Bangalore/Project record

K-RERA · the public record

Assetz 66 & Shibui

Bengaluru East · APG ENVIRONMENT HOMES

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

70%construction reportedQ1 2026 filing
27units not bookedof 102 · Q1 2026 filing
30 Jun 2028declared completionK-RERA registration · read 20 Sep 2026

The record · free to read

Registration read 20 Sep 2026

Progress & dates

The timeline on file.

Promoter-reported construction

K-RERA quarterly filings · Q3 2025 to Q1 2026

declared completion

30 Jun 2028

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

K-RERA registration · read 20 Sep 2026

Inventory & scale

What this registration contains.

3BHK
48
4BHK
48

Filed categories, unchanged · K-RERA registration · read 20 Sep 2026

The whole registration

1.8registered acres

55.9registered units per acre

The average covers the registered land and all registered unit types. It does not describe the space, outlook or surroundings of an individual home.

From another project · Prestige Park Grove

A larger advertised area. Almost the same carpet area.

In Tower 14, E4 has 141 sq ft more saleable area than E2. Its carpet area is only 0.46 sq m larger. The report puts the two layouts side by side.

This illustrates the report format. These findings concern the named sample, not this project.

Read the sample report ↗
Prestige Park Grove · Tower 14 comparison · approved sample report
Prestige Park Grove · Tower 14 comparison · approved sample report

The source record

The details behind the headline.

K-RERA · PRM/KA/RERA/1251/446/PR/300124/006601

This project, on the record

The comparable facts of this project, from its own RERA registration record. Each context percentile names its exact comparison set, drawn from Quietlist’s full register store. The paid report adds drawing-read rows to this same table — what the filed plans show about the site, its edges and the unit layouts.

On the register

Declared completion30 June 2028
Land area7,385 sq m (1.8 acres)
Homes registered102
Tower/wing entries1
Unit mix48 × 3BHK, 48 × 4BHK

In context

Density55.9 homes per acre
Density in context23rd percentile of 1119 Bengaluru East projects (median 75.5)

Values as crawled from the official K-RERA record; context percentiles name their comparison population.

Official Registry Facts

Official project scale

RERA filing

Registration-form facts from the K-RERA detail page: use these to sanity-check the builder brochure, parking allotment, and sanctioned-plan references before relying on plan-extracted approximations.

DisclosureOfficial valueWhy it matters
Registered units102Total inventory registered with K-RERA.
Official carpet area15,219 sqmRegulator-disclosed project-level carpet area, not vision-derived room sums.
Official built-up area32,866 sqmUseful scale context when comparing density and project cost.
Registered land area7,385 sqmThe land area attached to this K-RERA registration.
Sanctioned FAR/FSI3Higher FAR generally means a denser vertical build, subject to site layout and open-space design.
Registered tower/wing entries1Official tower/wing count in the K-RERA detail page.
Parking total (reconciled)177Separate filed counts; these categories may overlap and are not added together.
Covered-parking field177Separate filed counts; these categories may overlap and are not added together.
Open-parking field0Separate filed counts; these categories may overlap and are not added together.
Garage field0Separate filed counts; these categories may overlap and are not added together.
Approved plan number0000Use this to match the sanctioned drawing set shown by the builder.
Plan approval date08-01-2024
Project start date01-01-2024

Official inventory & towers

RERA filing

K-RERA registration tables showing the project mix and tower/wing scale. Use this to sanity-check sales claims such as "only large homes", "low density", or "plenty of parking" against the filed inventory.

Registered inventory mix

TypeUnitsShareOfficial carpet area
3BHK4850%6,189 sqm
4BHK4850%9,029 sqm

Registered tower / wing summary

Tower/wingFloorsUnitsParkingHeight
Tower A13102177-

Official unit register

RERA filing

K-RERA detail-page flat rows: exact unit numbers, official carpet area, UDS, and parking lots. 102 official flat/unit rows, matching the 102 registered units disclosed above. Use this as a checklist against the specific flat number in your cost sheet and draft agreement.

By unit type

Unit typeRowsCarpet areaUDSParking lots
4 BHK52187.9-215.6 sqm80.8-94.5 sqm52
3 BHK50128.9 sqm57.2 sqm50

By tower / wing

Tower/wingRowsCarpet areaUDSParking lots
Tower A102128.9-215.6 sqm57.2-94.5 sqm102
Show sample official unit rows
UnitTowerFloorTypeCarpetUDSParking
A011Tower A13 BHK128.9 sqm57.2 sqm1
A012Tower A14 BHK187.9 sqm80.8 sqm1
A013Tower A14 BHK187.9 sqm80.8 sqm1
A014Tower A13 BHK128.9 sqm57.2 sqm1
A015Tower A13 BHK128.9 sqm57.2 sqm1
A016Tower A14 BHK187.9 sqm80.8 sqm1

Legal, Approvals & Project Team

Litigation & compliance

RERA filing

No litigation declared on this project's K-RERA filing.

All 44 standard compliance document slots have usable uploaded filings.

No completion certificate (OC) on file yet — project has not been declared complete.

Named utility/regulatory approvals

Electricity (BESCOM/ESCOM)✓ On file (Electricity Permission Letter)
Water & sewage (BWSSB/KWSSB)✓ On file (Water Permission Letter)
Fire NOC✓ On file (Fire Force Department)
Pollution control (KSPCB)✓ On file (KSPCB)
Environmental clearance✓ On file (SEIAA)
Airport Authority height clearance✓ On file (Airport Authority of India)

"Not found in catalog" can mean the approval genuinely isn't on file yet, or that it doesn't apply to this project (K-RERA doesn't tell us which). Ask the builder directly for any marked not found before relying on it.

K-RERA enforcement record (the regulator's own defaulter list & penalty orders)

1 K-RERA order on this project (PROJECT MODIFICATION) — read the order copies on the K-RERA portal.

Statutory approval status

RERA filing

Clean approvals profile: every applicable statutory NOC is on file — including Fire NOC, environmental clearance and pollution-control clearance (KSPCB), the clearances buyers most often find still pending. Nothing is outstanding among the statutory NOCs — which compliance documents are filed versus still under process is a separate matter, covered in Litigation & compliance above. Since these are developer-filed portal statuses, have your lawyer confirm them against the linked NOC copies.

3 further authority slots are marked not applicable by the regulator.

Authority / NOCStatusDateFile
Water supply and sewage boardApproved21-08-2023BWSSB NOC 21 08 2023.pdf
KSPCB- PCB (10 Acres to 125 Acres)Approved26-06-2023KSPCB NOC 26 06 2023.pdf
KSPCB- MOEF (Above 50 Acres)Approved22-06-2023MOEF NOC 22 06 2023.pdf
KPTCL- BESCOMApproved19-07-2023Bescom NOC 19 07 2023.pdf
Fire and SafetyApproved22-08-2023FIRE NOC 22 08 2023.pdf
Airport Authority of IndiaApproved25-09-2023AAI NOC 25 09 2023.pdf
BSNL/Telecommunication DepartmentApproved01-08-2023BSNL NOC 01 08 2023.pdf

Project team & certifications

RERA filing

K-RERA names 4 project professional/vendor rows across Chartered accountant, Engineer, Architect, Contractor. Use this to cross-check whose certificates, drawings, and contractor commitments support the filing; final reliance still belongs with your lawyer/technical reviewer.

RoleNameRegistration / licenceSinceLocality
Chartered accountantY S Shetty & Company006308S2009Bengaluru Urban, Karnataka - 560010
EngineerB E PruthvirajaBCCL/BL-3.6/ SE-0061/2021-20222008Bengaluru Urban, Karnataka - 560083
ArchitectAr. Meghna SrivastavaCA/99/240432011Bengaluru Urban, Karnataka - 560032
ContractorKK CIVIL CONTRACTOR-2000Bengaluru Urban, Karnataka - 560040

Financials & Construction Progress

Financial disclosures

RERA filing

Latest quarterly filing (2026-Q1): ₹24.34 Cr collected from buyers, ₹20.07 Cr withdrawn from the project's escrow account.

Construction progress66% → 70% (+4 pts)
Units sold/booked as registered75/102 (74%)
Buyer collections in available QPRs₹73.35 Cr
Escrow withdrawals in available QPRs₹49.49 Cr (0.67x collections)
  • Construction progress moved from 66% to 70% across the filed QPR window.
  • The builder has drawn 0.67x of buyer collections from escrow (about 67% of the ₹73 Cr collected) — money is largely staying in the regulated escrow account rather than being pulled out ahead of spend, which is the safer direction. A ratio near or above 1.0 would be the one to scrutinise.

QPR figures are developer-filed quarterly disclosures. Collections and withdrawals are not a project valuation; they are a sanity check for whether sales, construction progress, and escrow draws appear directionally aligned.

Declared construction cost ÷ registered units averages to ₹95.9 lakhs per unit — the developer's own declared construction/development cost, not a sale price. K-RERA filings don't disclose what the builder is charging, so this can't tell you whether you're getting a fair deal — only you comparing your quoted price against comparable listings nearby can answer that.

RERA 70% project account is on file: ICICI Bank Kumara Park,Bangalore IFSC Code : ICIC0006253 Pin Code : 560001. RERA requires 70% of buyer collections to sit in this separate, project-specific account, drawn only against certified construction milestones — confirm your payments are made to THIS account (not a general builder account) and that it appears on your allotment letter.

Location & Connectivity

The nearest major job hub is ~0 km away — walking/short-hop distance to a major employment hub — a genuine work-near-home location.

LandmarkStraight-line
Whitefield IT hub0 km
Bellandur–Marathahalli belt8 km
MG Road / city centre16 km
Outer Ring Road / Manyata16 km
Electronic City17 km
Kempegowda Int'l Airport26 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Built by Apg Environment.

Other RERA-registered projects in Whitefield

Major developers building in Whitefield

Figures are the developer's own quarterly disclosures on the Karnataka RERA register. "Built" is the highest construction % filed; "sold" is booked units over total. Not a claim about the developer's intent. Explore every project on our Bangalore project-health tool.

Own a unit in Assetz 66 & Shibui?

Sell directly to Quietlist's pre-screened buyer list — flat fee, no broker commission.

List your unit →

Last checked against the RERA register: 20 Sep 2026