Bangalore/Project record

K-RERA · the public record

Casagrand Florella

Anekal · Casa Grande Garden City Builders

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

09 Mar 2022declared completionK-RERA registration · read 20 Sep 2026
36registered unitsK-RERA registration · read 20 Sep 2026

The record · free to read

Registration read 20 Sep 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

09 Mar 2022

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

K-RERA registration · read 20 Sep 2026

Inventory & scale

What this registration contains.

3 BHK
31

Filed categories, unchanged · K-RERA registration · read 20 Sep 2026

The whole registration

1.7registered acres

20.9registered units per acre

The average covers the registered land and all registered unit types. It does not describe the space, outlook or surroundings of an individual home.

From another project · Prestige Park Grove

A larger advertised area. Almost the same carpet area.

In Tower 14, E4 has 141 sq ft more saleable area than E2. Its carpet area is only 0.46 sq m larger. The report puts the two layouts side by side.

This illustrates the report format. These findings concern the named sample, not this project.

Read the sample report ↗
Prestige Park Grove · Tower 14 comparison · approved sample report
Prestige Park Grove · Tower 14 comparison · approved sample report

The source record

The details behind the headline.

K-RERA · PRM/KA/RERA/1251/308/PR/210319/004044

This project, on the record

The comparable facts of this project, from its own RERA registration record. Each context percentile names its exact comparison set, drawn from Quietlist’s full register store. The paid report adds drawing-read rows to this same table — what the filed plans show about the site, its edges and the unit layouts.

On the register

Declared completion9 March 2022
Land area6,980 sq m (1.7 acres)
Homes registered36
Tower/wing entries3
Unit mix31 × 3 BHK

In context

Density20.9 homes per acre
Density in context13th percentile of 471 Anekal projects (median 75.8)

Values as crawled from the official K-RERA record; context percentiles name their comparison population.

Official Registry Facts

Official project scale

RERA filing

Registration-form facts from the K-RERA detail page: use these to sanity-check the builder brochure, parking allotment, and sanctioned-plan references before relying on plan-extracted approximations.

DisclosureOfficial valueWhy it matters
Registered units36Total inventory registered with K-RERA.
Official carpet area106 sqmRegulator-disclosed project-level carpet area, not vision-derived room sums.
Registered land area6,980 sqmThe land area attached to this K-RERA registration.
Sanctioned FAR/FSI1.75Higher FAR generally means a denser vertical build, subject to site layout and open-space design.
Registered tower/wing entries3Official tower/wing count in the K-RERA detail page.
Parking total (reconciled)36Separate filed counts; these categories may overlap and are not added together.
Open-parking field4Separate filed counts; these categories may overlap and are not added together.
Garage field0Separate filed counts; these categories may overlap and are not added together.
Project start date15-03-2021

Official inventory & towers

RERA filing

K-RERA registration tables showing the project mix and tower/wing scale. Use this to sanity-check sales claims such as "only large homes", "low density", or "plenty of parking" against the filed inventory.

Registered inventory mix

TypeUnitsShareOfficial carpet area
3 BHK31100%106 sqm

Registered tower / wing summary

Tower/wingFloorsUnitsParkingHeight
Block 121111-
Block 222020-
Block 3355-

Official unit register

RERA filing

K-RERA detail-page flat rows: exact unit numbers, official carpet area, UDS, and parking lots. 35 official flat/unit rows vs 36 registered units disclosed above; ask why the row count differs. Use this as a checklist against the specific flat number in your cost sheet and draft agreement.

By unit type

Unit typeRowsCarpet areaUDSParking lots
3BHK3048.0 sqm41.8-457.3 sqm30
4BHK545.4-48.0 sqm48.5-50.8 sqm5

By tower / wing

Tower/wingRowsCarpet areaUDSParking lots
Block 21948.0 sqm41.8-44.1 sqm19
Block 11148.0 sqm450.4-457.3 sqm11
Block 3545.4-48.0 sqm48.5-50.8 sqm5
Show sample official unit rows
UnitTowerFloorTypeCarpetUDSParking
1Block 103BHK48.0 sqm450.4 sqm1
2Block 103BHK48.0 sqm457.3 sqm1
3Block 103BHK48.0 sqm457.3 sqm1
4Block 103BHK48.0 sqm457.3 sqm1
5Block 103BHK48.0 sqm457.3 sqm1
6Block 103BHK48.0 sqm457.3 sqm1

Legal, Approvals & Project Team

Litigation & compliance

RERA filing

No litigation declared on this project's K-RERA filing.

⚠ 2 of 23 compliance document slots are filed as under process / not yet usable: Performa of Allotment Letter, Brochure of Current Project.

2 additional compliance slots are filed as Not Applicable.

No completion certificate (OC) on file yet — project has not been declared complete.

⚠ Registration validity has lapsed: originally due 09 Mar 2022, extended (Section 6 Extension) to 09 Mar 2023 — both dates have passed with no OC on file. The extension on file was granted on 19 Aug 2022 (K-RERA extension no. EX/PRM/KA/RERA/1251/308/PR/220819/004044) — it has been used, its deadline has also passed, and no further extension is recorded.

Named utility/regulatory approvals

Electricity (BESCOM/ESCOM)✓ On file (BESCOM)
Water & sewage (BWSSB/KWSSB)✓ On file (BWSSB)
Fire NOCNot found in catalog
Pollution control (KSPCB)✓ On file (KSPCB)
Environmental clearanceNot found in catalog
Airport Authority height clearanceNot found in catalog

"Not found in catalog" can mean the approval genuinely isn't on file yet, or that it doesn't apply to this project (K-RERA doesn't tell us which). Ask the builder directly for any marked not found before relying on it.

K-RERA enforcement record (the regulator's own defaulter list & penalty orders)

⚠ Listed on K-RERA's official DEFAULTER list.

K-RERA complaint orders (2 complaints against a project of this name on K-RERA's orders register)

PartiesRelief soughtDisposalOrder date
BIKALKUMAR K. JHA vs M/S CASA GRANDE GARDEN CITY BUILDERS PRIVATE LIMITEDIt would be a great help if RERA team can push builder and get us the unit and the compensation for all the delay causedAUTHORITY27/11/2023
PRAVEEN SREEKUMARAN NAIR vs CASA GRANDE GARDEN CITY BUILDERS PVT LTD1. Builder to deliver what's advertised and mentioned in the sale agreement 2. Builder to compensate for the land that used for the common amenities which was not mentioned in the sale agreementAUTHORITY21/03/2023

⚠ Matched by PROJECT NAME (the orders register carries no registration number) — confirm the respondent above is this project's builder before relying on it.

Complaints on this project's K-RERA page (8 complaints listed against this promoter)

ComplaintSubject (as filed)ProjectStatus
CMP/200816/0006368
16-08-2020
Delay in Handover of Apartment C204 - CASAGRAND ROYCE ProjectCasagrand Royce (another project by this promoter)DISPOSED AUTHORITY BENCH4
CMP/211201/0008654
01-12-2021
DELAYED COMPLETION BREACH OF TRUST FINANCIAL LOSSES SUFFERED BY COMPLAINANTSCasagrand Royce (another project by this promoter)DISPOSED AUTHORITY BENCH4
CMP/220321/0009178
21-03-2022
Builder refuses to pay interset for the amount refunded after 4 yearsCasagrand Royce (another project by this promoter)DISPOSED AUTHORITY BENCH5
CMP/220616/0009641
16-06-2022
Delay In hand over which was expected to be done by 9th of March 2022Casagrand FlorellaDISPOSED AUTHORITY BENCH4
CMP/220706/0009722
06-07-2022
Builder not refunding the booking amount due to unavailability of the unitCasagrand Florella Phase 2 (another project by this promoter)DISPOSED AUTHORITY BENCH4
CMP/221104/0010175
04-11-2022
Builder not delivering the apartment flat C306 to date even after the expiry of the RERA Extended due date (15th July 2022) and denied to pay delay compensationCasa Grande Lorenza (another project by this promoter)DISPOSED AUTHORITY BENCH5
CMP/221107/0010222
07-11-2022
Builder not delivering the apartment flat C306 to date even after the expiry of the RERA Extended due date (15th July 2022) and denied to pay delay compensationCasa Grande Lorenza (another project by this promoter)DISPOSED AUTHORITY BENCH5
CMP/221221/0010496
21-12-2022
Builder not adhering to the agreed and adding new clause in the sale deedCasagrand FlorellaDISPOSED AUTHORITY BENCH5

Listed on the project's own K-RERA detail page (registration-exact source). Rows on the promoter's other projects are track-record context — read the subject text, it is the complainant's own filed wording.

Project team & certifications

RERA filing

K-RERA names 3 project professional/vendor rows across Architect, Contractor, Structural engineer. Use this to cross-check whose certificates, drawings, and contractor commitments support the filing; final reliance still belongs with your lawyer/technical reviewer.

RoleNameRegistration / licenceSinceLocality
ArchitectPraveen-2014JP nagar 2nd phase, Bengaluru
ContractorCasagrand-2015Ulsoor Road, Bengaluru
Structural engineerSuresh---

Builder track record

RERA filing

Casagrand has 20 other K-RERA-registered projects in our records — grouped across the several project-specific entities this developer registers under (e.g. this project is filed as “Casa Grande”) (average reported construction progress 41%). 11 are past their declared completion deadline with no completion certificate recorded — but because K-RERA publishes OCs inconsistently, a project that has actually been finished and handed over still shows up this way, so this overstates real delays, especially for a high-volume established builder.

Read this as a list to spot-check for a pattern of genuinely stalled projects, not as a delay rate — pull up a few of the builder’s other K-RERA registrations and check whether they’ve actually been delivered.

Financials & Construction Progress

Financial disclosures

RERA filing

⚠ No quarterly financial disclosures (collections, escrow withdrawals) on record, despite no completion certificate yet — meaning we can't verify the project's cashflows against its construction progress. Worth asking the builder directly why no quarterly filings are available.

Declared construction cost ÷ registered units averages to ₹32.2 lakhs per unit — the developer's own declared construction/development cost, not a sale price. K-RERA filings don't disclose what the builder is charging, so this can't tell you whether you're getting a fair deal — only you comparing your quoted price against comparable listings nearby can answer that.

RERA 70% project account is on file: ICICI Bank ULSOOR ROAD (IFSC ICIC0003904, a/c …1226). RERA requires 70% of buyer collections to sit in this separate, project-specific account, drawn only against certified construction milestones — confirm your payments are made to THIS account (not a general builder account) and that it appears on your allotment letter.

Construction photo filings

RERA filing

K-RERA has 1 project-photo upload.

These are developer-uploaded progress photos in the official document catalog. We do not treat them as proof of current site condition; use them as a prompt to ask for newer dated photos or a site visit. Individual filings are listed in the document catalog below.

Location & Connectivity

The nearest major job hub is ~13 km away — a real but liveable commute to the nearest job hub — factor peak-hour traffic.

LandmarkStraight-line
Electronic City13 km
Bellandur–Marathahalli belt15 km
Whitefield IT hub16 km
MG Road / city centre25 km
Outer Ring Road / Manyata29 km
Kempegowda Int'l Airport42 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Built by Casa Grande. View Casa Grande's full track record →
Casa Grande has 20 projects registered in Bangalore, 3 past RERA deadline.

Other projects by this builder in Bangalore

Casagrand Flamingo
Past deadline · 68% built · 100% sold
Casagrand Zaiden
Past deadline · 65% built · 100% sold
Casagrand Meridian
Past deadline · 80% built · 100% sold
Casagrand Amor
On track · 40% built · 70% sold
Casagrand Estancia
On track · 5% built · 64% sold

Other RERA-registered projects in Sarjapura

Major developers building in Sarjapura

Figures are the developer's own quarterly disclosures on the Karnataka RERA register. "Built" is the highest construction % filed; "sold" is booked units over total. Not a claim about the developer's intent. Explore every project on our Bangalore project-health tool.

Own a unit in Casagrand Florella?

Sell directly to Quietlist's pre-screened buyer list — flat fee, no broker commission.

List your unit →

Last checked against the RERA register: 20 Sep 2026