OXY DESIRE

GADE VASTI · VENKATESH ASSOCIATES

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 Jun 2024declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Jun 2024

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52100002355

Delivery and registration

When is the project declared for completion?

OXY DESIRE is registered with MahaRERA as P52100002355 and the promoter has declared completion for 30 Jun 2024.

30 Jun 2024

declared completion

27months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52100002355
Registered on31 Jul 2017
Promoter-declared completion30 Jun 2024
Current statusCertificate Signed
Against todayabout 27 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for OXY DESIRE record 28 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 28 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Venkatesh Associates is the promoter of record on 161 projects registered with MahaRERA, 27 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

161projects

registered with MahaRERA

27flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for OXY DESIRE in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+13.

BuildingWingsFloorsDeclared completion
A1G+1331 Dec 2018
B1G+1331 Dec 2018

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 5 times, as recorded on the register.

FromExtended toStated reason
as registered30 Apr 2020Reason for delay which is mentioned below uploaded document
30 Apr 202030 Apr 2020LOCAL LEVEL BUILDING PERMISSION AUTHORITY PMRDA CHANGES SANCTIONING NORMS AND RULES DUE TO DELAY REVISED /FINAL SANCTION
30 Apr 202031 Dec 2021As per Extension application Number EXT52100005802 We apply for extension for 1 year i.e Dec 2019 to Dec 2020 but as per Rera Authority its Approved till 30/04/2020 then As per di
31 Dec 202130 Jun 2023Dear sir , As per Rera Authority guideline section 7(3) We are apply for extension of proposed completion date upto 30/06/2023 . Project are delay due to Covid -19 Lock
30 Jun 202330 Jun 2024Dear sir , Till date about 98 % project work are completed , Society formation also completed out of 238 tenement 223 tenement are sold only few i.e 10 tenement remaning

Location, Land & Connectivity

Located at GADE VASTI, BAKORI ROAD, Haveli, Pune, 412207. Per the filed land record, the plot is bounded to the north by GAT NO 758 AND 771 PART, to the south by GAT NO 774 PART, to the east by ROAD AND GAT NO 770 and to the west by ROAD. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~8 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Kharadi / EON IT Park8 km
Pune Int'l Airport (Lohegaon)9 km
Magarpatta / Hadapsar IT12 km
Pune Junction / city centre16 km
Baner–Balewadi belt24 km
Hinjewadi Rajiv Gandhi IT Park28 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Venkatesh Associates is the promoter on 12 MahaRERA-registered projects, of which 1 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

See every Venkatesh Associates project & its RERA track record →

Other flagged projects by Venkatesh Associates

Other RERA-registered projects in Wagholi

Aurora 2
possession by Sep 2026 · Magnum Developers
Elite
possession by Sep 2026 · V & J Developers
Enliven Home B Wing Phase 2
possession by Sep 2026 · Siddhivinayak Properties
Godrej Greens
possession by Sep 2026 · Dream World Landmarks LLP
Kharadi Pune Phase I - Tower 1 To 4
possession by Oct 2026 · Lodha Developers Limited
Defence Colony Pune Phase4
possession by Nov 2026 · Defence Colony Pune

Major developers building in Wagholi

Other RERA-registered projects in Pune

OXY Eterno
declared completion Jun 2025 · Keystone Eterno LLP
OXY Flora
declared completion Dec 2024 · Yogesh Developers
OXY Flora Phase 2
declared completion Dec 2022 · OXY Flora Phase 2
OXY Flora Phase 3
possession by Dec 2026 · Yogesh Developers
OXY Galaxy
declared completion Jun 2018 · Venkatesh Estate
Oxy Gold D
declared completion Aug 2022 · M M Developers

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.