MahaRERA Property Intelligence · Pune

Mayuri Optimum

P52100002131 · promoter Vinesh Naresh Kumar

Certificate SignedDue 31 Jan 2021

Delivery & Registration

MahaRERA registrationP52100002131
Registered on31 Jul 2017
Promoter-declared completion31 Jan 2021
Current statusCertificate Signed
Against todayabout 66 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+8.

BuildingWingsFloorsDeclared completion
b Wing1G+8-
A WING1G+8-
AMINITY1G+2-

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Deadline Extensions

The promoter has had the MahaRERA completion deadline formally extended 1 time. Each extension is the regulator letting the finish line move — the clearest evidence of delivery slippage, straight from the record.

From (declared)To (revised)Stated reason
31 Jan 202131 Jul 2020Work Completed 100% but we are awaiting For Fir NOC & Then Need to apply Completion Certificate.

Location, Land & Connectivity

Located at Haveli, Pune, 411028. Per the filed land record, the plot is bounded to the north by Odha, to the south by Shri Shrikant katariya, to the east by undri pisoli road and to the west by Baby shantaram Kalbhor land. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~8 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Magarpatta / Hadapsar IT8 km
Pune Junction / city centre10 km
Kharadi / EON IT Park12 km
Pune Int'l Airport (Lohegaon)15 km
Baner–Balewadi belt19 km
Hinjewadi Rajiv Gandhi IT Park24 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Hadapsar

Kumar Parc Residences - A1
possession by Nov 2026 · Kumar Properties Infratech Developers Pv
ARV Royale Phase II
possession by Dec 2026 · Vedant Properties
Amanora Crown Towers
possession by Dec 2026 · City Realty & Development Private Li
Elina Premium
possession by Dec 2026 · Binawat Realty LLP
Freedom High Street
possession by Dec 2026 · Dilip Baburao Tupe
Kohinoor Artize Wing A
possession by Dec 2026 · Shivayogi Kashinath Chikhale

Major developers building in Hadapsar

Other RERA-registered projects in Pune

Mayuri Residency
declared completion Jan 2023 · Aryan Developers
Mayuri Sunrise
declared completion Dec 2021 · V Satav Developers
Mayuri Tarangan
declared completion Jun 2022 · Aryan Engineers
Maza Gharkul
declared completion Dec 2025 · Swaraa Groups
Maza Gharkul Karegaon
declared completion Nov 2020 · Kuber Properties
MBM Developers THE West Ford Phase 1
declared completion Jun 2021 · M B M Developers

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026