MahaRERA Property Intelligence · Pune

Yes Residency

P52100010630 · Hadapsar · promoter Yemul Sancheti Associates

Certificate SignedDue 30 Jun 2024

Delivery & Registration

MahaRERA registrationP52100010630
Registered on31 Aug 2017
Promoter-declared completion30 Jun 2024
Current statusCertificate Signed
Against todayabout 25 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Yemul Sancheti Associates is the promoter of record on 17 projects, of which none currently carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+12.

BuildingWingsFloorsDeclared completion
Yes Residency1G+1230 Jun 2022

Complaints & Orders

2 complaints are on the MahaRERA record for this project, with orders passed in 2. An adjudicated complaint is the clearest evidence of how this promoter behaves when pushed — read the orders in full.

Complaint no.FiledPartiesStatus
CC00500000002292318/04/2019MANJUSHA BHUSARI vs YEMUL AND SANCHETI ASSOCIATESorder passed
CC00500000005391210/01/2020ASHA GANGURDE vs YEMUL AND SANCHETI ASSOCIATESorder passed

Legal & Litigation

The promoter has declared 1 court case on this project to MahaRERA. Litigation can cloud the land title or stall the build — have a lawyer pull the cause list for each and confirm whether it touches the title to your flat. This is declared by the promoter; there may be further cases not on the RERA record.

CourtCase no.YearStatus
Special5862017On Going

Deadline Extensions

The promoter has had the MahaRERA completion deadline formally extended 4 times. Each extension is the regulator letting the finish line move — the clearest evidence of delivery slippage, straight from the record.

From (declared)To (revised)Stated reason
30 Jun 202430 Jun 2024Due to the Revised building plans and TDR related issues
30 Jun 202430 Jun 2021At the time of registration of project with MahaRERA, we had planned for the finance from own contribution/ construction finance. However, we could not arrange the funds from finan
30 Jun 202430 Jun 2021At the time of registration of the project with MAHARERA, we had planned for the finance form own contribution/ construction finance. However, we could not arrange funds form finan
30 Jun 202430 Jun 2023Work on the project was halted due to COVID-19 & Also funds are not received from the customers.

Location, Land & Connectivity

Located at Hadapsar, Hadapsar, Pune City, Pune, 411028. Per the filed land record, the plot is bounded to the north by Road, to the south by S No 84 21 And 84 27, to the east by S No 84 15 and to the west by S No 84 24 And84 12. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~2 km away — walking/short-hop distance to a major employment hub — a genuine work-near-home location.

LandmarkStraight-line
Magarpatta / Hadapsar IT2 km
Kharadi / EON IT Park6 km
Pune Junction / city centre7 km
Pune Int'l Airport (Lohegaon)9 km
Baner–Balewadi belt17 km
Hinjewadi Rajiv Gandhi IT Park23 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Yemul& Sancheti Associates is the promoter on 2 MahaRERA-registered projects, with none currently carrying a regulator flag — a reassuring wider track record (matched on the promoter name in the register; it doesn't guarantee this specific project, but a clean portfolio is a good sign).

Other flagged projects by Yemul& Sancheti Associates

Yemul& Sancheti Associates
FlaggedPune

Other RERA-registered projects in Hadapsar

Kumar Parc Residences - A1
possession by Nov 2026 · Kumar Properties Infratech Developers Pv
ARV Royale Phase II
possession by Dec 2026 · Vedant Properties
Amanora Crown Towers
possession by Dec 2026 · City Realty & Development Private Li
Elina Premium
possession by Dec 2026 · Binawat Realty LLP
Freedom High Street
possession by Dec 2026 · Dilip Baburao Tupe
Kohinoor Artize Wing A
possession by Dec 2026 · Shivayogi Kashinath Chikhale

Major developers building in Hadapsar

Other RERA-registered projects in Pune

Yesai Park
possession by Oct 2027 · Siddhivinayak Developers
Yin Yang
declared completion Dec 2020 · Proxima Creations
Yog Mudra
possession by Jun 2027 · Pawan Enterprises Through Madhukar Datta
Yog Sahakari Griha Rachna Sanstha Maryadit
declared completion Dec 2025 · Yog Sahakari Griha Rachana Sanstha Marya
Yogamrut
possession by Aug 2026 · Jay Ganesh Buildcon
Yoganand Park 2
declared completion Dec 2025 · Belvalkar Housing LLP

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026