SAMRUDDHI PRANGAN

Pune · Samruddhi Associates

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

31 May 2020declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 May 2020

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52100014304

Delivery and registration

When is the project declared for completion?

SAMRUDDHI PRANGAN is registered with MahaRERA as P52100014304 and the promoter has declared completion for 31 May 2020.

31 May 2020

declared completion

76months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52100014304
Registered on20 Nov 2017
Promoter-declared completion31 May 2020
Current statusCertificate Signed
Against todayabout 76 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for SAMRUDDHI PRANGAN record 11 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 11 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Samruddhi Associates is the promoter of record on 100 projects registered with MahaRERA, 16 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

100projects

registered with MahaRERA

16flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for SAMRUDDHI PRANGAN in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+5.

BuildingWingsFloorsDeclared completion
SAMRUDDHI PRANGAN1G+531 May 2019

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 1 time, as recorded on the register.

FromExtended toStated reason
as registered31 May 2020We Samruddhi Associates are developing a residential project Samruddhi Prangan, having Plot Bearing / CTS / Survey / Final Plot No.: 14/2/1 at Sus, Mulshi, Pune, 411021 and we were

Location, Land & Connectivity

Located at Haveli, Pune, 411021. Per the filed land record, the plot is bounded to the north by SURVEY NO 14, to the south by SURVEY NO 14, to the east by ROAD and to the west by SURVEY NO 14. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~1 km away — walking/short-hop distance to a major employment hub — a genuine work-near-home location.

LandmarkStraight-line
Baner–Balewadi belt1 km
Hinjewadi Rajiv Gandhi IT Park6 km
Pune Junction / city centre11 km
Pune Int'l Airport (Lohegaon)16 km
Magarpatta / Hadapsar IT17 km
Kharadi / EON IT Park18 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Samruddhi Associates is the promoter on 2 MahaRERA-registered projects, of which 1 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

Other RERA-registered projects in Bavdhan

Purva Aspire
possession by Sep 2026 · Puravankara Limited
Marvel Selva Ridge Villa 6, 9, 11, 12
Developer in insolvency (NCLT) · possession by Dec 2026 · Marvel Omega Builders PVT LTD
Reelicon Fairy Bell
possession by Dec 2026 · Reelicon Red Homes Private Limited
Green Mint
possession by Dec 2026 · Sunil Vishwanath Salunke
Neelanchal Phase I
Not filing quarterly progress reports · possession by Dec 2026 · Pinnacle Vastunirman Pvt. Ltd
Neelanchal Phase II
possession by Dec 2026 · Pinnacle Vastunirman Pvt. Ltd

Major developers building in Bavdhan

Other RERA-registered projects in Pune

Samruddhi Prime
declared completion Jul 2024 · Namrata Sandeep Landge
Samruddhi Residency
possession by Mar 2031 · Navnath Properties
Samruddhi Rise
possession by Dec 2029 · Samruddhee Constructions
Samruddhi Rutugandh
declared completion Dec 2022 · Samruddhi Promoters
Samruddhi Serenity
possession by Mar 2029 · Crystal Reality
Samruddhi Sneh
declared completion Nov 2024 · Samruddhi Landmarks

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026