Plotted Development Intelligence · Pune

PANCHATATVA GANESH PARK

P52100048914 · HADPSAR · promoter Panchatatva Ganesh Park

Certificate SignedDue 16 Dec 2024

Delivery & Registration

MahaRERA registrationP52100048914
Registered on24 Jan 2023
Promoter-declared completion16 Dec 2024
Current statusCertificate Signed
Against todayabout 19 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Panchatatva Ganesh Park is the promoter of record on 2 projects, of which 1 carries a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Sales & Inventory

Of 19 plots filed with MahaRERA, 0 are sold/booked and 19 remain available (~0% sold) — early in sales — more choice of units now, but confirm the developer has the pre-sales to fund the build. This is the promoter's own reported inventory as at the last compliance filing; confirm current availability directly.

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Deadline Extensions

The promoter has had the MahaRERA completion deadline formally extended 1 time. Each extension is the regulator letting the finish line move — the clearest evidence of delivery slippage, straight from the record.

From (declared)To (revised)Stated reason
31 Dec 202316 Dec 2024The project completion date was 31/12/2023. However, we received the Occupancy Certificate (OC) on 16/12/2024. Therefore, we are required to apply for a project extension before ap

Location, Land & Connectivity

Located at HADPSAR, NEAR MASTANI TALAV ROAD, Haveli, Pune, 412308. Per the filed land record, the plot is bounded to the north by BY A PROPERTY OF GAT NUMBER 498, to the south by BY A PROPERTY OF GAT NUMBER 489 AND 490, to the east by BY A PROPERTY OF GAT NUMBER 494 AND 497 and to the west by EXISTING ROAD AND GAT NUMBER 491. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~11 km away — a real but liveable commute to the nearest job hub — factor peak-hour traffic.

LandmarkStraight-line
Magarpatta / Hadapsar IT11 km
Kharadi / EON IT Park14 km
Pune Junction / city centre16 km
Pune Int'l Airport (Lohegaon)18 km
Baner–Balewadi belt26 km
Hinjewadi Rajiv Gandhi IT Park31 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Fursungi

Simplicity Phase 4 - A Wing
possession by Jul 2026 · J K P Developers Unit NO 2
Tranquility Annexe C Wing
possession by Jul 2026 · K AND B Associates
Casalino Towers Phase 3
possession by Oct 2026 · Sai Siddhi Promoters & Builders
Silver Park - B Wing
possession by Dec 2026 · Hakke AND KAD Developers
Green Hive Plus Wing A4
possession by Dec 2026 · Ram India Shelters
Sahara Platinum
possession by Dec 2026 · Sahara Buildtek

Major developers building in Fursungi

Other RERA-registered projects in Pune

Panchatatva Vitthal Park
declared completion Sep 2023 · Rupesh Vijay Kolhapure
Panchavati Nest
declared completion Apr 2021 · Panchavati Developers
Panchawati
declared completion Jan 2021 · D AND P Associates
Panchratna
possession by Jun 2027 · Chaphalkar Karandikar Developers
Panchratna Developers B Wing
declared completion Dec 2021 · Panchratna Developers
Panchratna Hills
declared completion Apr 2023 · Panchratna Associates

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026