 2025 · Ranade Realtors LLP

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026