RAVINANDA TRINITY

Wagholi · ICON LANDMARKS LLP

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 Jun 2023declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Jun 2023

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52100002848

Delivery and registration

When is the project declared for completion?

RAVINANDA TRINITY is registered with MahaRERA as P52100002848 and the promoter has declared completion for 30 Jun 2023.

30 Jun 2023

declared completion

39months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52100002848
Registered on04 Aug 2017
Promoter-declared completion30 Jun 2023
Current statusCertificate Signed
Against todayabout 39 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for RAVINANDA TRINITY record 24 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 24 quarterly progress reports on record since registration, with no current default.

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for RAVINANDA TRINITY in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+14.

BuildingWingsFloorsDeclared completion
A WING1G+1401 Jul 2022
B WING1G+1401 Jul 2022
C WING1G+1301 Jul 2022

Legal and disputes

What disputes are disclosed?

1 complaint is on the MahaRERA record for RAVINANDA TRINITY, with orders passed in 1 of them.

1complaint

1with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 12 Jul 2026

Complaint no.FiledPartiesStatus
CC00500000010644304/01/2022Mr. KIRAN SUBHASH GOSAVI vs M/s ICON LANDMARK LLPorder passed

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 1 time, as recorded on the register.

FromExtended toStated reason
as registered30 Jun 2023Covid 19 Pandemic, inflation & Partnership Issues. (Supplementary Partnership Deed Attach)

Location, Land & Connectivity

Located at Wagholi, JSPM college road, Haveli, Pune, 412207. Per the filed land record, the plot is bounded to the north by ELAN, to the south by 719 PART AND ROAD, to the east by JSPM COLLEGE and to the west by 719 PART. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~122 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Hinjewadi Rajiv Gandhi IT Park122 km
Baner–Balewadi belt127 km
Pune Junction / city centre138 km
Pune Int'l Airport (Lohegaon)138 km
Kharadi / EON IT Park142 km
Magarpatta / Hadapsar IT143 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Wagholi

Aurora 2
possession by Sep 2026 · Magnum Developers
Elite
possession by Sep 2026 · V & J Developers
Enliven Home B Wing Phase 2
possession by Sep 2026 · Siddhivinayak Properties
Godrej Greens
possession by Sep 2026 · Dream World Landmarks LLP
Kharadi Pune Phase I - Tower 1 To 4
possession by Oct 2026 · Lodha Developers Limited
Defence Colony Pune Phase4
possession by Nov 2026 · Defence Colony Pune

Major developers building in Wagholi

Other RERA-registered projects in Pune

Ravinanda37
possession by Mar 2027 · Ravinanda Icon Landmarks Unit1
Ravindu
declared completion Jul 2026 · Shubh Ventures
Raviprabha Residency
declared completion Dec 2024 · Shree Associates
Raviraj Splendour Greens
possession by Dec 2027 · Raviraj Sheth Developers LLP
Raviumang
possession by Dec 2029 · Sunil Radhakrishan Israni
Rayat Residency
possession by Sep 2026 · Soham Constructions AND Developers

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026