Pune/Project record

MahaRERA · the public record

SKKY VILLAS PHASE II

GAT NUMBER 1421 AND 1422 WAGHOLI · SAMEER DATTATRAY BHADALE

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 Jun 2022declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Jun 2022

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52100026038

Delivery and registration

When is the project declared for completion?

SKKY VILLAS PHASE II is registered with MahaRERA as P52100026038 and the promoter has declared completion for 30 Jun 2022.

30 Jun 2022

declared completion

51months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52100026038
Registered on11 Aug 2020
Promoter-declared completion30 Jun 2022
Current statusCertificate Signed
Against todayabout 51 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for SKKY VILLAS PHASE II record 8 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Filing progress reports — 8 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Sameer Dattatray Bhadale is the promoter of record on 110 projects registered with MahaRERA, 30 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

110projects

registered with MahaRERA

30flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

How much has actually been sold?

In SKKY VILLAS PHASE II, 17 of 18 plots filed with MahaRERA are recorded as sold or booked, about 94%, and 1 remain available.

94%sold

17 of 18 plots

Counts as the promoter filed them at the last compliance date; this is the filed inventory, not current availability.

Source · MahaRERA sold/unsold inventory filing · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for SKKY VILLAS PHASE II in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Location, Land & Connectivity

Located at GAT NUMBER 1421 AND 1422 WAGHOLI, OPPOSITE TO MARVEL FRIA , Haveli, Pune, 412207. Per the filed land record, the plot is bounded to the north by GAT NUMBER 1424 PART, to the south by 12 METER ROAD AND GAT NUMBER 1402 PART, to the east by GAT NUMBER 1421 PART AND 1422 PART and to the west by REMAINING PART OF GAT NUMBER 1421 AND 1422. These are the boundaries as recorded in the filed land record.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Wagholi

Aurora 2
possession by Sep 2026 · Magnum Developers
Elite
possession by Sep 2026 · V & J Developers
Enliven Home B Wing Phase 2
possession by Sep 2026 · Siddhivinayak Properties
Godrej Greens
possession by Sep 2026 · Dream World Landmarks LLP
Kharadi Pune Phase I - Tower 1 To 4
possession by Oct 2026 · Lodha Developers Limited
Defence Colony Pune Phase4
possession by Nov 2026 · Defence Colony Pune

Major developers building in Wagholi

Other RERA-registered projects in Pune

Skky Villas Phase III
declared completion Dec 2021 · Aditya Pride Realty
Sky 2 Cosmos
possession by Oct 2026 · Emperos Properties
Sky Bhumi
declared completion Mar 2025 · Sky Bhumi
SKY Blue
possession by Oct 2026 · Royal Realty
SKY County
possession by Dec 2027 · Deshmukh Developments
SKY Crest
declared completion Jun 2026 · Rahul Properties

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026